Contractor dossier
517 projects on file, including joint ventures this contractor is part of.
Total projects
517
Total budget
₱34.1B
Average progress
91.8%
Completion rate
82.4%
Average risk score
54.9
Medium risk on average, out of 100
Flagged as unusual
56
10.8% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region V | 127 | ₱7.7B | 58.0 | 7 | 97.4% |
| Region III | 112 | ₱6B | 50.1 | 13 | 89.3% |
| National Capital Region | 72 | ₱3.9B | 52.1 | 2 | 95.0% |
| Region IV-A | 50 | ₱3.8B | 59.2 | 10 | 77.4% |
| Region IV-B | 45 | ₱3.4B | 51.1 | 2 | 99.1% |
| Region I | 32 | ₱2.3B | 55.1 | 3 | 87.9% |
| Region II | 29 | ₱1.9B | 53.2 | 4 | 99.0% |
| Negros Island Region | 11 | ₱1.5B | 77.3 | 9 | 52.1% |
| Cordillera Administrative Region | 11 | ₱1.1B | 59.3 | 1 | 99.5% |
| Region VI | 7 | ₱399.9M | 57.2 | 2 | 76.3% |
| Region XI | 4 | ₱772.6M | 58.0 | 0 | 100.0% |
| Region X | 4 | ₱414.3M | 56.1 | 0 | 100.0% |
| Region VII | 4 | ₱311.8M | 55.1 | 0 | 100.0% |
| Region XII | 3 | ₱288.5M | 71.4 | 3 | 75.6% |
| Region VIII | 3 | ₱169.3M | 51.6 | 0 | 100.0% |
| Region XIII | 3 | ₱337M | 45.2 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Flood Control and Drainage | 164 | ₱10.5B | 55.3 | 22 | 90.4% |
| Roads | 155 | ₱12.8B | 55.5 | 4 | 91.8% |
| Buildings and Facilities | 95 | ₱3.9B | 47.4 | 12 | 93.9% |
| Bridges | 66 | ₱3.7B | 53.3 | 3 | 95.0% |
| OTHER | 19 | ₱1.6B | 73.7 | 9 | 95.3% |
| Water Provision and Storage | 8 | ₱344.3M | 62.2 | 2 | 83.5% |
| Bridges, Roads | 6 | ₱968.3M | 66.2 | 0 | 71.2% |
| GAA 2025 SSP | 3 | ₱228.7M | 95.0 | 3 | 85.2% |
| GAA 2025 OO-2 | 1 | ₱141.1M | 93.7 | 1 | 50.3% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25CL0061CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURE ALONG TAKAR RIVER PHASE 6, IBA, ZAMBALES | Region III | Zambales 1st DEO | On-Going | ₱97.5M | 82% | High risk95 | Flagged0.014 |
| 25CL0062CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURE ALONG TAKAR RIVER PHASE 7, IBA, ZAMBALES | Region III | Zambales 1st DEO | On-Going | ₱97.5M | 95% | High risk95 | Flagged0.011 |
| 25OA0016CONSTRUCTION OF R-10 PUMPING STATION, NAVOTAS CITY | National Capital Region | Malabon-Navotas DEO | On-Going | ₱33.6M | 78% | High risk94 | Flagged0.008 |
| 25HK0058ORGANIZATIONAL OUTCOME 2:PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-REHABILITATION OF FLOOD CONTROL STRUCTURE (RIGHT SIDE), BARANGAY CABANLUTAN,BA | Negros Island Region | Negros Oriental 2nd DEO | On-Going | ₱141.1M | 50% | High risk94 | Flagged0.005 |
| 24FL0113CONSTRUCTION OF REVETMENT AT SAN RAMON, DOWNSTREAM PHASE 4, BULAN, SORSOGON | Region V | Sorsogon 2nd DEO | On-Going | ₱141.4M | 99% | High risk92 | Flagged0.054 |
| 24DD0308CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING AT PINAGKAWITAN NATIONAL HIGH SCHOOL, BARANGAY PINAGKAWITAN, LIPA CITY, BAT | Region IV-A | Batangas 4th DEO | On-Going | ₱78.7M | 54% | High risk87 | Flagged0.055 |
| 17DD0194DRAINAGE IMPROVEMENT, ROSARIO-SAN JUAN ROAD (S01926LZ), K0126 + 774.00 - K0128 + 649.00; K0128 + 649.00 - K0130 + 638.00 | Region IV-A | Batangas 4th DEO | Completed | ₱98M | 100% | High risk83 | Flagged0.022 |
