Contractor dossier
517 projects on file, including joint ventures this contractor is part of.
Total projects
517
Total budget
₱34.1B
Average progress
91.8%
Completion rate
82.4%
Average risk score
54.9
Medium risk on average, out of 100
Flagged as unusual
56
10.8% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region V | 127 | ₱7.7B | 58.0 | 7 | 97.4% |
| Region III | 112 | ₱6B | 50.1 | 13 | 89.3% |
| National Capital Region | 72 | ₱3.9B | 52.1 | 2 | 95.0% |
| Region IV-A | 50 | ₱3.8B | 59.2 | 10 | 77.4% |
| Region IV-B | 45 | ₱3.4B | 51.1 | 2 | 99.1% |
| Region I | 32 | ₱2.3B | 55.1 | 3 | 87.9% |
| Region II | 29 | ₱1.9B | 53.2 | 4 | 99.0% |
| Negros Island Region | 11 | ₱1.5B | 77.3 | 9 | 52.1% |
| Cordillera Administrative Region | 11 | ₱1.1B | 59.3 | 1 | 99.5% |
| Region VI | 7 | ₱399.9M | 57.2 | 2 | 76.3% |
| Region XI | 4 | ₱772.6M | 58.0 | 0 | 100.0% |
| Region X | 4 | ₱414.3M | 56.1 | 0 | 100.0% |
| Region VII | 4 | ₱311.8M | 55.1 | 0 | 100.0% |
| Region XII | 3 | ₱288.5M | 71.4 | 3 | 75.6% |
| Region VIII | 3 | ₱169.3M | 51.6 | 0 | 100.0% |
| Region XIII | 3 | ₱337M | 45.2 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Flood Control and Drainage | 164 | ₱10.5B | 55.3 | 22 | 90.4% |
| Roads | 155 | ₱12.8B | 55.5 | 4 | 91.8% |
| Buildings and Facilities | 95 | ₱3.9B | 47.4 | 12 | 93.9% |
| Bridges | 66 | ₱3.7B | 53.3 | 3 | 95.0% |
| OTHER | 19 | ₱1.6B | 73.7 | 9 | 95.3% |
| Water Provision and Storage | 8 | ₱344.3M | 62.2 | 2 | 83.5% |
| Bridges, Roads | 6 | ₱968.3M | 66.2 | 0 | 71.2% |
| GAA 2025 SSP | 3 | ₱228.7M | 95.0 | 3 | 85.2% |
| GAA 2025 OO-2 | 1 | ₱141.1M | 93.7 | 1 | 50.3% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25CL0061CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURE ALONG TAKAR RIVER PHASE 6, IBA, ZAMBALES | Region III | Zambales 1st DEO | On-Going | ₱97.5M | 82% | High risk95 | Flagged0.014 |
| 25CL0062CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURE ALONG TAKAR RIVER PHASE 7, IBA, ZAMBALES | Region III | Zambales 1st DEO | On-Going | ₱97.5M | 95% | High risk95 | Flagged0.011 |
| 25OA0016CONSTRUCTION OF R-10 PUMPING STATION, NAVOTAS CITY | National Capital Region | Malabon-Navotas DEO | On-Going | ₱33.6M | 78% | High risk94 | Flagged0.008 |
| 25HK0058ORGANIZATIONAL OUTCOME 2:PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-REHABILITATION OF FLOOD CONTROL STRUCTURE (RIGHT SIDE), BARANGAY CABANLUTAN,BA | Negros Island Region | Negros Oriental 2nd DEO | On-Going | ₱141.1M | 50% | High risk94 | Flagged0.005 |
| 24FL0113CONSTRUCTION OF REVETMENT AT SAN RAMON, DOWNSTREAM PHASE 4, BULAN, SORSOGON | Region V | Sorsogon 2nd DEO | On-Going | ₱141.4M | 99% | High risk92 | Flagged0.054 |
| 24DD0308CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING AT PINAGKAWITAN NATIONAL HIGH SCHOOL, BARANGAY PINAGKAWITAN, LIPA CITY, BAT | Region IV-A | Batangas 4th DEO | On-Going | ₱78.7M | 54% | High risk87 | Flagged0.055 |
| 17DD0194DRAINAGE IMPROVEMENT, ROSARIO-SAN JUAN ROAD (S01926LZ), K0126 + 774.00 - K0128 + 649.00; K0128 + 649.00 - K0130 + 638.00 | Region IV-A | Batangas 4th DEO | Completed | ₱98M | 100% | High risk83 | Flagged0.022 |
| 24GA0248CONSTRUCTION OF PUMPING STATION AT BRGY. POBLACION, KALIBO, AKLAN | Region VI | Aklan DEO | On-Going | ₱96.2M | 3% | High risk83 | Flagged0.070 |
