Contractor dossier
24 projects on file, including joint ventures this contractor is part of.
Total projects
24
Total budget
₱622.9M
Average progress
85.2%
Completion rate
66.7%
Below 70%
Average risk score
65.4
High risk on average, out of 100
Flagged as unusual
6
25.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region I | 24 | ₱622.9M | 65.4 | 6 | 85.2% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 12 | ₱213.7M | 66.4 | 2 | 88.6% |
| Bridges | 10 | ₱285.6M | 59.7 | 2 | 89.6% |
| GAA 2025 OO-1 | 1 | ₱48.3M | 93.4 | 1 | 25.7% |
| OTHER | 1 | ₱75.3M | 80.7 | 1 | 59.1% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25AA0022BRIDGE PROGRAM - WIDENING OF PERMANENT BRIDGES - BADUANG BR. (B00542LZ) ALONG MANILA NORTH RD | Region I | Ilocos Norte 1st DEO | On-Going | ₱48.3M | 26% | High risk93 | Flagged0.025 |
| 17A00031CONSTRUCTION AND MAINTENANCE OF BRIDGES ALONG NATIONAL ROADS, WIDENING OF PERMANENT BRIDGES (TO MORE THAN 2 LANES), PASUQUIN BRIDGE (B00529LZ) ALONG MANILA NORTH ROAD | Region I | Region I | On-Going | ₱75.3M | 59% | High risk81 | Flagged0.054 |
| 24AA0434CONCRETING OF UBBOG - AGAGA, BRGY. TANAP FMR, BURGOS, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | On-Going | ₱28.7M | 86% | High risk76 | Flagged0.021 |
| 24AA0425CONCRETING OF SITIO 6, BRGY. CAMANGGAAN TO SITIO LUSONG, BRGY. 29 FMR, BRGY. CAMANGGAAN AND BRGY. 29, LAOAG CITY, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | On-Going | ₱10.7M | 84% | High risk74 | Flagged0.016 |
| 25A00512ROAD WIDENING - PRIMARY ROADS, MANILA NORTH RD - K0485 + (-088) - K0485 + 462 | Region I | Region I | On-Going | ₱9.2M | 0% | High risk71 | —-0.016 |
| 23AA0222SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD, VIRA-DIBUA ROAD, BARANGAY NO. 55-C, VIRA, LAOAG CITY, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | On-Going | ₱23.5M | 94% | High risk71 | —-0.031 |
| 24AA0030REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - TERTIARY ROADS - PASUQUIN RADAR AIRSTATION RD - K0507 + 350 - K0508 + 232 | Region I | Ilocos Norte 1st DEO | Completed | ₱21.6M | 100% | High risk71 | —-0.082 |
| 22AA0138REHABILITATION OF ROAD, BARANGAY P.F. ALVIAR, SALSALAMAGUI, VINTAR, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | Completed | ₱46.3M | 100% | High risk70 | —-0.076 |
| 22AA0044SUSTAINABLE INFRASTRUCTURE PROJECTS ELLEVATING GAPS (SIPAG) ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR ATRATEGIC PUBLIC BUILDINGS FACILITIES, REHABILITATION OF TANAP - NAGSUROT IRRIGATION ACCESS ROAD ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | Completed | ₱14.7M | 100% | High risk70 | —-0.081 |
| 23A00058WIDENING OF PERMANENT BRIDGES - PASUQUIN BR. (B00529LZ) ALONG MANILA NORTH RD | Region I | Region I | On-Going | ₱48.2M | 80% | High risk70 | Flagged0.002 |
