Contractor dossier
75 projects on file, including joint ventures this contractor is part of.
Total projects
75
Total budget
₱7.6B
Average progress
96.9%
Completion rate
90.7%
Average risk score
55.8
Medium risk on average, out of 100
Flagged as unusual
4
5.3% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region I | 35 | ₱2.9B | 55.6 | 3 | 93.6% |
| Region III | 24 | ₱2.5B | 53.5 | 1 | 99.7% |
| Cordillera Administrative Region | 16 | ₱2.1B | 59.7 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 30 | ₱3.8B | 54.2 | 1 | 99.1% |
| Flood Control and Drainage | 20 | ₱1.7B | 55.3 | 0 | 95.0% |
| Bridges | 15 | ₱1.4B | 55.0 | 1 | 96.7% |
| OTHER | 6 | ₱398.4M | 76.4 | 2 | 98.0% |
| Buildings and Facilities | 3 | ₱154.4M | 37.1 | 0 | 85.1% |
| Bridges, Roads | 1 | ₱144.8M | 60.9 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24AH0199CONSTRUCTION OF RIVERBANK PROTECTION ALONG SINUCALAN RIVER, BRGY.LASIP CHICO,DAGUPAN CITY, PANGASINA | Region I | Pangasinan 2nd DEO | On-Going | ₱46.8M | 94% | High risk86 | Flagged0.046 |
| 24CN0222CONSTRUCTION OF BIRTHPLACE OF PHILIPPINE SURFING MARKER AND BAYWALK BALER, AURORA | Region III | Aurora DEO | On-Going | ₱144.8M | 94% | High risk80 | Flagged0.006 |
| 24CN0191CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY SABANG, BALER, AURORA | Region III | Aurora DEO | Completed | ₱96.5M | 100% | High risk76 | —-0.047 |
| 24A00293CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION OF RIVERBANK PROTECTION ALONG SINUCALAN RIVER, BRGY. LASIP CHICO, DAGUPAN CITY, PANGASINAN | Region I | Region I | Completed | ₱96.5M | 100% | High risk76 | —-0.030 |
| 20PI0078CHICO KARAYAN BRIDGE-LANAO-TIKITIK BYPASS ROAD, PACKAGE B, MOUNTAIN PROVINCE | Cordillera Administrative Region | Mountain Province 1st DEO | Completed | ₱57.3M | 100% | High risk74 | —-0.022 |
| 21PI0083CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, CHICO KARAYAN BRIDGE - LANAO - TIKITIK BYPASS ROAD, PACKAGE C, MOUNTAIN PROVINCE | Cordillera Administrative Region | Mountain Province 1st DEO | Completed | ₱55.8M | 100% | High risk74 | —-0.023 |
| 20PI0077CHICO KARAYAN BRIDGE-LANAO-TIKITIK BYPASS ROAD, PACKAGE A, MOUNTAIN PROVINCE | Cordillera Administrative Region | Mountain Province 1st DEO | Completed | ₱49M | 100% | High risk73 | —-0.023 |
| 22CN0029REHABILITATION OF DUONGAN RIVER CONTROL, BALER, AURORA | Region III | Aurora DEO | Completed | ₱90.9M | 100% | High risk72 | —-0.048 |
| 20AH0054CONST'N./IMPROVEMENT OF ACCESS ROAD LEADING TO THE ANGALACAN RIVER ECOTOURISM PARK MANGALDAN,PANGASI | Region I | Pangasinan 2nd DEO | Completed | ₱44.8M | 100% | High risk72 | —-0.028 |
| 22CN0031CONSTRUCTION OF MALUPA-DIAN-AGUANG RIVER CONTROL, MA. AURORA, AURORA | Region III | Aurora DEO | Completed | ₱90.3M | 100% | High risk72 | —-0.048 |
| 17CN0040REHABILITATION/RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE ALONG NUEVA ECIJA - AURORA ROAD K0202+700-K0202+950; K0201+300-K0202+000; K0199+300-K0199+400; K0191+-100-K0191+000; K0190+000-K0190+150; K0188+1018-K0188+1033; ETC | Region III | Aurora DEO | Completed | ₱69.8M | 100% | High risk71 | —-0.063 |