| 24FE0022OO2: FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF DIKE ALONG BICOL RIVER BASIN, ISLA MATUNGAW, MILAOR, CAMARINES SUR | Region V | Camarines Sur 2nd DEO | On-Going | ₱125.4M | 99% | High risk82 | Flagged0.008 |
| 23BD0041BASIC INFRASTRUCTURE PROGRAM - MULTI- PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, TUGUEGARAO EAST CENTRAL SCHOOL, TUGUEGARAO CITY, CAGAYAN | Region II | Cagayan 3rd DEO | On-Going | ₱49.4M | 72% | High risk82 | Flagged0.025 |
| 24MC0028CONSTRUCTION OF REVETMENT ALONG MARBOL RIVER STA. 21 + 900 - STA. 22 + 700 R/S, BARANGAY NEW CEBU, PRES. ROXAS, COTABATO (REPUBLISHED) | Region XII | Cotabato 2nd DEO | On-Going | ₱96.5M | 94% | High risk81 | Flagged0.017 |
| 24MC0027CONSTRUCTION OF REVETMENT ALONG MARBOL RIVER STA. 21 + 400 - STA. 22 + 200 L/S, BARANGAY NEW CEBU, PRES. ROXAS, COTABATO (REPUBLISHED) | Region XII | Cotabato 2nd DEO | On-Going | ₱96.5M | 93% | High risk81 | Flagged0.017 |
| 25CL0079CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURE ALONG BAYTO RIVER, PHASE 3, SANTA CRUZ, ZAMBALES | Region III | Zambales 1st DEO | On-Going | ₱95.1M | 25% | High risk81 | Flagged0.005 |
| 25CL0080CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURE ALONG BAYTO RIVER, PHASE 4, SANTA CRUZ, ZAMBALES | Region III | Zambales 1st DEO | On-Going | ₱95.1M | 39% | High risk81 | Flagged0.000 |
| 24CL0078CONSTRUCTION OF MALOMA RIVER FLOOD CONTROL STRUCTURE, UPSTREAM, PACKAGE 3, SAGPAT SECTION, SAN FELIPE, ZAMBALES | Region III | Zambales 1st DEO | Completed | ₱95.2M | 100% | High risk81 | —-0.043 |
| 24CL0077CONSTRUCTION OF MALOMA RIVER FLOOD CONTROL STRUCTURE, UPSTREAM, PACKAGE 2, SAGPAT SECTION, SAN FELIPE, ZAMBALES | Region III | Zambales 1st DEO | Completed | ₱95.2M | 100% | High risk81 | —-0.043 |
| 24CL0079CONSTRUCTION OF MALOMA RIVER FLOOD CONTROL STRUCTURE, UPSTREAM, PACKAGE 4, SAGPAT SECTION, SAN FELIPE, ZAMBALES | Region III | Zambales 1st DEO | Completed | ₱95.3M | 100% | High risk81 | —-0.043 |
| 25CC0329CONSTRUCTION OF PUMPING STATION INCLUDING FLOOD GATE (PHASE II) AT BARANGAY ATLAG, MALOLOS CITY, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱92.7M | 34% | High risk81 | —-0.004 |
| 24CC0548CONSTRUCTION OF FLOOD CONTROL STRUCTURE INCLUDING PUMPING STATION AND FLOOD GATE AT BARANGAY SANTO ROSARIO, MALOLOS CITY, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱92.6M | 0% | High risk81 | Flagged0.008 |
| 24CC0547CONSTRUCTION OF FLOOD CONTROL STRUCTURE INCLUDING PUMPING STATION AND FLOOD GATE AT BARANGAY CALERO CREEK, MALOLOS CITY, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱92.6M | 51% | High risk81 | —-0.006 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24GA0248CONSTRUCTION OF PUMPING STATION AT BRGY. POBLACION, KALIBO, AKLAN | Region VI | Aklan DEO | On-Going | ₱96.2M | 3% | High risk83 | Flagged0.070 |
| 24DD0308CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING AT PINAGKAWITAN NATIONAL HIGH SCHOOL, BARANGAY PINAGKAWITAN, LIPA CITY, BAT | Region IV-A | Batangas 4th DEO | On-Going | ₱78.7M | 54% | High risk87 | Flagged0.055 |
| 24FL0113CONSTRUCTION OF REVETMENT AT SAN RAMON, DOWNSTREAM PHASE 4, BULAN, SORSOGON | Region V | Sorsogon 2nd DEO | On-Going | ₱141.4M | 99% | High risk92 | Flagged0.054 |