| 24GA0248CONSTRUCTION OF PUMPING STATION AT BRGY. POBLACION, KALIBO, AKLAN | Region VI | Aklan DEO | On-Going | ₱96.2M | 3% | High risk83 | Flagged0.070 |
| 24FE0022OO2: FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF DIKE ALONG BICOL RIVER BASIN, ISLA MATUNGAW, MILAOR, CAMARINES SUR | Region V | Camarines Sur 2nd DEO | On-Going | ₱125.4M | 99% | High risk82 | Flagged0.008 |
| 23BD0041BASIC INFRASTRUCTURE PROGRAM - MULTI- PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, TUGUEGARAO EAST CENTRAL SCHOOL, TUGUEGARAO CITY, CAGAYAN | Region II | Cagayan 3rd DEO | On-Going | ₱49.4M | 72% | High risk82 | Flagged0.025 |
| 24MC0028CONSTRUCTION OF REVETMENT ALONG MARBOL RIVER STA. 21 + 900 - STA. 22 + 700 R/S, BARANGAY NEW CEBU, PRES. ROXAS, COTABATO (REPUBLISHED) | Region XII | Cotabato 2nd DEO | On-Going | ₱96.5M | 94% | High risk81 | Flagged0.017 |
| 24MC0027CONSTRUCTION OF REVETMENT ALONG MARBOL RIVER STA. 21 + 400 - STA. 22 + 200 L/S, BARANGAY NEW CEBU, PRES. ROXAS, COTABATO (REPUBLISHED) | Region XII | Cotabato 2nd DEO | On-Going | ₱96.5M | 93% | High risk81 | Flagged0.017 |
| 25CL0079CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURE ALONG BAYTO RIVER, PHASE 3, SANTA CRUZ, ZAMBALES | Region III | Zambales 1st DEO | On-Going | ₱95.1M | 25% | High risk81 | Flagged0.005 |
| 25CL0080CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURE ALONG BAYTO RIVER, PHASE 4, SANTA CRUZ, ZAMBALES | Region III | Zambales 1st DEO | On-Going | ₱95.1M | 39% | High risk81 | Flagged0.000 |
| 24CL0078CONSTRUCTION OF MALOMA RIVER FLOOD CONTROL STRUCTURE, UPSTREAM, PACKAGE 3, SAGPAT SECTION, SAN FELIPE, ZAMBALES | Region III | Zambales 1st DEO | Completed | ₱95.2M | 100% | High risk81 | —-0.043 |
| 24CL0077CONSTRUCTION OF MALOMA RIVER FLOOD CONTROL STRUCTURE, UPSTREAM, PACKAGE 2, SAGPAT SECTION, SAN FELIPE, ZAMBALES | Region III | Zambales 1st DEO | Completed | ₱95.2M | 100% | High risk81 | —-0.043 |
| 24CL0079CONSTRUCTION OF MALOMA RIVER FLOOD CONTROL STRUCTURE, UPSTREAM, PACKAGE 4, SAGPAT SECTION, SAN FELIPE, ZAMBALES | Region III | Zambales 1st DEO | Completed | ₱95.3M | 100% | High risk81 | —-0.043 |
| 25CC0329CONSTRUCTION OF PUMPING STATION INCLUDING FLOOD GATE (PHASE II) AT BARANGAY ATLAG, MALOLOS CITY, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱92.7M | 34% | High risk81 | —-0.004 |
| 24CC0548CONSTRUCTION OF FLOOD CONTROL STRUCTURE INCLUDING PUMPING STATION AND FLOOD GATE AT BARANGAY SANTO ROSARIO, MALOLOS CITY, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱92.6M | 0% | High risk81 | Flagged0.008 |
| 24CC0547CONSTRUCTION OF FLOOD CONTROL STRUCTURE INCLUDING PUMPING STATION AND FLOOD GATE AT BARANGAY CALERO CREEK, MALOLOS CITY, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱92.6M | 51% | High risk81 | —-0.006 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24GA0248CONSTRUCTION OF PUMPING STATION AT BRGY. POBLACION, KALIBO, AKLAN | Region VI | Aklan DEO | On-Going | ₱96.2M | 3% | High risk83 | Flagged0.070 |
| 24DD0308CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING AT PINAGKAWITAN NATIONAL HIGH SCHOOL, BARANGAY PINAGKAWITAN, LIPA CITY, BAT | Region IV-A | Batangas 4th DEO | On-Going | ₱78.7M | 54% | High risk87 | Flagged0.055 |