| 17A00009NETWORK DEVELOPMENT, IMPROVEMENT/WIDENING OF NATIONAL ROADS-PRIMARY ROADS - OTHER PRIMARY ROADS, BAKIT-BAKIT JUNCTION- UMINGAN ROAD, PANGASINAN KO177+(-157)-KO178+300,KO180+000-KO180+411,KO186+025-KO187+000,KO187+000-KO188+550, KO189+821-KO191+000, KO192+ | Region I | Region I | Completed | ₱154.4M | 100% | High risk69 | —-0.033 |
| 16AD0177CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS: CONSTRUCTION OF GROUNDSILL OF KATKATENG BRIDGE ALONG CERVANTES-QUIRINO ROAD,CERVANTES, ILOCOS SUR | Region I | Ilocos Sur 2nd DEO | Completed | ₱27.9M | 100% | High risk66 | —-0.042 |
| 17AH0086CONSTRUCTION OF BANK PROTECTION WORKS(AGNO RIVER BASIN)BRGY. DORONGAN PUNTA, MANGATAREM, PANGASINAN | Region I | Pangasinan 2nd DEO | Completed | ₱19.6M | 100% | High risk65 | —-0.044 |
| 17CN0032CONSTRUCTION OF DITEKI FLOOD CONTROL, MARIA AURORA, AURORA | Region III | Aurora DEO | Completed | ₱29.4M | 100% | High risk64 | —-0.060 |
| 18A00043CONSTRUCTION OF NEW PERMANENT BRIDGES - SUWAGAYAN BR. 2 ALONG CERVANTES-QUIRINO RD. INCLUDING ROW | Region I | Region I | Completed | ₱133.6M | 100% | High risk63 | —-0.027 |
| 21A00147CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - LINGAYEN BYPASS ROAD (PHASE II), PANGASINAN | Region I | Region I | Completed | ₱212.3M | 100% | High risk62 | —-0.015 |
| 23A00036WIDENING OF PERMANENT BRIDGES - DAWEL PARALLEL BR. ALONG DAGUPAN-BONUAN-SAN FABIAN RD | Region I | Region I | On-Going | ₱134.7M | 91% | High risk62 | Flagged0.007 |
| 17PM0027NETWORK DEVELOPMENT-PAVING OF UNPAVED ROADS, TERTIARY ROADS JCT. TALUBIN-BARLIG-NATONIN-PARACELIS-CALACCAD RD (S03997LZ) K0421+444 - K0423+486 | Cordillera Administrative Region | Mountain Province 2nd DEO | Completed | ₱96.5M | 100% | High risk62 | —-0.029 |
| 19P00010ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - BRIDGE PROGRAM - REPLACEMENT OF PERMANENT WEAK BRIDGES, LUNAS BRIDGE (B04258LZ) ALONG JCT. TALUBIN - BARLIG - NATONIN - PARACELIS - CALACCAD ROAD | Cordillera Administrative Region | Cordillera Administrative Region | Completed | ₱128M | 100% | High risk62 | —-0.029 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24AH0199CONSTRUCTION OF RIVERBANK PROTECTION ALONG SINUCALAN RIVER, BRGY.LASIP CHICO,DAGUPAN CITY, PANGASINA | Region I | Pangasinan 2nd DEO | On-Going | ₱46.8M | 94% | High risk86 | Flagged0.046 |
| 24AH0154CONCRETING OF BRGY. MANLOCBOC TO BRGY. POBLACION FMR, BRGY. MANLOCBOC AND BRGY. POBLACION,AGUILAR,PA | Region I | Pangasinan 2nd DEO | On-Going | ₱49.8M | 74% | Medium risk52 | Flagged0.019 |
| 23A00036WIDENING OF PERMANENT BRIDGES - DAWEL PARALLEL BR. ALONG DAGUPAN-BONUAN-SAN FABIAN RD | Region I | Region I | On-Going | ₱134.7M | 91% | High risk62 | Flagged0.007 |
| 24CN0222CONSTRUCTION OF BIRTHPLACE OF PHILIPPINE SURFING MARKER AND BAYWALK BALER, AURORA | Region III | Aurora DEO | On-Going | ₱144.8M | 94% | High risk80 | Flagged0.006 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 26 | 21P00078CLUSTER: ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS MT. PROVINCE - CAGAYAN VIA TABUK - ENRILE R | Cordillera Administrative Region | Cordillera Administrative Region | Completed | ₱289.5M | 100% | Medium risk59 | —-0.042 |