| 24DD0277ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM, CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, CONSTRUCTION OF LIPA CITY-MATAAS NA KAHOY DIVERSION RD. LEADING TO TAAL CIRCUMFERENTIAL ROAD PHASE 7, BATAN | Region IV-A | Batangas 4th DEO | On-Going | ₱187.4M | 0% | High risk69 | Flagged0.040 |
| 24DD0275ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM, CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, CONSTRUCTION OF LIPA CITY-MATAAS NA KAHOY DIVERSION RD. LEADING TO TAAL CIRCUMFERENTIAL ROAD PHASE 5, BATAN | Region IV-A | Batangas 4th DEO | On-Going | ₱187.4M | 0% | High risk69 | Flagged0.040 |
| 17DF0096CONSTRUCTION OF 4STY 12CL SCHOOL BUILDING AT HALAYHAY ES, TANZA, CAVITE | Region IV-A | Cavite 1st DEO | On-Going | ₱31.7M | 98% | Medium risk46 | Flagged0.039 |
| 17AA0616CONST. OF 1 UNIT 4 STOREY 20 CL, 2 UNITS 2 STOREY 8 CL, 2 UNITS 2 STOREY 4 CL SCHOOL BUILDING LAOAG | Region I | Ilocos Norte 1st DEO | Completed | ₱110.1M | 100% | Medium risk58 | Flagged0.032 |
| 24FL0117CONST. OF FLOOD MITIGATION STRUCTURE (REVETMENT) ALONG MARINAB RIVER AT BARANGAY MARINAB, BULAN, SOR | Region V | Sorsogon 2nd DEO | On-Going | ₱95.4M | 44% | High risk80 | Flagged0.028 |
| 25E00132CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF FLOOD CONTROL STRUCTURE, STO. NINO RIVER WATERWAYS ALONG ARAMAYWAN-BERONG-PTO. PRINCESA ROAD, PALAWAN | Region IV-B | Region IV-B | On-Going | ₱161.8M | 81% | High risk76 | Flagged0.027 |
| 23BD0041BASIC INFRASTRUCTURE PROGRAM - MULTI- PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, TUGUEGARAO EAST CENTRAL SCHOOL, TUGUEGARAO CITY, CAGAYAN | Region II | Cagayan 3rd DEO | On-Going | ₱49.4M | 72% | High risk82 | Flagged0.025 |
| 24FL0118CONST, OF FLOOD MITIGATION STRUCTURE (REVETMENT) ALOBNG QUEZON (CABARAWAN) RIVER AT BARANGAY QUEZON | Region V | Sorsogon 2nd DEO | On-Going | ₱95.5M | 66% | High risk80 | Flagged0.025 |
| 24DD0276ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM, CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, CONSTRUCTION OF LIPA CITY-MATAAS NA KAHOY DIVERSION RD. LEADING TO TAAL CIRCUMFERENTIAL ROAD PHASE 6, BATAN | Region IV-A | Batangas 4th DEO | On-Going | ₱187.4M | 61% | High risk69 | Flagged0.024 |
| 17DD0194DRAINAGE IMPROVEMENT, ROSARIO-SAN JUAN ROAD (S01926LZ), K0126 + 774.00 - K0128 + 649.00; K0128 + 649.00 - K0130 + 638.00 | Region IV-A | Batangas 4th DEO | Completed | ₱98M | 100% | High risk83 | Flagged0.022 |
| 23AH0162CLUSTER NO. I - CONVERGENCE AND SPECIAL SUPPORT PROGRAM- CONSTRUCTION/ REHABILITATION OF WATER SUPPLY/ SEPTAGE AND SEWERAGE/ RAIN WATER COLLECTORS WATER SUPPLY SYSTEM: 1. CONSTRUCTION OF SOLAR WATER SYSTEM IN THE MUNICIPALITY OF SAN FABIAN, PANGASINAN; 2. | Region I | Pangasinan 2nd DEO | On-Going | ₱39.2M | 17% | Medium risk47 | Flagged0.021 |
| 24CC0568CONSTRUCTION OF 4STY8CL, SAN ROQUE NATIONAL HS, PAOMBONG, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱40.3M | 58% | Medium risk54 | Flagged0.020 |
| 24CC0544CONSTRUCTION OF 4STY 8CL, MATIAS B. SALVADOR MEMORIAL ELEMENTARY SCHOOL, PANDI, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱41.3M | 66% | Medium risk48 | Flagged0.019 |
| 25G00078CONSTRUCTION OF RIVER CONTROL ALONG PANAY RIVER BASIN, BARANGAY BITOON ILAWOD TO BARANGAY POBLACION ILAYA, CUARTERO, CAPIZ | Region VI | Region VI | On-Going | ₱150.7M | 31% | High risk80 | Flagged0.019 |