| 18AA0372REHAB./RECONST./UPGRADING OF DAMAGED PAVED ROADS, TERTIARY ROADS, ILOCOS NORTE-APAYAO ROAD, K0490+395-K0490+429, K0490+653-K0490+770, K0490+779-K0491+000 | Region I | Ilocos Norte 1st DEO | Completed | ₱9.2M | 100% | High risk70 | —-0.084 |
| 18AA0373NETWORK DEVELOPMENT PROGRAM, OFF-CARRIAGEWAY IMPROVEMENT, TERTIARY ROADS, ILOCOS NORTE-APAYAO - K0490+(-552)-K0490+(-038), K0492+553-K0492+994, SARRAT, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | Completed | ₱19.4M | 100% | High risk68 | —-0.081 |
| 18AA0361REHAB./MAJOR REPAIR OF PERMANENT BRIDGES, BANBAN BR. (B04483LZ) ALONG MNR, BANGUI, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | Completed | ₱9.5M | 100% | High risk68 | —-0.044 |
| 17A00025CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO AIRPORT - LAOAG INTERNATIONAL AIRPORT-GABU-FORT ILOCANDIA ROAD (BRIDGE REPLACEMENT) INCLUDING ROW, LAOAG CITY, ILOCOS NORTE 1ST LD | Region I | Region I | Completed | ₱53.7M | 100% | High risk67 | —-0.016 |
| 21AA0072REHABILITATION/IMPROVEMENT OF STA. ROSA - PANDAN - PARIIR ROAD (KM491.514 - 502.050), SARRAT, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | Completed | ₱9.9M | 100% | High risk67 | —-0.085 |
| 17AB0037CONSTRUCTION AND MAINTENANCE OF BRIDGES ALONG NATIONAL ROADS, REHABILITATION/MAJOR REPAIR OF PERMANENT BRIDGES, BAGBAG BRIDGE 3 (B00814LZ) ALONG LAOAG-SARRAT-PIDDIG-SOLSONA ROAD, SOLSONA, ILOCOS NORTE | Region I | Ilocos Norte 2nd DEO | Completed | ₱65M | 100% | High risk67 | —-0.021 |
| 17AA0064REHAB/MAJOR REPAIR OF PERM BRIDGES, BANBAN BRIDGE(BO4483LZ)ALONG MNR, BANGUI, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | Completed | ₱4.8M | 100% | High risk66 | —-0.020 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 17A00031CONSTRUCTION AND MAINTENANCE OF BRIDGES ALONG NATIONAL ROADS, WIDENING OF PERMANENT BRIDGES (TO MORE THAN 2 LANES), PASUQUIN BRIDGE (B00529LZ) ALONG MANILA NORTH ROAD | Region I | Region I | On-Going | ₱75.3M | 59% | High risk81 | Flagged0.054 |
| 25AA0022BRIDGE PROGRAM - WIDENING OF PERMANENT BRIDGES - BADUANG BR. (B00542LZ) ALONG MANILA NORTH RD | Region I | Ilocos Norte 1st DEO | On-Going | ₱48.3M | 26% | High risk93 | Flagged0.025 |
| 24AA0434CONCRETING OF UBBOG - AGAGA, BRGY. TANAP FMR, BURGOS, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | On-Going | ₱28.7M | 86% | High risk76 | Flagged0.021 |
| 24AA0425CONCRETING OF SITIO 6, BRGY. CAMANGGAAN TO SITIO LUSONG, BRGY. 29 FMR, BRGY. CAMANGGAAN AND BRGY. 29, LAOAG CITY, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | On-Going | ₱10.7M | 84% | High risk74 | Flagged0.016 |
| 25A00104WIDENING OF PERMANENT BRIDGES, DAKKEL A DANUM BR. (B00548LZ) ALONG MANILA NORTH RD (PHASE II) | Region I | Region I | On-Going | ₱4.7M | 15% | Medium risk47 | Flagged0.008 |