| 27 | 18P00033CONVERGENCE AND SPECIAL SUPPORT PROGRAM : CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS - GUISSET-BINGA-BALOY-TINONGDAN ROAD LEADING TO BINGA DAM AND MT. UGO, SITE FOR THE INTERNATIONAL SKY RUNNING EVENT | Cordillera Administrative Region | Cordillera Administrative Region | Completed | ₱140.3M | 100% | Medium risk59 | —-0.061 |
| 28 | 20P00028ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - PRIMARY ROADS KENNON ROADKO235+410 - KO235+480KO235+834 | Cordillera Administrative Region | Cordillera Administrative Region | Completed | ₱163.3M | 100% | Medium risk58 | —-0.059 |
| 29 | 22P00009ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM: CONSTRUCTION OF MISSING LINKS/NEW ROADS BAGUIO - LA TRINIDAD - ITOGON - SABLAN TUBA AND TUBLAY, LABEY - LACAMEN PROVINCIAL ROAD (SECTION 4B OF BLISTT O | Cordillera Administrative Region | Cordillera Administrative Region | Completed | ₱193M | 100% | Medium risk58 | —-0.048 |
| 30 | 20A00022CONSTRUCTION OF BYPASS AND DIVERSION ROADS, URDANETA BYPASS ROAD, PANGASINAN | Region I | Region I | Completed | ₱139.7M | 100% | Medium risk58 | —-0.064 |
| 31 | 21P00025ORGANIZATIONAL OUTCOME 1:ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION - REHABILITATION / RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - PRIMARY ROADS, KENNON ROAD - K0222 + 112 - K0222 + 260TUBA, BEN | Cordillera Administrative Region | Cordillera Administrative Region | Completed | ₱193M | 100% | Medium risk58 | —-0.050 |
| 32 | 21P00077ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF MISSING LINKS / NEW ROADS BAGUIO - LA TRINIDAD - ITOGON - SABLAN - TUBA AND TUBLAY, LABEY - LACAMEN PROVINCIAL ROAD (SECTION 4B OF BLIS | Cordillera Administrative Region | Cordillera Administrative Region | Completed | ₱284.7M | 100% | Medium risk58 | —-0.046 |
| 33 | 20P00017ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF MISSING LINKS/NEW ROADS BAGUIO - LA TRINIDAD - ITOGON - SABLAN - TUBA AND TUBLAY, LABEY - LACAMEN PROVINCIAL ROAD (SECTION 4A) | Cordillera Administrative Region | Cordillera Administrative Region | Completed | ₱235.1M | 100% | Medium risk58 | —-0.048 |
| 34 | 19A00061CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, URDANETA BYPASS ROAD, PANGASINAN | Region I | Region I | Completed | ₱179.5M | 100% | Medium risk57 | —-0.056 |
| 35 | 22C00083FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF CAMILING-AGNO RIVER FLOODWAY, TARLAC (PHASE 3), PROVINCE OF TARLAC | Region III | Region III | Completed | ₱289.5M | 100% | Medium risk57 | —-0.044 |
| 36 | 22C00084FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF CAMILING-AGNO RIVER FLOODWAY, TARLAC (PHASE 4), PROVINCE OF TARLAC | Region III | Region III | Completed | ₱289.5M | 100% | Medium risk57 | —-0.039 |
| 37 | 23C00063FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS-CONSTRUCTION OF CAMILING-AGNO RIVER FLOODWAY, (PHASE 5), PROVINCE OF TARLAC | Region III | Region III | Completed | ₱193M | 100% | Medium risk57 | —-0.044 |
