Contractor dossier
76 projects on file, including joint ventures this contractor is part of.
Total projects
76
Total budget
₱1.9B
Average progress
80.2%
Completion rate
55.3%
Below 70%
Average risk score
44.5
Medium risk on average, out of 100
Flagged as unusual
7
9.2% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region III | 53 | ₱1.6B | 42.0 | 3 | 82.6% |
| Negros Island Region | 11 | ₱100.6M | 45.0 | 0 | 77.4% |
| Region I | 7 | ₱83.4M | 66.7 | 4 | 66.5% |
| National Capital Region | 3 | ₱7.4M | 32.7 | 0 | 100.0% |
| Region IV-A | 1 | ₱9.7M | 47.5 | 0 | 3.1% |
| Region VI | 1 | ₱4.9M | 46.8 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 30 | ₱633.2M | 38.3 | 0 | 84.4% |
| Buildings and Facilities | 21 | ₱148.2M | 37.3 | 1 | 77.8% |
| Flood Control and Drainage | 11 | ₱783.7M | 56.4 | 0 | 91.0% |
| Bridges | 7 | ₱200M | 43.5 | 1 | 71.9% |
| GAA 2025 SSP | 4 | ₱61.7M | 94.4 | 4 | 56.8% |
| Water Provision and Storage | 2 | ₱4.4M | 31.2 | 0 | 100.0% |
| OTHER | 1 | ₱19.5M | 84.5 | 1 | 0.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25A00379BASIC INFRASTRUCTURE PROGRAM (BIP), CONSTRUCTION OF MULTI - PURPOSE BUILDING, BARANGAY PUELAY, VILLASIS, PANGASINAN | Region I | Region I | On-Going | ₱4.8M | 48% | High risk95 | Flagged0.026 |
| 25A00380BASIC INFRASTRUCTURE PROGRAM (BIP), CONSTRUCTION OF MULTI - PURPOSE BUILDING, BARANGAY ZONE V, VILLASIS, PANGASINAN | Region I | Region I | On-Going | ₱4.8M | 55% | High risk95 | Flagged0.026 |
| 25A00381BASIC INFRASTRUCTURE PROGRAM (BIP), CONSTRUCTION OF MULTI - PURPOSE BUILDING, BARANGAY SAN JOSE, SANTO TOMAS, PANGASINAN | Region I | Region I | On-Going | ₱4.8M | 63% | High risk95 | Flagged0.024 |
| 25CO0008SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONST OF FLOOD MITIGATION STRUCTURE, COLO RIS, DINALUPIHAN, BATAAN | Region III | Bataan 3rd DEO | On-Going | ₱47.3M | 62% | High risk94 | Flagged0.013 |
| 25CA0074CONSTRUCTION OF SCHOOL BUILDING, MABUCO ELEMENTARY SCHOOL, MABUCO ELEMENTARY SCHOOL, BARANGAY MABUCO, HERMOSA, BATAAN | Region III | Bataan 1st DEO | On-Going | ₱19.5M | 0% | High risk84 | Flagged0.062 |
| 24C00048FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BAGAC RIVER (VALDEZ BRIDGE), BAGAC, BATAAN (PHASE II) | Region III | Region III | On-Going | ₱94.3M | 93% | High risk81 | —-0.012 |
| 24CM0078FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, REHABILITATION OF FLOOD MITIGATION STRUCTURE, STO. TOMAS RIVER (STA. FE SECTION), SAN MARCELINO, ZAMBALES | Region III | Zambales 2nd DEO | Completed | ₱386M | 100% | High risk80 | —-0.019 |
| 24C00161FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG COLO TRIBUTARY (PINULOT SECTION) TO COLO RIVER, PHASE 2-P, BRGY PINULOT, DINALUPIHAN, BATAAN | Region III | Region III | On-Going | ₱47.3M | 54% | High risk73 | —-0.008 |
| 24C00174CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI PURPOSE BLDG/FACILITIES TO SUPPORT SOCIAL SERVICES - REHABILITATION OF MULTI-PURPOSE BUILDING, BRGY. PARANG, BAGAC, BATAAN | Region III | Region III | Completed | ₱5M | 100% | High risk71 | —-0.070 |
