Contractor dossier
517 projects on file, including joint ventures this contractor is part of.
Total projects
517
Total budget
₱34.1B
Average progress
91.8%
Completion rate
82.4%
Average risk score
54.9
Medium risk on average, out of 100
Flagged as unusual
56
10.8% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region V | 127 | ₱7.7B | 58.0 | 7 | 97.4% |
| Region III | 112 | ₱6B | 50.1 | 13 | 89.3% |
| National Capital Region | 72 | ₱3.9B | 52.1 | 2 | 95.0% |
| Region IV-A | 50 | ₱3.8B | 59.2 | 10 | 77.4% |
| Region IV-B | 45 | ₱3.4B | 51.1 | 2 | 99.1% |
| Region I | 32 | ₱2.3B | 55.1 | 3 | 87.9% |
| Region II | 29 | ₱1.9B | 53.2 | 4 | 99.0% |
| Negros Island Region | 11 | ₱1.5B | 77.3 | 9 | 52.1% |
| Cordillera Administrative Region | 11 | ₱1.1B | 59.3 | 1 | 99.5% |
| Region VI | 7 | ₱399.9M | 57.2 | 2 | 76.3% |
| Region XI | 4 | ₱772.6M | 58.0 | 0 | 100.0% |
| Region X | 4 | ₱414.3M | 56.1 | 0 | 100.0% |
| Region VII | 4 | ₱311.8M | 55.1 | 0 | 100.0% |
| Region XII | 3 | ₱288.5M | 71.4 | 3 | 75.6% |
| Region VIII | 3 | ₱169.3M | 51.6 | 0 | 100.0% |
| Region XIII | 3 | ₱337M | 45.2 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Flood Control and Drainage | 164 | ₱10.5B | 55.3 | 22 | 90.4% |
| Roads | 155 | ₱12.8B | 55.5 | 4 | 91.8% |
| Buildings and Facilities | 95 | ₱3.9B | 47.4 | 12 | 93.9% |
| Bridges | 66 | ₱3.7B | 53.3 | 3 | 95.0% |
| OTHER | 19 | ₱1.6B | 73.7 | 9 | 95.3% |
| Water Provision and Storage | 8 | ₱344.3M | 62.2 | 2 | 83.5% |
| Bridges, Roads | 6 | ₱968.3M | 66.2 | 0 | 71.2% |
| GAA 2025 SSP | 3 | ₱228.7M | 95.0 | 3 | 85.2% |
| GAA 2025 OO-2 | 1 | ₱141.1M | 93.7 | 1 | 50.3% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25CL0061CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURE ALONG TAKAR RIVER PHASE 6, IBA, ZAMBALES | Region III | Zambales 1st DEO | On-Going | ₱97.5M | 82% | High risk95 | Flagged0.014 |
| 25CL0062CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURE ALONG TAKAR RIVER PHASE 7, IBA, ZAMBALES | Region III | Zambales 1st DEO | On-Going | ₱97.5M | 95% | High risk95 | Flagged0.011 |
| 25OA0016CONSTRUCTION OF R-10 PUMPING STATION, NAVOTAS CITY | National Capital Region | Malabon-Navotas DEO | On-Going | ₱33.6M | 78% | High risk94 | Flagged0.008 |
| 25HK0058ORGANIZATIONAL OUTCOME 2:PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-REHABILITATION OF FLOOD CONTROL STRUCTURE (RIGHT SIDE), BARANGAY CABANLUTAN,BA | Negros Island Region | Negros Oriental 2nd DEO | On-Going | ₱141.1M | 50% | High risk94 | Flagged0.005 |
| 24FL0113CONSTRUCTION OF REVETMENT AT SAN RAMON, DOWNSTREAM PHASE 4, BULAN, SORSOGON | Region V | Sorsogon 2nd DEO | On-Going | ₱141.4M | 99% | High risk92 | Flagged0.054 |
