Opening the dossier…
Opening the dossier…
Contractor dossier
71 projects on file, including joint ventures this contractor is part of.
Total projects
71
Total budget
₱1.7B
Average progress
99.9%
Completion rate
97.2%
Average risk score
29.5
Low risk on average, out of 100
Flagged as unusual
1
1.4% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region II | 53 | ₱929M | 25.1 | 1 | 99.9% |
| Cordillera Administrative Region | 18 | ₱771.5M | 42.2 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 30 | ₱63.4M | 19.7 | 0 | 100.0% |
| Roads | 20 | ₱616.1M | 35.2 | 0 | 100.0% |
| Bridges | 11 | ₱842.7M | 42.5 | 1 | 99.6% |
| Flood Control and Drainage | 6 | ₱141.7M | 33.9 | 0 | 100.0% |
| Water Provision and Storage | 3 | ₱1.9M | 18.2 | 0 | 100.0% |
| OTHER | 1 | ₱34.7M | 73.5 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 20PJ0049LOCAL INFRASTRUCTURE PROGRAM- CONSTRUCTION OF LOCAL BRIDGE, INWALOY-EPENG-MAGULON | Cordillera Administrative Region | Ifugao 2nd DEO | Completed | ₱34.7M | 100% | High risk74 | —-0.017 |
| 24B00043OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT - CONSTRUCTION OF MISSING LINKS/ NEW ROADS - ARITAO-QUIRINO ROAD (UMASOK BR. AND APPROACHES), PACKAGE 2, QUIRINO | Region II | Region II | On-Going | ₱144.6M | 100% | High risk64 | —-0.009 |
| 19B00042OO 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: BRIDGE PROGRAM: REPLACEMENT OF PERMANENT WEAK BRIDGES: PINARIPAD BRIDGE (B01214LZ) ALONG CDMA (DALEMDEM-PINARIPAD-PALACIAN) BY-PASS ROAD, AGLIPAY, QUIRINO | Region II | Region II | Completed | ₱350M | 100% | High risk64 | Flagged0.013 |
| 19B00031ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: BRIDGE PROGRAM: CONSTRUCTION OF NEW PERMANENT BRIDGE: DISILUAD BRIDGE ALONG CORDON-AURORA BOUNDARY ROAD (ISABELA BDRY.-JCT. DUMABATO) (PARALLEL BRIDGE) B01939LZ, K0350+749, QUIRINO | Region II | Region II | Completed | ₱186.4M | 100% | High risk64 | —-0.003 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 19B00042OO 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: BRIDGE PROGRAM: REPLACEMENT OF PERMANENT WEAK BRIDGES: PINARIPAD BRIDGE (B01214LZ) ALONG CDMA (DALEMDEM-PINARIPAD-PALACIAN) BY-PASS ROAD, AGLIPAY, QUIRINO | Region II | Region II | Completed | ₱350M | 100% | High risk64 | Flagged0.013 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 51 | 18PG0032CONSTRUCTION OF MULTIPURPOSE BUILDING AT HAPAO, HUNGDUAN, IFUGAO | Cordillera Administrative Region | Ifugao 1st DEO | Completed | ₱1.9M | 100% | Low risk17 | —-0.082 |
| 52 | 19BK0041REHABILITATION OF MULTI-PURPOSE BUILDING BRGY. VILLA PEÑA, CABARROGUIS, QUIRINO | Region II | Quirino DEO | Completed | ₱1.7M | 100% | Low risk14 | —-0.084 |
| 53 | 19BK0060REHABILITATION OF MULTI-PURPOSE BUILDING BRGY. CARDENAS, SAGUDAY, QUIRINO | Region II | Quirino DEO | Completed | ₱1.8M | 100% | Low risk14 | —-0.084 |
| 54 | 19BK0063CONSTRUCTION OF MULTI-PURPOSE BUILDING BRGY. BURGOS, CABARROGUIS, QUIRINO | Region II | Quirino DEO | Completed | ₱1.7M | 100% | Low risk14 | —-0.085 |
