Contractor dossier
100 projects on file, including joint ventures this contractor is part of.
Total projects
100
Total budget
₱1.6B
Average progress
95.6%
Completion rate
91.0%
Average risk score
40.0
Medium risk on average, out of 100
Flagged as unusual
2
2.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| National Capital Region | 83 | ₱1.3B | 41.0 | 2 | 95.0% |
| Region IV-A | 7 | ₱182.3M | 49.0 | 0 | 100.0% |
| Region IV-B | 7 | ₱115.4M | 31.5 | 0 | 95.5% |
| Region III | 3 | ₱7.1M | 11.1 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 37 | ₱435.5M | 38.8 | 0 | 99.1% |
| Buildings and Facilities | 34 | ₱629.9M | 35.1 | 0 | 93.5% |
| Flood Control and Drainage | 17 | ₱330M | 44.1 | 0 | 97.2% |
| OTHER | 10 | ₱173.3M | 50.2 | 1 | 95.1% |
| GAA 2025 SSP | 1 | ₱19.4M | 93.4 | 1 | 5.3% |
| Water Provision and Storage | 1 | ₱4.3M | 24.9 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25OC0137CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY SAN ISIDRO,PARAÑAQUE CITY, METRO MANILA | National Capital Region | Metro Manila 2nd DEO | On-Going | ₱19.4M | 5% | High risk93 | Flagged0.030 |
| 24OA0086CONSTRUCTION OF FOUR (4) STOREY, EIGHT (8) CLASSROOM SCHOOL BUILDING, NINOY AQUINO ELEMENTARY SCHOOL, MALABON CITY | National Capital Region | Malabon-Navotas DEO | On-Going | ₱42.9M | 51% | High risk74 | Flagged0.054 |
| 23DD0189CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF ROAD MARAWOY-SABANG, LIPA | Region IV-A | Batangas 4th DEO | Completed | ₱51.5M | 100% | High risk70 | —-0.037 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24OA0086CONSTRUCTION OF FOUR (4) STOREY, EIGHT (8) CLASSROOM SCHOOL BUILDING, NINOY AQUINO ELEMENTARY SCHOOL, MALABON CITY | National Capital Region | Malabon-Navotas DEO | On-Going | ₱42.9M | 51% | High risk74 | Flagged0.054 |
| 25OC0137CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY SAN ISIDRO,PARAÑAQUE CITY, METRO MANILA | National Capital Region | Metro Manila 2nd DEO | On-Going | ₱19.4M | 5% | High risk93 | Flagged0.030 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25OC0137CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY SAN ISIDRO,PARAÑAQUE CITY, METRO MANILA | National Capital Region | Metro Manila 2nd DEO | On-Going | ₱19.4M | 5% | High risk93 | Flagged0.030 |
| 2 | 24OA0086CONSTRUCTION OF FOUR (4) STOREY, EIGHT (8) CLASSROOM SCHOOL BUILDING, NINOY AQUINO ELEMENTARY SCHOOL, MALABON CITY | National Capital Region | Malabon-Navotas DEO | On-Going | ₱42.9M | 51% | High risk74 | Flagged0.054 |
| 3 | 23DD0189CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF ROAD MARAWOY-SABANG, LIPA | Region IV-A | Batangas 4th DEO | Completed | ₱51.5M | 100% | High risk70 | —-0.037 |
| 4 | 24OD0194CONSTRUCTION OF MULTI-PURPOSE BUILDING, (3S COMPLETION, LEARNING CENTER, VALACE) GEN. T. DE LEON VALENZUELA CITY | National Capital Region | Metro Manila 3rd DEO | On-Going | ₱77.7M | 91% | Medium risk59 | —-0.046 |
| 5 | 20OD0221CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. GEN. T. DE LEON, VALENZUELA CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱48.3M | 100% | Medium risk56 | —-0.094 |
| 6 | 24OC0109CONSTRUCTION OF FLOOD MITIGATION STRUCTURE AT VILLANUEVA CREEK NEAR VALLEY 2, BRGY. SAN ISIDRO,PARAÑAQUE CITY, METRO MANILA | National Capital Region | Metro Manila 2nd DEO | On-Going | ₱69.5M | 66% | Medium risk53 | —-0.036 |
| 7 | 21OA0041CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. LONGOS, MALABON CITY | National Capital Region | Malabon-Navotas DEO | Completed | ₱38.2M | 100% | Medium risk52 | —-0.098 |
| 8 | 25OA0089CONSTRUCTION OF SCHOOL BUILDING, DAGAT-DAGATAN ELEMENTARY SCHOOL, NAVOTAS CITY | National Capital Region | Malabon-Navotas DEO | On-Going | ₱29.1M | 32% | Medium risk52 | —-0.045 |
| 9 | 20OD0081REHABILITATION OF ROADS AND DRIANAGE ALONG BAHAYANG PAG-ASA, BRGY. MAYSAN, VALENZUELA CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱46.9M | 100% | Medium risk51 | —-0.095 |