| 24DD0308CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING AT PINAGKAWITAN NATIONAL HIGH SCHOOL, BARANGAY PINAGKAWITAN, LIPA CITY, BAT | Region IV-A | Batangas 4th DEO | On-Going | ₱78.7M | 54% | High risk87 | Flagged0.055 |
| 17DD0194DRAINAGE IMPROVEMENT, ROSARIO-SAN JUAN ROAD (S01926LZ), K0126 + 774.00 - K0128 + 649.00; K0128 + 649.00 - K0130 + 638.00 | Region IV-A | Batangas 4th DEO | Completed | ₱98M | 100% | High risk83 | Flagged0.022 |
| 24GA0248CONSTRUCTION OF PUMPING STATION AT BRGY. POBLACION, KALIBO, AKLAN | Region VI | Aklan DEO | On-Going | ₱96.2M | 3% | High risk83 | Flagged0.070 |
| 24FE0022OO2: FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF DIKE ALONG BICOL RIVER BASIN, ISLA MATUNGAW, MILAOR, CAMARINES SUR | Region V | Camarines Sur 2nd DEO | On-Going | ₱125.4M | 99% | High risk82 | Flagged0.008 |
| 23BD0041BASIC INFRASTRUCTURE PROGRAM - MULTI- PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, TUGUEGARAO EAST CENTRAL SCHOOL, TUGUEGARAO CITY, CAGAYAN | Region II | Cagayan 3rd DEO | On-Going | ₱49.4M | 72% | High risk82 | Flagged0.025 |
| 24MC0028CONSTRUCTION OF REVETMENT ALONG MARBOL RIVER STA. 21 + 900 - STA. 22 + 700 R/S, BARANGAY NEW CEBU, PRES. ROXAS, COTABATO (REPUBLISHED) | Region XII | Cotabato 2nd DEO | On-Going | ₱96.5M | 94% | High risk81 | Flagged0.017 |
| 24MC0027CONSTRUCTION OF REVETMENT ALONG MARBOL RIVER STA. 21 + 400 - STA. 22 + 200 L/S, BARANGAY NEW CEBU, PRES. ROXAS, COTABATO (REPUBLISHED) | Region XII | Cotabato 2nd DEO | On-Going | ₱96.5M | 93% | High risk81 | Flagged0.017 |
| 25CL0079CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURE ALONG BAYTO RIVER, PHASE 3, SANTA CRUZ, ZAMBALES | Region III | Zambales 1st DEO | On-Going | ₱95.1M | 25% | High risk81 | Flagged0.005 |
| 25CL0080CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURE ALONG BAYTO RIVER, PHASE 4, SANTA CRUZ, ZAMBALES | Region III | Zambales 1st DEO | On-Going | ₱95.1M | 39% | High risk81 | Flagged0.000 |
| 24CL0078CONSTRUCTION OF MALOMA RIVER FLOOD CONTROL STRUCTURE, UPSTREAM, PACKAGE 3, SAGPAT SECTION, SAN FELIPE, ZAMBALES | Region III | Zambales 1st DEO | Completed | ₱95.2M | 100% | High risk81 | —-0.043 |
| 24CL0077CONSTRUCTION OF MALOMA RIVER FLOOD CONTROL STRUCTURE, UPSTREAM, PACKAGE 2, SAGPAT SECTION, SAN FELIPE, ZAMBALES | Region III | Zambales 1st DEO | Completed | ₱95.2M | 100% | High risk81 | —-0.043 |
| 24CL0079CONSTRUCTION OF MALOMA RIVER FLOOD CONTROL STRUCTURE, UPSTREAM, PACKAGE 4, SAGPAT SECTION, SAN FELIPE, ZAMBALES | Region III | Zambales 1st DEO | Completed | ₱95.3M | 100% | High risk81 | —-0.043 |
| 25CC0329CONSTRUCTION OF PUMPING STATION INCLUDING FLOOD GATE (PHASE II) AT BARANGAY ATLAG, MALOLOS CITY, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱92.7M | 34% | High risk81 | —-0.004 |