| 25C00320CONVERGENCE ANS SPECIAL SUPPORT PROGRAM - SPECIAL ROAD FUND - MOTOR VEHICLES USER'S CHARGE (MVUC) AS PER RA 11239 - INSTALLATION/APPLICATION OF ROAD SAFETY FACILITIES (ROADWAY LIGHTING) ALONGJCT LAYAC-BALANGA-MARIVELES PORT RD - MARIVELES, BATAAN | Region III | Bataan 3rd DEO | On-Going | ₱18.9M | 0% | High risk70 | —-0.012 |
| 25C00177CONVERGENCE AND SPECIAL SUPPORT PROG. - BASIC INFRASTRUCTURE PROG. - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - REHAB. OF FLOOD MITIGATION STRUCTURE ALONG SAGUING RIVER (TRIBUTARY TO COLO RIVER) DINALUPIHAN, BAT. | Region III | Bataan 3rd DEO | On-Going | ₱9.7M | 100% | High risk69 | —-0.034 |
| 17CA0018CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION/IMPROVEMENT OF PENTOR-BALSIK RIVER (TORRES SECTION), DINALUPIHAN, BATAAN | Region III | Bataan 1st DEO | Completed | ₱13.7M | 100% | High risk68 | —-0.061 |
| 24HM0076CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/ FACILITIES, REHABILITATION OF LICOAN ROAD, MARIA, SIQUIJOR | Negros Island Region | Siquijor DEO | On-Going | ₱29.6M | 82% | High risk66 | —-0.023 |
| 24C00160BRIDGE PROGRAM - REPLACEMENT OF PERMANENT WEAK BRIDGES - AMO BR. (B01613LZ) ALONG JCT. LAYAC-BALANGA-MARIVELES PORT ROAD (PHASE 1) | Region III | Region III | On-Going | ₱40.2M | 0% | High risk64 | Flagged0.016 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25CA0074CONSTRUCTION OF SCHOOL BUILDING, MABUCO ELEMENTARY SCHOOL, MABUCO ELEMENTARY SCHOOL, BARANGAY MABUCO, HERMOSA, BATAAN | Region III | Bataan 1st DEO | On-Going | ₱19.5M | 0% | High risk84 | Flagged0.062 |
| 24AI0221CONSTRUCTION OF ONE (1) STOREY TWO (2) CLASSROOM SCHOOL BUILDING IN CASABULA ELEMENTARY SCHOOL BARANGAY CASANTAAN, URDANETA CITY, PANGASINAN | Region I | Pangasinan 3rd DEO | On-Going | ₱5.4M | 0% | Medium risk46 | Flagged0.031 |
| 25A00379BASIC INFRASTRUCTURE PROGRAM (BIP), CONSTRUCTION OF MULTI - PURPOSE BUILDING, BARANGAY PUELAY, VILLASIS, PANGASINAN | Region I | Region I | On-Going | ₱4.8M | 48% | High risk95 | Flagged0.026 |
| 25A00380BASIC INFRASTRUCTURE PROGRAM (BIP), CONSTRUCTION OF MULTI - PURPOSE BUILDING, BARANGAY ZONE V, VILLASIS, PANGASINAN | Region I | Region I | On-Going | ₱4.8M | 55% | High risk95 | Flagged0.026 |
| 25A00381BASIC INFRASTRUCTURE PROGRAM (BIP), CONSTRUCTION OF MULTI - PURPOSE BUILDING, BARANGAY SAN JOSE, SANTO TOMAS, PANGASINAN | Region I | Region I | On-Going | ₱4.8M | 63% | High risk95 | Flagged0.024 |
| 24C00160BRIDGE PROGRAM - REPLACEMENT OF PERMANENT WEAK BRIDGES - AMO BR. (B01613LZ) ALONG JCT. LAYAC-BALANGA-MARIVELES PORT ROAD (PHASE 1) | Region III | Region III | On-Going | ₱40.2M | 0% | High risk64 | Flagged0.016 |
| 25CO0008SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONST OF FLOOD MITIGATION STRUCTURE, COLO RIS, DINALUPIHAN, BATAAN | Region III | Bataan 3rd DEO | On-Going | ₱47.3M | 62% | High risk94 | Flagged0.013 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 51 | 22CA0058BASIC INFRASTRUCTURE PROGRAM (BIP)- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - RECONSTRUCTION OF MULAWIN - BAYAN BRIDGE, ORANI, BATAAN | Region III | Bataan 1st DEO | Completed | ₱7.9M | 100% | Medium risk37 | —-0.064 |
