Opening the dossier…
Opening the dossier…
Contractor dossier
44 projects on file, including joint ventures this contractor is part of.
Total projects
44
Total budget
₱825.2M
Average progress
91.4%
Completion rate
75.0%
Average risk score
41.8
Medium risk on average, out of 100
Flagged as unusual
1
2.3% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region VIII | 44 | ₱825.2M | 41.8 | 1 | 91.4% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 24 | ₱624.9M | 47.5 | 0 | 91.7% |
| Buildings and Facilities | 8 | ₱49.1M | 38.5 | 0 | 87.3% |
| Flood Control and Drainage | 6 | ₱141.2M | 38.9 | 0 | 97.7% |
| Bridges | 3 | ₱5M | 22.0 | 1 | 78.5% |
| Water Provision and Storage | 2 | ₱3M | 22.1 | 0 | 100.0% |
| OTHER | 1 | ₱1.9M | 47.6 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25IH0044CONSTRUCTION OF MULTIPURPOSE BUILDING (COVERED COURT), BRGY. WARD III, SAN ANTONIO NORTHERN SAMAR | Region VIII | Northern Samar 1st DEO | On-Going | ₱11.9M | 1% | High risk68 | —-0.006 |
| 17I00002IMPROVEMENT/WIDENING OF NATIONAL ROADS, ALLEN - CATARMAN ROAD (S00005SM), KO734+000 - KO739+290, NORTHERN SAMAR, 1ST LD | Region VIII | Region VIII | Completed | ₱144.7M | 100% | High risk64 | —-0.036 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 19IH0129CONSTRUCTION OF BRIDGE - CONSTRUCTION OF FOOT BRIDGE, PHASE I, GALUTAN NATIONAL HIGH SCHOOL (CATARMAN RIVER) TO BRGY. DOÑA PULQUERIA, CATARMAN, N. SAMAR | Region VIII | Northern Samar 1st DEO | On-Going | ₱2M | 36% | Low risk25 | Flagged0.023 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 26 | 22IH0002ROAD WIDENING - CATARMAN-CALBAYOG RD - K0771 + 010 - K0771 + 268, LOPE DE VEGA, NORTHERN SAMAR | Region VIII | Northern Samar 1st DEO | Completed | ₱7.9M | 100% | Medium risk47 | —-0.094 |
| 27 | 22IH0074CONSTRUCTION OF ROAD, SITIO CRYSTAL MOUNTAIN, BARANGAY SAN JOSE, MONDRAGON, NORTHERN SAMAR | Region VIII | Northern Samar 1st DEO | Completed | ₱4.9M | 100% | Medium risk47 | —-0.095 |
| 28 | 22IH0082CONSTRUCTION / UPGRADING / REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS CATARMAN-LAOANG RD - K0744 + (-100) - K0744 + 245, CATARMAN, NORTHERN SAMAR | Region VIII | Northern Samar 1st DEO | Completed | ₱5.3M | 100% | Medium risk47 | —-0.093 |
| 29 | 20IH0023CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BRGY. ZONE 2 AND BRGY. LOOC, ALLEN, N. SAMAR | Region VIII | Northern Samar 1st DEO | On-Going | ₱32.8M | 86% | Medium risk47 | —-0.010 |
| 30 | 22IH0003REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - POBLACION - BARANGAY CABACUNGAN ROAD- K0704+866 - K0704+914, ALLEN, NORTHERN SAMAR | Region VIII | Northern Samar 1st DEO | Completed | ₱7.3M | 100% | Medium risk47 | —-0.095 |
| 31 | 22IH0092CONSTRUCTION OF DRAINAGE CANAL, BARANGAY DAGANAS, CATARMAN, NORTHERN SAMAR | Region VIII | Northern Samar 1st DEO | Completed | ₱4.9M | 100% | Medium risk46 | —-0.080 |