| 24CC0548CONSTRUCTION OF FLOOD CONTROL STRUCTURE INCLUDING PUMPING STATION AND FLOOD GATE AT BARANGAY SANTO ROSARIO, MALOLOS CITY, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱92.6M | 0% | High risk81 | Flagged0.008 |
| 24CC0547CONSTRUCTION OF FLOOD CONTROL STRUCTURE INCLUDING PUMPING STATION AND FLOOD GATE AT BARANGAY CALERO CREEK, MALOLOS CITY, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱92.6M | 51% | High risk81 | —-0.006 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24GA0248CONSTRUCTION OF PUMPING STATION AT BRGY. POBLACION, KALIBO, AKLAN | Region VI | Aklan DEO | On-Going | ₱96.2M | 3% | High risk83 | Flagged0.070 |
| 24DD0308CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING AT PINAGKAWITAN NATIONAL HIGH SCHOOL, BARANGAY PINAGKAWITAN, LIPA CITY, BAT | Region IV-A | Batangas 4th DEO | On-Going | ₱78.7M | 54% | High risk87 | Flagged0.055 |
| 24FL0113CONSTRUCTION OF REVETMENT AT SAN RAMON, DOWNSTREAM PHASE 4, BULAN, SORSOGON | Region V | Sorsogon 2nd DEO | On-Going | ₱141.4M | 99% | High risk92 | Flagged0.054 |
| 24DD0277ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM, CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, CONSTRUCTION OF LIPA CITY-MATAAS NA KAHOY DIVERSION RD. LEADING TO TAAL CIRCUMFERENTIAL ROAD PHASE 7, BATAN | Region IV-A | Batangas 4th DEO | On-Going | ₱187.4M | 0% | High risk69 | Flagged0.040 |
| 24DD0275ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM, CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, CONSTRUCTION OF LIPA CITY-MATAAS NA KAHOY DIVERSION RD. LEADING TO TAAL CIRCUMFERENTIAL ROAD PHASE 5, BATAN | Region IV-A | Batangas 4th DEO | On-Going | ₱187.4M | 0% | High risk69 | Flagged0.040 |
| 17DF0096CONSTRUCTION OF 4STY 12CL SCHOOL BUILDING AT HALAYHAY ES, TANZA, CAVITE | Region IV-A | Cavite 1st DEO | On-Going | ₱31.7M | 98% | Medium risk46 | Flagged0.039 |
| 17AA0616CONST. OF 1 UNIT 4 STOREY 20 CL, 2 UNITS 2 STOREY 8 CL, 2 UNITS 2 STOREY 4 CL SCHOOL BUILDING LAOAG | Region I | Ilocos Norte 1st DEO | Completed | ₱110.1M | 100% | Medium risk58 | Flagged0.032 |
| 24FL0117CONST. OF FLOOD MITIGATION STRUCTURE (REVETMENT) ALONG MARINAB RIVER AT BARANGAY MARINAB, BULAN, SOR | Region V | Sorsogon 2nd DEO | On-Going | ₱95.4M | 44% | High risk80 | Flagged0.028 |
| 25E00132CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF FLOOD CONTROL STRUCTURE, STO. NINO RIVER WATERWAYS ALONG ARAMAYWAN-BERONG-PTO. PRINCESA ROAD, PALAWAN | Region IV-B | Region IV-B | On-Going | ₱161.8M | 81% | High risk76 | Flagged0.027 |
| 23BD0041BASIC INFRASTRUCTURE PROGRAM - MULTI- PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, TUGUEGARAO EAST CENTRAL SCHOOL, TUGUEGARAO CITY, CAGAYAN | Region II | Cagayan 3rd DEO | On-Going | ₱49.4M | 72% | High risk82 | Flagged0.025 |