| 52 | 17OI0067CONST./REHAB. OF WATER SUPPLY/SEPTAGE AND SEWERAGE/RAINWATER COLLECTORS-RAINWATER COLLECTORS SYSTEM | National Capital Region | Las Piñas-Muntinlupa DEO | Completed | ₱3.1M | 100% | Medium risk36 | —-0.028 |
| 53 | 17OE0089LOCAL INFRASTRUCTURE PROGRAM: BUILDING AND OTHER STRUCTURES: MULTI-PURPOSE/FACILITIES: CONSTRUCTION OF MULTI-PURPOSE BUILDING (OFW CENTER) BRGY. 91, TONDO, MANILA, TONDO, MANILA CITY | National Capital Region | North Manila DEO | Completed | ₱3M | 100% | Medium risk36 | —-0.073 |
| 54 | 22CL0023CONSTRUCTION OF HEADQUARTERS NAVAL STATION LEOVIGUILDO GANTIOQUI (NSLG), NETC, SAN ANTONIO, ZAMBALES | Region III | Zambales 1st DEO | Completed | ₱19.6M | 100% | Medium risk36 | —-0.097 |
| 55 | 23HM0031CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM, MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, REHABILITATION OF MULTI-PURPOSE FACILITIES, BARANGAY OLAVE, ENRIQUE VILLANUEVA, SIQUIJOR | Negros Island Region | Siquijor DEO | On-Going | ₱2M | 100% | Medium risk36 | —-0.038 |
| 56 | 23CA0035BASIC INFRASTRUCTURE PROGRAM - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES- CONSTRUCTION OF MULTI-PURPOSE BUILDING IN BARANGAY BALSIK, HERMOSA, BATAAN | Region III | Bataan 1st DEO | Completed | ₱7.9M | 100% | Medium risk34 | —-0.104 |
| 57 | 23CM0002PREVENTIVE MAINTENANCE - PRIMARY ROADS JOSE ABAD SANTOS AVE (JASA), K0122+493 - K0122+731, OLONGAPO CITY | Region III | Zambales 2nd DEO | Completed | ₱10.7M | 100% | Medium risk33 | —-0.098 |
| 58 | 21CA0018ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS - TABACAN POBLACION ROAD, K0102+(-127)-K0102+047, K0102+349-K0102+593DINALUPIHAN, BATAAN | Region III | Bataan 1st DEO | Completed | ₱8.1M | 100% | Medium risk33 | —-0.103 |
| 59 | 23CM0001PREVENTIVE MAINTENANCE - PRIMARY ROADS JOSE ABAD SANTOS AVE (JASA), K0119+022 - K0119+235, OLONGAPO CITY | Region III | Zambales 2nd DEO | Completed | ₱9.4M | 100% | Medium risk33 | —-0.099 |
| 60 | 24HM0084CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE FACILITY CANGMALALAG, LARENA, SIQUIJOR | Negros Island Region | Siquijor DEO | On-Going | ₱2.2M | 97% | Medium risk33 | —-0.047 |
| 61 | 23CA0018BASIC INFRASTRUCTURE PROGRAM -ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/ FACILITIES -REPLACEMENT OF ROMULO BRIDGE, SAN PEDROHERMOSA, BATAAN | Region III | Bataan 1st DEO | Completed | ₱11.9M | 100% | Medium risk32 | —-0.065 |
| 62 | 25CO0011FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL MITIGATION STRUCTURE AT IBIS CIS, BRGY. IBIS, BAGAC, BATAAN | Region III | Bataan 3rd DEO | On-Going | ₱42.6M | 87% | Medium risk30 | —-0.052 |
| 63 | 24CH0069BRIDGE PROGRAM - REPLACEMENT OF PERMANENT WEAK BRIDGE - FORTUNA BR. (CANTILEVER) (B01524LZ) ALONG SN ANTONIO-FLORIDABLANCA RD. (PHASE 2), FLORIDABLANCA, PAMPANGA | Region III | Pampanga 2nd DEO | Completed | ₱4.8M | 100% | Medium risk30 | —-0.064 |
