Opening the dossier…
Opening the dossier…
Contractor dossier
71 projects on file, including joint ventures this contractor is part of.
Total projects
71
Total budget
₱1.7B
Average progress
99.9%
Completion rate
97.2%
Average risk score
29.5
Low risk on average, out of 100
Flagged as unusual
1
1.4% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region II | 53 | ₱929M | 25.1 | 1 | 99.9% |
| Cordillera Administrative Region | 18 | ₱771.5M | 42.2 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 30 | ₱63.4M | 19.7 | 0 | 100.0% |
| Roads | 20 | ₱616.1M | 35.2 | 0 | 100.0% |
| Bridges | 11 | ₱842.7M | 42.5 | 1 | 99.6% |
| Flood Control and Drainage | 6 | ₱141.7M | 33.9 | 0 | 100.0% |
| Water Provision and Storage | 3 | ₱1.9M | 18.2 | 0 | 100.0% |
| OTHER | 1 | ₱34.7M | 73.5 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 20PJ0049LOCAL INFRASTRUCTURE PROGRAM- CONSTRUCTION OF LOCAL BRIDGE, INWALOY-EPENG-MAGULON | Cordillera Administrative Region | Ifugao 2nd DEO | Completed | ₱34.7M | 100% | High risk74 | —-0.017 |
| 24B00043OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT - CONSTRUCTION OF MISSING LINKS/ NEW ROADS - ARITAO-QUIRINO ROAD (UMASOK BR. AND APPROACHES), PACKAGE 2, QUIRINO | Region II | Region II | On-Going | ₱144.6M | 100% | High risk64 | —-0.009 |
| 19B00042OO 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: BRIDGE PROGRAM: REPLACEMENT OF PERMANENT WEAK BRIDGES: PINARIPAD BRIDGE (B01214LZ) ALONG CDMA (DALEMDEM-PINARIPAD-PALACIAN) BY-PASS ROAD, AGLIPAY, QUIRINO | Region II | Region II | Completed | ₱350M | 100% | High risk64 | Flagged0.013 |
| 19B00031ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: BRIDGE PROGRAM: CONSTRUCTION OF NEW PERMANENT BRIDGE: DISILUAD BRIDGE ALONG CORDON-AURORA BOUNDARY ROAD (ISABELA BDRY.-JCT. DUMABATO) (PARALLEL BRIDGE) B01939LZ, K0350+749, QUIRINO | Region II | Region II | Completed | ₱186.4M | 100% | High risk64 | —-0.003 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 19B00042OO 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: BRIDGE PROGRAM: REPLACEMENT OF PERMANENT WEAK BRIDGES: PINARIPAD BRIDGE (B01214LZ) ALONG CDMA (DALEMDEM-PINARIPAD-PALACIAN) BY-PASS ROAD, AGLIPAY, QUIRINO | Region II | Region II | Completed | ₱350M | 100% | High risk64 | Flagged0.013 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 20PJ0049LOCAL INFRASTRUCTURE PROGRAM- CONSTRUCTION OF LOCAL BRIDGE, INWALOY-EPENG-MAGULON | Cordillera Administrative Region | Ifugao 2nd DEO | Completed | ₱34.7M | 100% | High risk74 | —-0.017 |
| 2 | 24B00043OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT - CONSTRUCTION OF MISSING LINKS/ NEW ROADS - ARITAO-QUIRINO ROAD (UMASOK BR. AND APPROACHES), PACKAGE 2, QUIRINO | Region II | Region II | On-Going | ₱144.6M | 100% | High risk64 | —-0.009 |
| 3 | 19B00042OO 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: BRIDGE PROGRAM: REPLACEMENT OF PERMANENT WEAK BRIDGES: PINARIPAD BRIDGE (B01214LZ) ALONG CDMA (DALEMDEM-PINARIPAD-PALACIAN) BY-PASS ROAD, AGLIPAY, QUIRINO | Region II | Region II | Completed | ₱350M | 100% | High risk64 | Flagged0.013 |