| 32 | 17IH0004REHAB./RECONSTRUCTION/UPGRADING OF DAMAGED PAVED NATIONAL ROADS INCLUDING DRAINAGE ALONG POBLACION - BRGY. CABACUNGAN ROAD, K0699+(-971) - K0699+(-876), ALLEN, N. SAMAR | Region VIII | Northern Samar 1st DEO | Completed | ₱2.7M | 100% | Medium risk38 | —-0.058 |
| 33 | 24IH0027CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, PHASE II, BARANGAY CAHICSAN, MONDRAGON, NORTHERN SAMAR | Region VIII | Northern Samar 1st DEO | On-Going | ₱2M | 100% | Low risk26 | —-0.051 |
| 34 | 19IH0129CONSTRUCTION OF BRIDGE - CONSTRUCTION OF FOOT BRIDGE, PHASE I, GALUTAN NATIONAL HIGH SCHOOL (CATARMAN RIVER) TO BRGY. DOÑA PULQUERIA, CATARMAN, N. SAMAR | Region VIII | Northern Samar 1st DEO | On-Going | ₱2M | 36% | Low risk25 | Flagged0.023 |
| 35 | 19IH0027LOCAL INFRASTRUCTURE PROJECT - CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. DALUPIRIT, SAN ANTONIO, NORTHERN SAMAR | Region VIII | Northern Samar 1st DEO | Completed | ₱2.6M | 100% | Low risk25 | —-0.097 |
| 36 | 23IH0116CONSTRUCTION OF MONDRAGON BANTAYAN OLD ROAD SHORE PROTECTION, MONDRAGON, NORTHERN SAMAR | Region VIII | Northern Samar 1st DEO | Completed | ₱3.9M | 100% | Low risk23 | —-0.080 |
| 37 | 22IH0043CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, PHASE II, BARANGAY SAN LAZARO, VICTORIA, NORTHERN SAMAR | Region VIII | Northern Samar 1st DEO | Completed | ₱1.9M | 100% | Low risk23 | —-0.095 |
| 38 | 20IH0096CONSTRUCTION OF LEVEL II WATER SUPPLY SYSTEM, BRGY. LIPATA, ALLEN, NORTHERN SAMAR | Region VIII | Northern Samar 1st DEO | Completed | ₱1.5M | 100% | Low risk22 | —-0.062 |
| 39 | 21IH0068CONSTRUCTION/REHABILITATION OF WATER SUPPLY LEVEL II, BARANGAY TASVILLA, ALLEN, NORTHERN SAMAR | Region VIII | Northern Samar 1st DEO | Completed | ₱1.6M | 100% | Low risk22 | —-0.063 |
| 40 | 22IH0090REHABILITATION/MAJOR REPAIR OF PERMANENT BRIDGES - SABANG BR.(B00278SM) ALONG ALLEN - CATARMAN RD., LAVEZARES, NORTHERN SAMAR | Region VIII | Northern Samar 1st DEO | Completed | ₱1.9M | 100% | Low risk21 | —-0.058 |
| 41 | 22IH0072REHABILITATION/MAJOR REPAIR OF PERMANENT BRIDGES LAMOD BR. (B00286SM) ALONG ALLEN-CATARMAN RD. ROSARIO, NORTHERN SAMAR | Region VIII | Northern Samar 1st DEO | Completed | ₱1.1M | 100% | Low risk20 | —-0.058 |
| 42 | 20IH0088CONSTRUCTION OF DRAINAGE SYSTEM AT BRGY. SABANG ZONE I, ALLEN, NORTHERN SAMAR | Region VIII | Northern Samar 1st DEO | Completed | ₱1.7M | 100% | Low risk19 | —-0.080 |
| 43 | 18IH0008PAVING OF UNPAVED ROADS POBLACION - BARANGAY BONIFACIO RD. K0701+762-K0701+8004, ALLEN, N. SAMAR | Region VIII | Northern Samar 1st DEO | Completed | ₱1.9M | 100% | Low risk19 | —-0.095 |
| 44 | 19IH0044CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BRGY. SAWANG, CAPUL, NORTHERN SAMAR | Region VIII | Northern Samar 1st DEO | Completed | ₱1.5M | 100% | Low risk15 | —-0.097 |