| 64 | 19CA0061CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEM REHABILITATION OF FLOOD CONTROL STRUCTURES ALONG PAGALANGGANG RIVER (PAGALANGGANG SECTION), STA. 001+124 TO 002+024, BARANGAY PAGALANGGANGDINALUPIHAN, BATAAN | Region III | Bataan 1st DEO | Completed | ₱24.5M | 100% | Low risk30 | —-0.090 |
| 65 | 17OI0086CONST./REHAB. OF WATER SUPPLY/SEPTAGE/RAINWATER COLLECTOR SYSTEM AT FIVE (5) SCHOOLS IN LAS PINAS CI | National Capital Region | Las Piñas-Muntinlupa DEO | Completed | ₱1.3M | 100% | Low risk26 | —-0.041 |
| 66 | 23CA0076CONVERGENCE AND SPECIAL SUPPORT PROGRAM -SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES -CONCRETING OF ROAD, BARANGAY MANDAMA-PULO | Region III | Bataan 1st DEO | Completed | ₱4.8M | 100% | Low risk25 | —-0.040 |
| 67 | 25CA0043BASIC INFRASTRUCTURE PROGRAM- MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (DOH BUILDING) IN BARANGAY CALAYLAYAN, ABUCAY, BATAAN | Region III | Bataan 1st DEO | On-Going | ₱3.8M | 44% | Low risk20 | —-0.051 |
| 68 | 22CB0015PREVENTIVE MAINTENANCE - TERTIARY ROADS - EPZA BY-PASS (BARASO COUNTRY RD) - KO159+000-KO159+601, KO162+500-KO163+031, BATAAN 2ND DISTRICT | Region III | Bataan 2nd DEO | Completed | ₱4.7M | 100% | Low risk19 | —-0.102 |
| 69 | 22CB0014PREVENTIVE MAINTENANCE - TERTIARY ROADS - JCT LAYAC-BALANGA-MARIVELES PORT RD - KO124+254-KO124+492, BATAAN 2ND DISTRICT | Region III | Bataan 2nd DEO | Completed | ₱3.3M | 100% | Low risk17 | —-0.096 |
| 70 | 19CA0079LOCAL INFRASTRUCTURE PROGRAM BUILDINGS AND OTHER STRUCTURES MULTI-PURPOSE/FACILITIES CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY MULAWIN, ORANI, BATAAN | Region III | Bataan 1st DEO | Completed | ₱4M | 100% | Low risk15 | —-0.105 |
| 71 | 20CA0011NETWORK DEVELOPMENT PROGRAM-OFF CARRIAGEWAY IMPROVEMENT PRIMARY ROADS-JOSE ABAD SANTOS AVE (JASA) - K0109+039 - K0109+494DINALUPIHAN, BATAAN | Region III | Bataan 1st DEO | Completed | ₱1.7M | 100% | Low risk15 | —-0.097 |
| 72 | 21CA0005LOCAL INFRASTRUCTURE PROGRAM- BUILDING AND OTHER STRUCTURES - MULTI-PURPOSE/FACILITIES- CONSTRUCTION OF MULTI-PURPOSE BUILDING, POBLACION, MORONG, BATAAN | Region III | Bataan 1st DEO | Completed | ₱3M | 100% | Low risk14 | —-0.100 |
| 73 | 21CA0021LOCAL INFRASTRUCTURE PROGRAM - LOCAL ROADS AND BRIDGES - LOCAL ROADS-IMPROVEMENT OF ROAD, UPPER PUROK 4, SAN PABLO, DINALUPIHAN, BATAAN | Region III | Bataan 1st DEO | Completed | ₱2M | 100% | Low risk14 | —-0.097 |
| 74 | 18CA0013ASSET PRESERVATION PROGRAM-PREVENTIVE MAINTENANCE, SECONDARY ROADS, ANGELES-PORAC-FLORIDABLANCA-DINALUPIHAN ROAD, K0118+067-K0118+187DINALUPIHAN, BATAAN | Region III | Bataan 1st DEO | Completed | ₱2M | 100% | Low risk14 | —-0.101 |
| 75 | 21CA0024LOCAL INFRASTRUCTURE PROGRAM - BUILDINGS AND OTHER STRUCTURES - MULTI-PURPOSE/FACILITIES - CONSTRUCTION OF NEW HEALTH CENTER BUILDING, BRGY. PENTOR, DINALUPIHAN, BATAAN | Region III | Bataan 1st DEO | Completed | ₱4M | 100% | Low risk13 | —-0.104 |