| 24FL0118CONST, OF FLOOD MITIGATION STRUCTURE (REVETMENT) ALOBNG QUEZON (CABARAWAN) RIVER AT BARANGAY QUEZON | Region V | Sorsogon 2nd DEO | On-Going | ₱95.5M | 66% | High risk80 | Flagged0.025 |
| 24DD0276ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM, CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, CONSTRUCTION OF LIPA CITY-MATAAS NA KAHOY DIVERSION RD. LEADING TO TAAL CIRCUMFERENTIAL ROAD PHASE 6, BATAN | Region IV-A | Batangas 4th DEO | On-Going | ₱187.4M | 61% | High risk69 | Flagged0.024 |
| 17DD0194DRAINAGE IMPROVEMENT, ROSARIO-SAN JUAN ROAD (S01926LZ), K0126 + 774.00 - K0128 + 649.00; K0128 + 649.00 - K0130 + 638.00 | Region IV-A | Batangas 4th DEO | Completed | ₱98M | 100% | High risk83 | Flagged0.022 |
| 23AH0162CLUSTER NO. I - CONVERGENCE AND SPECIAL SUPPORT PROGRAM- CONSTRUCTION/ REHABILITATION OF WATER SUPPLY/ SEPTAGE AND SEWERAGE/ RAIN WATER COLLECTORS WATER SUPPLY SYSTEM: 1. CONSTRUCTION OF SOLAR WATER SYSTEM IN THE MUNICIPALITY OF SAN FABIAN, PANGASINAN; 2. | Region I | Pangasinan 2nd DEO | On-Going | ₱39.2M | 17% | Medium risk47 | Flagged0.021 |
| 24CC0568CONSTRUCTION OF 4STY8CL, SAN ROQUE NATIONAL HS, PAOMBONG, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱40.3M | 58% | Medium risk54 | Flagged0.020 |
| 24CC0544CONSTRUCTION OF 4STY 8CL, MATIAS B. SALVADOR MEMORIAL ELEMENTARY SCHOOL, PANDI, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱41.3M | 66% | Medium risk48 | Flagged0.019 |
| 25G00078CONSTRUCTION OF RIVER CONTROL ALONG PANAY RIVER BASIN, BARANGAY BITOON ILAWOD TO BARANGAY POBLACION ILAYA, CUARTERO, CAPIZ | Region VI | Region VI | On-Going | ₱150.7M | 31% | High risk80 | Flagged0.019 |
| 23E00078SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONST. OF BULILUYAN SHORE PROTECTION AND CAUSEWAY DEVELOPMENT, BATARAZA, PALAWAN | Region IV-B | Region IV-B | On-Going | ₱120.6M | 77% | High risk62 | Flagged0.018 |
| 24MC0028CONSTRUCTION OF REVETMENT ALONG MARBOL RIVER STA. 21 + 900 - STA. 22 + 700 R/S, BARANGAY NEW CEBU, PRES. ROXAS, COTABATO (REPUBLISHED) | Region XII | Cotabato 2nd DEO | On-Going | ₱96.5M | 94% | High risk81 | Flagged0.017 |
| 24MC0027CONSTRUCTION OF REVETMENT ALONG MARBOL RIVER STA. 21 + 400 - STA. 22 + 200 L/S, BARANGAY NEW CEBU, PRES. ROXAS, COTABATO (REPUBLISHED) | Region XII | Cotabato 2nd DEO | On-Going | ₱96.5M | 93% | High risk81 | Flagged0.017 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 376 | 18OB0447RECONSTRUCTION OF BRIDGE ALONG WILSON STREET, INCLUDING DRAINAGE LATERALS, SAN JUAN CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱31.9M | 100% | Medium risk48 | —-0.048 |
| 377 | 18OI0185CONST. OF FOUR (4) STOREY, SIXTEEN (16) CLASSROOM S/B AT MUNTINLUPA NATIONAL H/S, BRGY. POBLACION, | National Capital Region | Las Piñas-Muntinlupa DEO | Completed | ₱39.1M | 100% | Medium risk48 | —-0.044 |