| 10 | 16OD0097REHABILITATION OF ROADS WITH DRAINAGE IMPROVEMENT ALONG 4TH AVENUE (FROM RIZAL AVE. TO 2ND ST.), CALOOCAN CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱11M | 100% | Medium risk50 | —-0.045 |
| 11 | 16OE0119MFO-1 NATIONAL ROAD NETWORK SERVICES REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED NATIONAL ROADS INCLUDING DRAINAGE BASED ON PAVEMENT MANAGEMENT SYSTEM HIGHWAY-4, H. LOPEZ BLVD., K0006+383.50 TO K0006+611.25 MANILA CITY | National Capital Region | North Manila DEO | Completed | ₱18.8M | 100% | Medium risk50 | —-0.043 |
| 12 | 18OD0160IMPROVEMENT OF ROAD AND DRAINAGE SYSTEM-BALUBARAN ROAD, BRGY. MALINTA (FROM MAC ARTHUR HW BALUBARAN TO ZAPRA ST., BRGY. MAYSAN TO T. SANTIAGO ST.), BRGY. VEINTE REALES, VALENZUELA CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱19.9M | 100% | Medium risk50 | —-0.041 |
| 13 | 18OD0121UPGRADING OF BALUBARAN ROAD 1 & 2, VALENZUELA CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱10M | 100% | Medium risk50 | —-0.043 |
| 14 | 16OD0093REHABILITATION OF ROADS WITH DRAINAGE IMPROVEMENT ALONG 3RD AVENUE (FROM RIZAL AVENUE TO 2ND ST.), CALOOCAN CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱8.2M | 100% | Medium risk49 | —-0.045 |
| 15 | 16OD0087REHABILITATION / RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED NATIONAL ROADS INCLUDING DRAINAGE BASED ON PAVEMENT MANAGEMENT SYSTEM / HIGHWAY-4, B. SERRANO ST., CALOOCAN CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱7.6M | 100% | Medium risk49 | —-0.069 |
| 16 | 22OC0193CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY DON GALO,PARAÑAQUE CITY, METRO MANILA | National Capital Region | Metro Manila 2nd DEO | Completed | ₱12.4M | 100% | Medium risk49 | —-0.097 |
| 17 | 24OC0073CONSTRUCTION OF MULTI-PURPOSE BUILDING, J.P RIZAL ST. (PHASE 2), BARANGAY STO. NIÑO, PARAÑAQUE CITY, METRO MANILA | National Capital Region | Metro Manila 2nd DEO | On-Going | ₱19.2M | 56% | Medium risk49 | —-0.042 |
| 18 | 18OA0046CONST./IMPVT./SEALING OF RIVERWALL INCL. UPGR. OF ROAD DIKE W/ DRAIN. IMPVT ALONG MAL-TULLAHAN RIVER | National Capital Region | Malabon-Navotas DEO | Completed | ₱49M | 100% | Medium risk49 | —-0.087 |
| 19 | 23OC0050CONSTRUCTION OF 2-STOREY TAMBO MULTI-PURPOSE BUILDING (BARANGAY HALL), BARANGAY TAMBO,PARAÑAQUE CITY, METRO MANILA | National Capital Region | Metro Manila 2nd DEO | On-Going | ₱10.6M | 0% | Medium risk49 | —-0.021 |
| 20 | 21OG0092CONSTRUCTION OF TWO STOREY MALE BARRACKS OF HCTIF, ISAFP, CAMP AGUINALDO, QUEZON CITY | National Capital Region | Quezon City 2nd DEO | Completed | ₱4.9M | 100% | Medium risk47 | —-0.102 |
| 21 | 19OD0251CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY 18, CALOOCAN CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱6.1M | 100% | Medium risk47 | —-0.096 |
| 22 | 18OA0115CONST. OF FOUR(4) STOREY TWELVE(12) CL. RM. SB, ACACIA ELEM. SCHOOL, MALABON CITY | National Capital Region | Malabon-Navotas DEO | Completed | ₱40M | 100% | Medium risk47 | —-0.040 |
| 23 | 21DD0264LOCAL PROGRAM, LOCAL INFRASTRUCTURE PROGRAM, LOCAL ROADS AND BRIDGES, LOCAL ROADS, CONSTRUCTION/ REHABILITATION/ IMPROVEMENT OF ROAD AT BARANGAY BALINTAWAK, BULACNIN, DAGATAN, LUMBANG AND TALISAY, LIPA CITY, BATANGAS | Region IV-A | Batangas 4th DEO | Completed | ₱28.8M | 100% | Medium risk47 | —-0.107 |
| 24 | 22DD0247CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF ROAD, BARANGAY BULACNIN, LIPA CITY, BATANGAS | Region IV-A | Batangas 4th DEO | Completed | ₱43.3M | 100% | Medium risk47 | —-0.106 |
| 25 | 22DD0325CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), INTERJURISDICTIONAL ROADS AND/OR BRIDGE (OR, ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS), REHABILITATION OF ROSARIO-TAYSAN RD, BATANGAS | Region IV-A | Batangas 4th DEO | Completed | ₱28.8M | 100% | Medium risk47 | —-0.109 |