| 23E00078SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONST. OF BULILUYAN SHORE PROTECTION AND CAUSEWAY DEVELOPMENT, BATARAZA, PALAWAN | Region IV-B | Region IV-B | On-Going | ₱120.6M | 77% | High risk62 | Flagged0.018 |
| 24MC0028CONSTRUCTION OF REVETMENT ALONG MARBOL RIVER STA. 21 + 900 - STA. 22 + 700 R/S, BARANGAY NEW CEBU, PRES. ROXAS, COTABATO (REPUBLISHED) | Region XII | Cotabato 2nd DEO | On-Going | ₱96.5M | 94% | High risk81 | Flagged0.017 |
| 24MC0027CONSTRUCTION OF REVETMENT ALONG MARBOL RIVER STA. 21 + 400 - STA. 22 + 200 L/S, BARANGAY NEW CEBU, PRES. ROXAS, COTABATO (REPUBLISHED) | Region XII | Cotabato 2nd DEO | On-Going | ₱96.5M | 93% | High risk81 | Flagged0.017 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 26 | 24CC0549CONSTRUCTION OF FLOOD CONTROL STRUCTURE WITH WATER PUMPING AT BARANGAY BAMBANG, BOCAUE, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱96.5M | 94% | High risk79 | —-0.022 |
| 27 | 25HK0051ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINTS MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-NET LENGHT CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS- CONSTRUCTION OF FLOOD CONTROL STRUCTURE, OKIOT SEAWALL, PHASE II, | Negros Island Region | Negros Oriental 2nd DEO | On-Going | ₱140.2M | 50% | High risk79 | Flagged0.012 |
| 28 | 25HK0072ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - REHABILITATION OF FLOOD CONTROL STRUCTURE, BARANGAY TAMOGONG, (BAIS BRI | Negros Island Region | Negros Oriental 2nd DEO | On-Going | ₱141.5M | 47% | High risk79 | Flagged0.012 |
| 29 | 25HK0069ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE, CANLUMBOG RIVER, BAIS CITY, NE | Negros Island Region | Negros Oriental 2nd DEO | On-Going | ₱141.2M | 55% | High risk79 | Flagged0.012 |
| 30 | 25HK0068ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE (DOWNSTREAM), BARANGAY LUYANG, | Negros Island Region | Negros Oriental 2nd DEO | On-Going | ₱141.1M | 47% | High risk79 | Flagged0.012 |
| 31 | 25HK0070ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BATANG RIVER, BARANGAY LUMBANG | Negros Island Region | Negros Oriental 2nd DEO | On-Going | ₱141.2M | 49% | High risk79 | Flagged0.012 |
| 32 | 25HK0071ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE, DI-AY RIVER, MABINAY, NEGROS O | Negros Island Region | Negros Oriental 2nd DEO | On-Going | ₱141M | 50% | High risk79 | Flagged0.011 |
| 33 | 25HK0049ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-NET LENGHT CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINGE SYSTEMS- CONSTRUCTION OF FLOOD CONTROL STRUCTURE, OKIOT SEAWALL, PHASE II, | Negros Island Region | Negros Oriental 2nd DEO | On-Going | ₱93.8M | 50% | High risk79 | Flagged0.004 |
| 34 | 25HK0047ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - REHABILITATION OF FLOOD CONTROL STRUCTURE, BARANGAY SAN JOSE, TANJAY CI | Negros Island Region | Negros Oriental 2nd DEO | On-Going | ₱140.7M | 67% | High risk78 | Flagged0.011 |
| 35 | 25CC0473CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY DUHAT, BOCAUE, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱57M | 10% | High risk77 | —-0.008 |
| 36 | 25CP0004ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - TERTIARY ROADS - SIBUL-BIAK-NA-BATO RD (SAN MIGUEL SECTION), SAN MIGUEL, BULACAN | Region III | Bulacan 3rd DEO | On-Going | ₱143.3M | 51% | High risk77 | —-0.011 |