| 378 | 18DN0162LOCAL INFRASTRUCTURE PROGRAM, LOCAL BRIDGES CONSTRUCTION OF BRIDGE CONNECTING BRGY. IBABA AND BRGY. SAN VICENTE, ANGONO, RIZAL | Region IV-A | Rizal 1st DEO | Completed | ₱19M | 100% | Medium risk48 | —-0.067 |
| 379 | 21DP0032BRIDGE PROGRAM - RETROFITTING/STRENGTHENING OF PERMANENT BRIDGES - MASAPANG BR. (B02882LZ) ALONG CALAMBA-STA. CRUZ-FAMY JCTN. RD | Region IV-A | Laguna 3rd DEO | Completed | ₱14.7M | 100% | Medium risk47 | —-0.067 |
| 380 | 17OH0018PROPOSED RETROFITTING/STRENGTHENING OF PERMANENT BRIDGES,NAGTAHAN LINK BRIDGE 1 (BO0570LZ)ALONG NAGT | National Capital Region | South Manila DEO | Completed | ₱13.9M | 100% | Medium risk47 | —-0.043 |
| 381 | 16OG0214IMPROVEMENT/ REHABILITATION OF DRAINAGE SYSTEM AND BUAYA CREEK, BRGY. CLARO (QUIRINO 3-B), QC | National Capital Region | Quezon City 2nd DEO | Completed | ₱18.5M | 100% | Medium risk47 | —-0.065 |
| 382 | 21DP0039BRIDGE PROGRAM - RETROFITTING/STRENGTHENING OF PERMANENT BRIDGES - CALAUAN BR. (B02880LZ) ALONG CALAMBA-STA. CRUZ-FAMY JCTN. RD | Region IV-A | Laguna 3rd DEO | Completed | ₱14.7M | 100% | Medium risk47 | —-0.068 |
| 383 | 16OG0209IMPROVEMENT/ REHABILITATION OF DRAINAGE SYSTEM AT BRGY. QUIRINO 3-A, QUEZON CITY | National Capital Region | Quezon City 2nd DEO | Completed | ₱13.9M | 100% | Medium risk47 | —-0.065 |
| 384 | 21DP0031BRIDGE PROGRAM - RETROFITTING/STRENGTHENING OF PERMANENT BRIDGES - LILIW BR. (B00080LZ) ALONG SAN PABLO-RIZAL-NAGCARLAN-LILIW RD | Region IV-A | Laguna 3rd DEO | Completed | ₱12.7M | 100% | Medium risk47 | —-0.067 |
| 385 | 19OE0186LOCAL PROGRAM - CONSTRUCTION / REPAIR / REHABILITATION / IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS - NATIONAL ROADS AND BRIDGES - NATIONAL ROAD - REHABILITATION / RECONSTRUCTION / UPGRADING OF RIZAL AVE. MANILA CITY | National Capital Region | North Manila DEO | Completed | ₱39.2M | 100% | Medium risk47 | —-0.099 |
| 386 | 18OA0106CONST. OF 4 STOREY 12 CL. RM. SCHOOL BLDG. TANGOS ES 1, NAVOTAS CITY | National Capital Region | Malabon-Navotas DEO | Completed | ₱40.7M | 100% | Medium risk47 | —-0.041 |
| 387 | 23AH0162CLUSTER NO. I - CONVERGENCE AND SPECIAL SUPPORT PROGRAM- CONSTRUCTION/ REHABILITATION OF WATER SUPPLY/ SEPTAGE AND SEWERAGE/ RAIN WATER COLLECTORS WATER SUPPLY SYSTEM: 1. CONSTRUCTION OF SOLAR WATER SYSTEM IN THE MUNICIPALITY OF SAN FABIAN, PANGASINAN; 2. | Region I | Pangasinan 2nd DEO | On-Going | ₱39.2M | 17% | Medium risk47 | Flagged0.021 |
| 388 | 24GA0176CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, PANAYAKAN, TANGALAN, AKLAN | Region VI | Aklan DEO | Completed | ₱5M | 100% | Medium risk47 | —-0.083 |