| 55 | 19BK0062CONSTRUCTION OF MULTI-PURPOSE BUILDING QPPO-SAN LEONARDO, AGLIPAY, QUIRINO | Region II | Quirino DEO | Completed | ₱1.2M | 100% | Low risk14 | —-0.082 |
| 56 | 18BK0112CONSTRUCTION OF MULTI-PURPOSE BUILDING YSMAEL, MADDELA, QUIRINO | Region II | Quirino DEO | Completed | ₱1.4M | 100% | Low risk14 | —-0.084 |
| 57 | 19BK0029CONSTRUCTION OF MULTI-PURPOSE BUILDING CALAOCAN I/S, CABARROGUIS, QUIRINO | Region II | Quirino DEO | Completed | ₱1.4M | 100% | Low risk14 | —-0.085 |
| 58 | 18BK0028CONSTRUCTION OF MULTI-PURPOSE BUILDING, QUIRINO DEO, MANGANDINGAY, CABARROGUIS, QUIRINO | Region II | Quirino DEO | Completed | ₱1.4M | 100% | Low risk14 | —-0.087 |
| 59 | 19BK0064CONSTRUCTION OF MULTI PURPOSE BUILDING (INDIGENOUS PEOPLES CENTER) BRGY. LANDINGAN, NAGTIPUNAN, QUIRINO | Region II | Quirino DEO | Completed | ₱1.5M | 100% | Low risk14 | —-0.087 |
| 60 | 19BK0037CONSTRUCTION (REPLACEMENT) OF MULTI-PURPOSE BUILDING BRGY. SAN FRANCISCO, AGLIPAY, QUIRINO | Region II | Quirino DEO | Completed | ₱1M | 100% | Low risk14 | —-0.080 |
| 61 | 19BK0085CONSTRUCTION OF MULTI-PURPOSE BUILDING (INDIGENOUS PEOPLES CENTER) BRGY. SAN LEONARDO, AGLIPAY, QUIRINO | Region II | Quirino DEO | Completed | ₱1.5M | 100% | Low risk14 | —-0.087 |
| 62 | 18BK0113CONSTRUCTION OF PERIMETER FENCE SAN ANTONIO, DIFFUN, QUIRINO | Region II | Quirino DEO | Completed | ₱969K | 100% | Low risk14 | —-0.080 |
| 63 | 19BK0013REHABILITATION OF MULTI-PURPOSE BUILDING BRGY. MAGSAYSAY, SAGUDAY, QUIRINO | Region II | Quirino DEO | Completed | ₱678.3K | 100% | Low risk14 | —-0.081 |
| 64 | 19BK0061REHABILITATION OF MULTI-PURPOSE BUILDING BRGY. RIZAL, SAGUDAY, QUIRINO | Region II | Quirino DEO | Completed | ₱550K | 100% | Low risk14 | —-0.081 |
| 65 | 19BK0010CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING BRGY. DON FAUSTINO PAGADUAN, DIFFUN, QUIRINO | Region II | Quirino DEO | Completed | ₱484.5K | 100% | Low risk14 | —-0.081 |
| 66 | 19BK0025CONSTRUCTION OF MULTI-PURPOSE BUILDING BRGY VILLAMOR, CABARROGUIS, QUIRINO | Region II | Quirino DEO | Completed | ₱969.5K | 100% | Low risk14 | —-0.084 |
| 67 | 19BK0040CONSTRUCTION OF MULTI-PURPOSE BUILDING, MADDELA COMPREHENSIVE HIGH SCHOOL, MADDELA, QUIRINO | Region II | Quirino DEO | Completed | ₱968.7K | 100% | Low risk14 | —-0.086 |
| 68 | 19BK0014CONSTRUCTION OF MULTI-PURPOSE BUILDING BRGY. DAGUPAN, AGLIPAY, QUIRINO | Region II | Quirino DEO | Completed | ₱484.6K | 100% | Low risk14 | —-0.082 |
| 69 | 17BK0156CONSTRUCTION OF ONE-STOREY TWO CLASSROOM SCHOOL BUILDING, CABARROGUIS CENTRAL SCHOOL, CABARROGUIS, QUIRINO | Region II | Quirino DEO | Completed | ₱2.6M | 100% | Low risk10 | —-0.023 |
| 70 | 17BK0155CONSTRUCTION OF ONE-STOREY TWO CLASSROOM SCHOOL BUILDING, BANUAR ELEMENTARY SCHOOL, CABARROGUIS, QUIRINO | Region II | Quirino DEO | Completed | ₱2.6M | 100% | Low risk10 | —-0.023 |
| 71 | 17BK0167CONSTRUCTION OF ONE-STOREY TWO CLASSROOM SCHOOL BUILDING, LIGAYA ELEMENTARY SCHOOL, AGLIPAY, QUIRINO | Region II | Quirino DEO | Completed | ₱2.6M | 100% | Low risk10 | —-0.022 |