| 37 | 17FE0009NETWORK DEVELOPMENT-IMPROVEMENT/WIDENING OF NATIONAL ROADS-TERTIARY ROADS, NAGA CITY BOUNDARY-CALABANGA-BALONGAY ROAD, K0443+686-K0444+880 | Region V | Camarines Sur 3rd DEO | Completed | ₱46.3M | 100% | High risk77 | —-0.030 |
| 38 | 17FK0036OFF-CARRIAGEWAY IMPV'T. INCLUDING DRAINAGE-SECONDARY ROADS-OFF CARRIEAGEWAY IMPVT'. SHOULDER PAVING/CONST. JCT. SORSOGON-BACON-MANITO ROAD, BACON DIST., SORSOGON CITY | Region V | Sorsogon DEO | Completed | ₱81.8M | 100% | High risk77 | —-0.028 |
| 39 | 24CC0492ROAD REHABILITATION OF OPLE ROAD LEADING TO BARASOAIN CHURCH, CITY OF MALOLOS AND PAOMBONG SECTION, CITY OF MALOLOS AND PAOMBONG, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱92.6M | 68% | High risk76 | —-0.021 |
| 40 | 25E00132CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF FLOOD CONTROL STRUCTURE, STO. NINO RIVER WATERWAYS ALONG ARAMAYWAN-BERONG-PTO. PRINCESA ROAD, PALAWAN | Region IV-B | Region IV-B | On-Going | ₱161.8M | 81% | High risk76 | Flagged0.027 |
| 41 | 18C00006NETWORK DEVELOPMENT PROGRAM-ROAD WIDENING-PRIMARY ROADS, DAANG MAHARLIKA (LZ), INCLUDING ROW, BULACAN 3RD LEGISLATIVE DISTRICT, PROVINCE OF BULACAN | Region III | Region III | Completed | ₱144.3M | 100% | High risk76 | Flagged0.007 |
| 42 | 24CC0088CONSTRUCTION OF REINFORCED CONCRETE SLOPE REVETMENT AT BARANGAY PIEL, BALIUAG, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱72.4M | 100% | High risk76 | —-0.061 |
| 43 | 24CC0093CONSTRUCTION OF REINFORCED CONCRETE SLOPE REVETMENT AT BARANGAY SAN ROQUE, BALIUAG, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱72.4M | 100% | High risk75 | —-0.061 |
| 44 | 24FB0229BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES -CONSTRUCTION OF MULTI-PURPOSE BLDG. (TRAINING AND INSTRUCTIONAL FACILITY/MEETINGS INCENTIVES CONFERENCES FOR EDUCATION, SPORTS BUILDING (MICES) AND PRIMARY | Region V | Albay 2nd DEO | On-Going | ₱169.8M | 0% | High risk74 | —-0.003 |
| 45 | 18C00059NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF BYPASS AND DIVERSION ROADS, BOCAUE-STA. MARIA BYPASS ROAD, BOCAUE AND STA. MARIA, BULACAN, BULACAN 4TH LEGISLATIVE DISTRICT, PROVINCE OF BULACAN | Region III | Region III | Completed | ₱158.5M | 100% | High risk74 | Flagged0.008 |
| 46 | 17FK0027CLUSTER I-CONSTRUCTION OF TWO STOREY (6) CLASSROOM SCHOOL BUILDING AND CONSTRUCTION OF CELEBRAL PALSY CLINIC BUILDING, SORSOGON CITY | Region V | Sorsogon DEO | Completed | ₱23.9M | 100% | High risk74 | —-0.034 |
| 47 | 23F00271OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF BY-PASS AND DIVERSION ROADS-NAGA-JCT. MAGARAO-CANAMAN-LIBMANAN JCT. PPH ROAD (SKYBRIDGE), PACKAGE 2, CAMARINES SUR, MAGARAO, CAMARINES SUR (3RD LEGISLATIVE DIST | Region V | Region V | On-Going | ₱141.1M | 92% | High risk73 | —-0.029 |
| 48 | 24CD0204CONSTRUCTION OF MULTI-PURPOSE BUILDING, MAHABANG PARANG ELEMENTARY SCHOOL, STA. MARIA, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱34.3M | 100% | High risk73 | —-0.070 |
| 49 | 24CC0094CONSTRUCTION OF REINFORCED CONCRETE SLOPE REVETMENT AT BARANGAY SULIVAN, BALIUAG, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱49M | 100% | High risk73 | —-0.064 |
| 50 | 18CD0185CONSTRUCTION OF BY-PASS/DIVERSION ROAD, CANDABA SAN MIGUEL BY-PASS ROAD, PACKAGE 1, INCL. ROW, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱140M | 100% | High risk73 | —-0.019 |