| 389 | 24DE0201ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM, PREVENTIVE MAINTENANCE - SECONDARY ROADS, BATANGAS PORT DIVERSION RD - K0167+130 - K0167+300 | Region IV-A | Batangas 2nd DEO | On-Going | ₱42.3M | 1% | Medium risk47 | —-0.039 |
| 390 | 18DO0055ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG MANGO RIVER, RODRIGUEZ, RIZAL | Region IV-A | Rizal 2nd DEO | Completed | ₱28.2M | 100% | Medium risk47 | —-0.088 |
| 391 | 17DF0162CONSTRUCTION OF 4STY 20CL SCHOOL BUILDING AT EMILIANO T. TIRONA MNHS, KAWIT, CAVITE | Region IV-A | Cavite 1st DEO | Completed | ₱41.2M | 100% | Medium risk47 | —-0.024 |
| 392 | 22C00069ASSET PRESERVATION PROGRAM-REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE-SECONDARY ROADS, NUEVA ECIJA-AURORA ROAD, PROVINCE OF AURORA | Region III | Region III | Completed | ₱125.4M | 100% | Medium risk47 | —-0.081 |
| 393 | 23C00145CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM-MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, REHABILITATION OF MUNICIPAL BUILDING (PHASE II), OBANDO, BULACAN, PROVINCE OF BULACAN | Region III | Region III | On-Going | ₱78M | 93% | Medium risk47 | —-0.055 |
| 394 | 22C00060ASSET PRESERVATION PROGRAM-REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE-SECONDARY ROADS, NUEVA ECIJA-AURORA ROAD, PROVINCE OF AURORA | Region III | Region III | Completed | ₱106.1M | 100% | Medium risk47 | —-0.085 |
| 395 | 23GA0006JAIME CARDINAL SIN AVENUE K0293+000 K0293+600 | Region VI | Aklan DEO | Completed | ₱29.8M | 100% | Medium risk47 | —-0.083 |
| 396 | 22DC0027ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM-PREVENTIVE MAINTENANCE-TERTIARY ROADS, LAKE-TAAL-TAGAYTAY RD | Region IV-A | Batangas 3rd DEO | Completed | ₱24.5M | 100% | Medium risk47 | —-0.105 |
| 397 | 18OI0184CONST. OF TWO (2) UNITS FOUR (4) STOREY, EIGHT (8) CLASSROOM S/B AT PUTATAN E/S, MUNTINLUPA CITY | National Capital Region | Las Piñas-Muntinlupa DEO | Completed | ₱36.4M | 100% | Medium risk47 | —-0.041 |
| 398 | 18FH0031CLUSTER 2-CONST/MAINT OF FLOOD MITIGATION STRUCTURES & DRAINAGE SYSTEM AT 2 VARIOUS SITES, SAN ANDRES, CATANDUANES:1) CONST. OF BISLIG FC AND DRAINAGE, BISLIG, SAN ANDRES;2)CONST. OF TIMBAAN FC & DRAINAGE, TIMBAAN, SAN ANDRES, CATANDUANES | Region V | Catanduanes DEO | Completed | ₱38.3M | 100% | Medium risk47 | —-0.086 |
| 399 | 18DF0043ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS; FLOOD MANAGEMENT PROGRAM: CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIESWITHIN MAJOR RIVER BASINS AND PRINCIPAL, CONSTRUCTION OF REVETMENT ALONG IMUS RIVER,BRGY. | Region IV-A | Cavite 1st DEO | Completed | ₱37.2M | 100% | Medium risk46 | —-0.087 |
| 400 | 18AI0073CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS TAYUG-NATIVIDAD RD | Region I | Pangasinan 3rd DEO | Completed | ₱27.8M | 100% | Medium risk46 | —-0.091 |