| 24FL0113CONSTRUCTION OF REVETMENT AT SAN RAMON, DOWNSTREAM PHASE 4, BULAN, SORSOGON | Region V | Sorsogon 2nd DEO | On-Going | ₱141.4M | 99% | High risk92 | Flagged0.054 |
| 24DD0277ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM, CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, CONSTRUCTION OF LIPA CITY-MATAAS NA KAHOY DIVERSION RD. LEADING TO TAAL CIRCUMFERENTIAL ROAD PHASE 7, BATAN | Region IV-A | Batangas 4th DEO | On-Going | ₱187.4M | 0% | High risk69 | Flagged0.040 |
| 24DD0275ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM, CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, CONSTRUCTION OF LIPA CITY-MATAAS NA KAHOY DIVERSION RD. LEADING TO TAAL CIRCUMFERENTIAL ROAD PHASE 5, BATAN | Region IV-A | Batangas 4th DEO | On-Going | ₱187.4M | 0% | High risk69 | Flagged0.040 |
| 17DF0096CONSTRUCTION OF 4STY 12CL SCHOOL BUILDING AT HALAYHAY ES, TANZA, CAVITE | Region IV-A | Cavite 1st DEO | On-Going | ₱31.7M | 98% | Medium risk46 | Flagged0.039 |
| 17AA0616CONST. OF 1 UNIT 4 STOREY 20 CL, 2 UNITS 2 STOREY 8 CL, 2 UNITS 2 STOREY 4 CL SCHOOL BUILDING LAOAG | Region I | Ilocos Norte 1st DEO | Completed | ₱110.1M | 100% | Medium risk58 | Flagged0.032 |
| 24FL0117CONST. OF FLOOD MITIGATION STRUCTURE (REVETMENT) ALONG MARINAB RIVER AT BARANGAY MARINAB, BULAN, SOR | Region V | Sorsogon 2nd DEO | On-Going | ₱95.4M | 44% | High risk80 | Flagged0.028 |
| 25E00132CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF FLOOD CONTROL STRUCTURE, STO. NINO RIVER WATERWAYS ALONG ARAMAYWAN-BERONG-PTO. PRINCESA ROAD, PALAWAN | Region IV-B | Region IV-B | On-Going | ₱161.8M | 81% | High risk76 | Flagged0.027 |
| 23BD0041BASIC INFRASTRUCTURE PROGRAM - MULTI- PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, TUGUEGARAO EAST CENTRAL SCHOOL, TUGUEGARAO CITY, CAGAYAN | Region II | Cagayan 3rd DEO | On-Going | ₱49.4M | 72% | High risk82 | Flagged0.025 |
| 24FL0118CONST, OF FLOOD MITIGATION STRUCTURE (REVETMENT) ALOBNG QUEZON (CABARAWAN) RIVER AT BARANGAY QUEZON | Region V | Sorsogon 2nd DEO | On-Going | ₱95.5M | 66% | High risk80 | Flagged0.025 |
| 24DD0276ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM, CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, CONSTRUCTION OF LIPA CITY-MATAAS NA KAHOY DIVERSION RD. LEADING TO TAAL CIRCUMFERENTIAL ROAD PHASE 6, BATAN | Region IV-A | Batangas 4th DEO | On-Going | ₱187.4M | 61% | High risk69 | Flagged0.024 |
| 17DD0194DRAINAGE IMPROVEMENT, ROSARIO-SAN JUAN ROAD (S01926LZ), K0126 + 774.00 - K0128 + 649.00; K0128 + 649.00 - K0130 + 638.00 | Region IV-A | Batangas 4th DEO | Completed | ₱98M | 100% | High risk83 | Flagged0.022 |
| 23AH0162CLUSTER NO. I - CONVERGENCE AND SPECIAL SUPPORT PROGRAM- CONSTRUCTION/ REHABILITATION OF WATER SUPPLY/ SEPTAGE AND SEWERAGE/ RAIN WATER COLLECTORS WATER SUPPLY SYSTEM: 1. CONSTRUCTION OF SOLAR WATER SYSTEM IN THE MUNICIPALITY OF SAN FABIAN, PANGASINAN; 2. | Region I | Pangasinan 2nd DEO | On-Going | ₱39.2M | 17% | Medium risk47 | Flagged0.021 |
| 24CC0568CONSTRUCTION OF 4STY8CL, SAN ROQUE NATIONAL HS, PAOMBONG, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱40.3M | 58% | Medium risk54 | Flagged0.020 |