| 23A00058WIDENING OF PERMANENT BRIDGES - PASUQUIN BR. (B00529LZ) ALONG MANILA NORTH RD | Region I | Region I | On-Going | ₱48.2M | 80% | High risk70 | Flagged0.002 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25AA0022BRIDGE PROGRAM - WIDENING OF PERMANENT BRIDGES - BADUANG BR. (B00542LZ) ALONG MANILA NORTH RD | Region I | Ilocos Norte 1st DEO | On-Going | ₱48.3M | 26% | High risk93 | Flagged0.025 |
| 2 | 17A00031CONSTRUCTION AND MAINTENANCE OF BRIDGES ALONG NATIONAL ROADS, WIDENING OF PERMANENT BRIDGES (TO MORE THAN 2 LANES), PASUQUIN BRIDGE (B00529LZ) ALONG MANILA NORTH ROAD | Region I | Region I | On-Going | ₱75.3M | 59% | High risk81 | Flagged0.054 |
| 3 | 24AA0434CONCRETING OF UBBOG - AGAGA, BRGY. TANAP FMR, BURGOS, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | On-Going | ₱28.7M | 86% | High risk76 | Flagged0.021 |
| 4 | 24AA0425CONCRETING OF SITIO 6, BRGY. CAMANGGAAN TO SITIO LUSONG, BRGY. 29 FMR, BRGY. CAMANGGAAN AND BRGY. 29, LAOAG CITY, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | On-Going | ₱10.7M | 84% | High risk74 | Flagged0.016 |
| 5 | 25A00512ROAD WIDENING - PRIMARY ROADS, MANILA NORTH RD - K0485 + (-088) - K0485 + 462 | Region I | Region I | On-Going | ₱9.2M | 0% | High risk71 | —-0.016 |
| 6 | 23AA0222SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD, VIRA-DIBUA ROAD, BARANGAY NO. 55-C, VIRA, LAOAG CITY, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | On-Going | ₱23.5M | 94% | High risk71 | —-0.031 |
| 7 | 24AA0030REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - TERTIARY ROADS - PASUQUIN RADAR AIRSTATION RD - K0507 + 350 - K0508 + 232 | Region I | Ilocos Norte 1st DEO | Completed | ₱21.6M | 100% | High risk71 | —-0.082 |
| 8 | 22AA0138REHABILITATION OF ROAD, BARANGAY P.F. ALVIAR, SALSALAMAGUI, VINTAR, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | Completed | ₱46.3M | 100% | High risk70 | —-0.076 |
| 9 | 22AA0044SUSTAINABLE INFRASTRUCTURE PROJECTS ELLEVATING GAPS (SIPAG) ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR ATRATEGIC PUBLIC BUILDINGS FACILITIES, REHABILITATION OF TANAP - NAGSUROT IRRIGATION ACCESS ROAD ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | Completed | ₱14.7M | 100% | High risk70 | —-0.081 |
| 10 | 23A00058WIDENING OF PERMANENT BRIDGES - PASUQUIN BR. (B00529LZ) ALONG MANILA NORTH RD | Region I | Region I | On-Going | ₱48.2M | 80% | High risk70 | Flagged0.002 |
| 11 | 18AA0372REHAB./RECONST./UPGRADING OF DAMAGED PAVED ROADS, TERTIARY ROADS, ILOCOS NORTE-APAYAO ROAD, K0490+395-K0490+429, K0490+653-K0490+770, K0490+779-K0491+000 | Region I | Ilocos Norte 1st DEO | Completed | ₱9.2M | 100% | High risk70 | —-0.084 |