| 4 | 19B00031ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: BRIDGE PROGRAM: CONSTRUCTION OF NEW PERMANENT BRIDGE: DISILUAD BRIDGE ALONG CORDON-AURORA BOUNDARY ROAD (ISABELA BDRY.-JCT. DUMABATO) (PARALLEL BRIDGE) B01939LZ, K0350+749, QUIRINO | Region II | Region II | Completed | ₱186.4M | 100% | High risk64 | —-0.003 |
| 5 | 23BK0064BRIDGE PROGRAM - REPLACEMENT OF PERMANENT WEAK BRIDGES - DUMABATO BR. (B04453LZ) ALONG DUMABATO-BALLIGUI RD, MADDELA, QUIRINO | Region II | Quirino DEO | Completed | ₱96.5M | 100% | Medium risk60 | —-0.031 |
| 6 | 20P00003ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS BANAUE - MAYOYAO - A. LISTA - ISABELA BDRY ROAD, KO341+(-880) - KO341+(-252), KO341+(-069) - KO348+187 | Cordillera Administrative Region | Cordillera Administrative Region | Completed | ₱116.5M | 100% | Medium risk57 | —-0.073 |
| 7 | 22P00043ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF MISSING LINKS/NEW ROADS - AGUINALDO - TOBOY - NATONIN ROADAGUINALDO IFUGAO | Cordillera Administrative Region | Cordillera Administrative Region | Completed | ₱118.2M | 100% | Medium risk57 | —-0.067 |
| 8 | 21P00039ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS BANAUE - HUNGDUAN - BENGUET BDRY ROAD, KO407+480 - KO | Cordillera Administrative Region | Cordillera Administrative Region | Completed | ₱114.1M | 100% | Medium risk56 | —-0.064 |
| 9 | 20PG0035REHABILITATION/RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDES ALONG NUEVA VIZCAYA-IFUGAO-MT. PROVINCE ROAD, KO296+000,KO296+1038-KO297+210,KO301+807-KO301+917,KO307+698,KO320+545-KO320+605,KO322+632,KO332+377-KO332+407,KO333+18 | Cordillera Administrative Region | Ifugao 1st DEO | Completed | ₱72M | 100% | Medium risk52 | —-0.079 |
| 10 | 23PJ001923PJ0019: CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF MAPACOPACO FLOOD CONTROL, STA. 41+902-STA. 42+170 (RS), STA. 42+667-STA. 43+527 (RS), POSNAAN AGUINALDO, IFUGAO | Cordillera Administrative Region | Ifugao 2nd DEO | Completed | ₱57.9M | 100% | Medium risk52 | —-0.068 |
| 11 | 24B00049OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: BRIDGE PROGRAM - CONSTRUCTION OF NEW BRIDGES - BUCAO BR. ALONG JCT ABBAG - NAGTIPUNAN - NUEVA VIZCAYA RD VIA DUPAX | Region II | Region II | On-Going | ₱48M | 95% | Medium risk49 | —-0.021 |
| 12 | 22PJ0009CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES-CONSTRUCTION OF NAMILLANGAN FLOOD CONTROL STA. 43+700-STA. 44+217.50 (R/S) NAMIL | Cordillera Administrative Region | Ifugao 2nd DEO | Completed | ₱49M | 100% | Medium risk48 | —-0.066 |
| 13 | 22BK0108BASIC INFRASTRUCTURE PROGRAM (BIP) - EVACUATION CENTERS/QUARANTINE FACILITIES/ PUBLIC HEALTH FACILITIES - CONSTRUCTION OF MULTI-PURPOSE BUILDING (EVACUATION CENTER) NAGABGABAN, AGLIPAY, QUIRINO | Region II | Quirino DEO | Completed | ₱4.9M | 100% | Medium risk47 | —-0.087 |