| 38 | 18A00028NETWORK DEVELOPMENT - CONSTRUCTION OF MISSING LINKS/ NEW ROADS - MANGATAREM-STA CRUZ ROAD, PACKAGE 1, PANGASINAN | Region I | Region I | Completed | ₱188M | 100% | Medium risk57 | —-0.054 |
| 39 | 18A00024CONSTRUCTION / UPGRADING / REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - PRIMARY ROADS - MANILA NORTH RD - K0194 + 859 TO K0198 + 635 | Region I | Region I | Completed | ₱167.2M | 100% | Medium risk57 | —-0.059 |
| 40 | 21A00097CONSTRUCTION OF BY-PASS AND DIVERSION ROADS- BINALONAN DIVERSION ROAD, PANGASINAN | Region I | Region I | Completed | ₱101.3M | 100% | Medium risk56 | —-0.075 |
| 41 | 21A00056CONSTRUCTION OF BY-PASS AND DIVERSION ROADS-URDANETA BYPASS ROAD, PANGASINAN | Region I | Region I | Completed | ₱101.3M | 100% | Medium risk56 | —-0.075 |
| 42 | 23A00264PREVENTIVE MAINTENANCE - SECONDARY ROADS, AGOO - BAGUIO CITY RD - K0237+(-885) - K0237+(-810), K0237 + 000 - K0237 + 885, K0238 + 000 - K0238 + 159, K0240 + 937 - K0241 + 000, K0241 + 234 - K0242 + 610, K0242 + 960 - K0243 + 226, K0243 + 596 - K0244 + 11 | Region I | Region I | Completed | ₱156.3M | 100% | Medium risk55 | —-0.064 |
| 43 | 23A00299SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), CONSTRUCTION OF BRIDGE, MANGCASUY - STA. MARIA, BINALONAN, PANGASINAN | Region I | Region I | Completed | ₱86.8M | 100% | Medium risk54 | —-0.038 |
| 44 | 21P00009ORGANIZATIONAL OUTCOME 1:ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION / RECONSTRUCTION OF ROADS WITH SLIP, SLOPE COLLAPSE AND LANDSLIDES - PRIMARY ROADS, KENNON ROADKO239+297 - KO239+380 | Cordillera Administrative Region | Cordillera Administrative Region | Completed | ₱91.1M | 100% | Medium risk54 | —-0.076 |
| 45 | 23CH0102CONSTRUCTION OF MULTI-PURPOSE BUILDING (NEW MUNICIPAL BUILDING) INCLUDING SITE DEVELOPMENT, PORAC, PAMPANGA | Region III | Pampanga 2nd DEO | Completed | ₱148.5M | 100% | Medium risk53 | —-0.069 |
| 46 | 17CH0031REHABILITATION/MAJOR REPAIR OF PERMANENT BRIDGE MANIBAUG BR. (B01502LZ) ALONG ANGLES-PORAC-FLORIDABL | Region III | Pampanga 2nd DEO | Completed | ₱7.1M | 100% | Medium risk53 | —-0.038 |
| 47 | 25A00307WIDENING OF PERMANENT BRIDGES - BUED PARALLEL BR. ALONG MANILA NORTH RD | Region I | Region I | On-Going | ₱56.2M | 60% | Medium risk52 | —-0.011 |
| 48 | 19P00005CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATION SAN ISIDRO SUR- POBLACION-LAPPA-MARAG-CADACLAN-SALAGUNTING TOURSIM ROAD LEADING TO MANACOTA UNDERGROUND RIVER AND OTHER TOURSIM AREA | Cordillera Administrative Region | Cordillera Administrative Region | Completed | ₱57.9M | 100% | Medium risk52 | —-0.036 |
| 49 | 24AH0154CONCRETING OF BRGY. MANLOCBOC TO BRGY. POBLACION FMR, BRGY. MANLOCBOC AND BRGY. POBLACION,AGUILAR,PA | Region I | Pangasinan 2nd DEO | On-Going | ₱49.8M | 74% | Medium risk52 | Flagged0.019 |
| 50 | 20PC0024CONSTRUCTION/MAINTENANCE OF FLOOD CONTROL MITIGATION STRUCTURES AND DRAINAGE SYSTEMS CONSTRUCTION OF MARAG FLOOD CONTROL MARAG, LUNA, APAYAO | Cordillera Administrative Region | Apayao 2nd DEO | Completed | ₱49.5M | 100% | Medium risk51 | —-0.061 |