| 12 | 18AA0373NETWORK DEVELOPMENT PROGRAM, OFF-CARRIAGEWAY IMPROVEMENT, TERTIARY ROADS, ILOCOS NORTE-APAYAO - K0490+(-552)-K0490+(-038), K0492+553-K0492+994, SARRAT, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | Completed | ₱19.4M | 100% | High risk68 | —-0.081 |
| 13 | 18AA0361REHAB./MAJOR REPAIR OF PERMANENT BRIDGES, BANBAN BR. (B04483LZ) ALONG MNR, BANGUI, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | Completed | ₱9.5M | 100% | High risk68 | —-0.044 |
| 14 | 17A00025CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO AIRPORT - LAOAG INTERNATIONAL AIRPORT-GABU-FORT ILOCANDIA ROAD (BRIDGE REPLACEMENT) INCLUDING ROW, LAOAG CITY, ILOCOS NORTE 1ST LD | Region I | Region I | Completed | ₱53.7M | 100% | High risk67 | —-0.016 |
| 15 | 21AA0072REHABILITATION/IMPROVEMENT OF STA. ROSA - PANDAN - PARIIR ROAD (KM491.514 - 502.050), SARRAT, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | Completed | ₱9.9M | 100% | High risk67 | —-0.085 |
| 16 | 17AB0037CONSTRUCTION AND MAINTENANCE OF BRIDGES ALONG NATIONAL ROADS, REHABILITATION/MAJOR REPAIR OF PERMANENT BRIDGES, BAGBAG BRIDGE 3 (B00814LZ) ALONG LAOAG-SARRAT-PIDDIG-SOLSONA ROAD, SOLSONA, ILOCOS NORTE | Region I | Ilocos Norte 2nd DEO | Completed | ₱65M | 100% | High risk67 | —-0.021 |
| 17 | 17AA0064REHAB/MAJOR REPAIR OF PERM BRIDGES, BANBAN BRIDGE(BO4483LZ)ALONG MNR, BANGUI, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | Completed | ₱4.8M | 100% | High risk66 | —-0.020 |
| 18 | 17AC0024WIDENING OF BANTAOAY BRIDGE (B00583LZ), MANILA NORTH ROAD | Region I | Ilocos Sur 1st DEO | Completed | ₱39.8M | 100% | Medium risk59 | —-0.015 |
| 19 | 17AB0042CONSTRUCTION AND MAINTENANCE OF BRIDGES ALONG NATIONAL ROADS, REPLACEMENT OF PERMANENT WEAK BRIDGE, SAWANG BRIDGE (B00558LZ) (PHASE I) | Region I | Ilocos Norte 2nd DEO | Completed | ₱31.4M | 100% | Medium risk57 | —-0.006 |
| 20 | 19AB0070REPLACEMENT OF PERMANENT WEAK BRIDGE, SAWANG BRIDGE (B00558LZ) ALONG PIAS-CURRIMAO-BALACCAD ROAD (PHASE II)/PAOAY, ILOCOS NORTE | Region I | Ilocos Norte 2nd DEO | Completed | ₱14.7M | 100% | Medium risk49 | —-0.048 |
| 21 | 21AB0125WIDENING OF PERMANENT BRIDGES, NAGRANGTAYAN BRIDGE (B00559LZ) ALONG PIAS-CURRIMAO-BALACCAD ROAD, PAOAY, ILOCOS NORTE | Region I | Ilocos Norte 2nd DEO | Completed | ₱13.9M | 100% | Medium risk48 | —-0.047 |
| 22 | 25A00104WIDENING OF PERMANENT BRIDGES, DAKKEL A DANUM BR. (B00548LZ) ALONG MANILA NORTH RD (PHASE II) | Region I | Region I | On-Going | ₱4.7M | 15% | Medium risk47 | Flagged0.008 |
| 23 | 21AB0124ROAD WIDENING - SECONDARY ROADS - PIAS-CURRIMAO-BALACCAD RD - K0472+125 - K0473+149, PAOAY, ILOCOS NORTE | Region I | Ilocos Norte 2nd DEO | Completed | ₱14.7M | 100% | Medium risk46 | —-0.084 |
| 24 | 23AB0001PREVENTIVE MAINTENANCE - PRIMARY ROADS, MANILA NORTH RD - K0452 + 403 - K0453 + 000 | Region I | Ilocos Norte 2nd DEO | Completed | ₱5.9M | 100% | Medium risk43 | —-0.080 |