| 14 | 19BK0016CONSTRUCTION OF MULTI-PURPOSE BUILDING BRGY. SAN PUGO, NAGTIPUNAN, QUIRINO | Region II | Quirino DEO | Completed | ₱4.9M | 100% | Medium risk47 | —-0.088 |
| 15 | 18PG0078RESTORATION/REHABILITATION/IMPROVEMENT OF VARIOUS ROADSLIPS/SCOURING,BACKSLOPE PROTECTIONS AND DAMAGED PCCCP ALONG BANAUE-HUNGDUAN-BENGUET BDRY. ROAD,NUEVA VIZ.-IFUGAO-MT. PROV. BDRY. ROAD AND KIANGAN-TINOC-BUGUIAS BDRY. ROAD, INTERMITTENT SECTION, IFUGAO | Cordillera Administrative Region | Ifugao 1st DEO | Completed | ₱36.6M | 100% | Medium risk46 | —-0.085 |
| 16 | 23PJ0002ASSET PRESERVATION REHABILITATION/ CONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE- SECONDARY ROADS- BANAUE- MAYOYAO- ALFONSO LISTA- ISABELA BOUNDARY ROAD- K0359+047- K0359+127, BANAUE, IFUGAO | Cordillera Administrative Region | Ifugao 2nd DEO | Completed | ₱43.1M | 100% | Medium risk46 | —-0.084 |
| 17 | 21PG0002REHAB./RECONST'N. OF NATIONAL RDS. W/ SLIP, SLOPE COLLAPSE AND LANDSLIDE ALONG BAN-HUNG-BENG. BDRY. RD., K0384+(-717)-K0384+(-607), K0367+808-K0367+816, K0369+815-K0369+827, K0372+300-K0372+340, K0379+445-K0379+638, K0380+290-K0380+310, HUNGDUAN AND TINOC | Cordillera Administrative Region | Ifugao 1st DEO | Completed | ₱44.9M | 100% | Medium risk46 | —-0.078 |
| 18 | 20PG0034CONSTRUCTION OF BOLIWONG FLOOD CONTROL, LAGAWE, IFUGAO | Cordillera Administrative Region | Ifugao 1st DEO | Completed | ₱31M | 100% | Medium risk46 | —-0.068 |
| 19 | 23PJ0007NETWORK DEVELOPMENT PROGRAM-OFF CARRIAGEWAY IMPROVEMENT-SECONDARY ROADS-BANAUE-MAYOYAO-A. LISTA-ISABELA BDRY RD-K0411+400-K0411+498, K0411+630-K0415+000, AGUINALDO, IFUGAO | Cordillera Administrative Region | Ifugao 2nd DEO | Completed | ₱41.1M | 100% | Medium risk46 | —-0.083 |
| 20 | 19BK0055CONSTRUCTION OF FOOTBRIDGE BRGY. YSMAEL, MADDELA, QUIRINO | Region II | Quirino DEO | Completed | ₱4.9M | 100% | Medium risk45 | —-0.051 |
| 21 | 18BK0137CONSTRUCTION OF UNIQUE WORKSHOP BUILDING, CABARROGUIS NSAT BUILDING 2, CABARROGUIS (CAPITAL), QUIRINO | Region II | Quirino DEO | Completed | ₱4.9M | 100% | Medium risk44 | —-0.042 |
| 22 | 18BK0136CONSTRUCTION OF UNIQUE WORKSHOP BUILDING, CABARROGUIS NSAT BUILDING 1, CABARROGUIS (CAPITAL), QUIRINO | Region II | Quirino DEO | Completed | ₱4.9M | 100% | Medium risk44 | —-0.042 |
| 23 | 23BK0046BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/ OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION/IMPROVEMENT OF ROAD, PINARIPAD NORTE, AGLIPAY, QUIRINO | Region II | Quirino DEO | Completed | ₱4.9M | 100% | Medium risk43 | —-0.084 |
| 24 | 23BK0038BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/ OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJO/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION/IMPROVEMENT OF ROAD MATADI, NAGTIPUNAN, QUIRINO | Region II | Quirino DEO | Completed | ₱9.6M | 100% | Medium risk43 | —-0.083 |
| 25 | 19BK0053CONSTRUCTION OF FOOTBRIDGE BRGY. MAGSAYSAY, DIFFUN, QUIRINO | Region II | Quirino DEO | Completed | ₱3.5M | 100% | Low risk27 | —-0.049 |