| 24CC0544CONSTRUCTION OF 4STY 8CL, MATIAS B. SALVADOR MEMORIAL ELEMENTARY SCHOOL, PANDI, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱41.3M | 66% | Medium risk48 | Flagged0.019 |
| 25G00078CONSTRUCTION OF RIVER CONTROL ALONG PANAY RIVER BASIN, BARANGAY BITOON ILAWOD TO BARANGAY POBLACION ILAYA, CUARTERO, CAPIZ | Region VI | Region VI | On-Going | ₱150.7M | 31% | High risk80 | Flagged0.019 |
| 23E00078SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONST. OF BULILUYAN SHORE PROTECTION AND CAUSEWAY DEVELOPMENT, BATARAZA, PALAWAN | Region IV-B | Region IV-B | On-Going | ₱120.6M | 77% | High risk62 | Flagged0.018 |
| 24MC0028CONSTRUCTION OF REVETMENT ALONG MARBOL RIVER STA. 21 + 900 - STA. 22 + 700 R/S, BARANGAY NEW CEBU, PRES. ROXAS, COTABATO (REPUBLISHED) | Region XII | Cotabato 2nd DEO | On-Going | ₱96.5M | 94% | High risk81 | Flagged0.017 |
| 24MC0027CONSTRUCTION OF REVETMENT ALONG MARBOL RIVER STA. 21 + 400 - STA. 22 + 200 L/S, BARANGAY NEW CEBU, PRES. ROXAS, COTABATO (REPUBLISHED) | Region XII | Cotabato 2nd DEO | On-Going | ₱96.5M | 93% | High risk81 | Flagged0.017 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 76 | 18FK0014OFF-CARRIAGEWAY IMPROVEMENT-SECONDARY ROADS-JUNCTION SORSOGON-BACON-MANITO ROAD, BACON DISTRICT, SORSOGON CITY, KO584+000-KO584+563;KO591+400-KO592+710, KO592+729-KO593+064, KO593+086-KO593+435, 593+461-KO594+807-KO594+833.60-KO594+941, BACON DIST., SOR. | Region V | Sorsogon DEO | Completed | ₱90.3M | 100% | High risk67 | —-0.089 |
| 77 | 17DL0113CONSTRUCTION OF VARIOUS WATER SUPPLY PROJECTS IN LOPEZ, QUEZON | Region IV-A | Quezon 4th DEO | Completed | ₱39.1M | 100% | High risk67 | —-0.043 |
| 78 | 17DL01081. LOCALLY-FUNDED PROJECTS B. CONSTRUCTION/ REPAIR/ REHABILITATION/ IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS 2. WATER MANAGEMENT A. WATER SUPPLY CONSTRUCTION OF WATER SUPPLY PROJECT, GUINAYANGAN, QUEZON | Region IV-A | Quezon 4th DEO | Completed | ₱43.2M | 100% | High risk67 | —-0.042 |
| 79 | 24DC0096CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) - BASIC INFRASTRUCTURE PROGRAM (BIP), BIP - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF BRIDGE ALONG LIPA CITY - MATAAS NA KAHO | Region IV-A | Batangas 3rd DEO | On-Going | ₱144.8M | 33% | High risk67 | Flagged0.004 |
| 80 | 24DC0095CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) - BASIC INFRASTRUCTURE PROGRAM (BIP), BIP - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF BRIDGE ALONG LIPA - CITY MATAAS NA KAHO | Region IV-A | Batangas 3rd DEO | On-Going | ₱148.5M | 42% | High risk67 | —-0.000 |
| 81 | 24DC0094CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) - BASIC INFRASTRUCTURE PROGRAM (BIP), BIP - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF BRIDGE ALONG LIPA CITY - MATAAS NA KAHO | Region IV-A | Batangas 3rd DEO | On-Going | ₱148.5M | 75% | High risk67 | —-0.008 |
| 82 | 19L00104CONST. OF ASPHALT ROAD-DAVAO CITY COASTAL BYPASS RD, (BAGO APLAYA-TIMES BEACH SECT.),PACKAGE 12,DAVA | Region XI | Region XI | Completed | ₱313.5M | 100% | High risk66 | —-0.015 |
| 83 | 17DL0114CONSTRUCTION OF VARIOUS WATER SUPPLY PROJECTS IN TAGKAWAYAN, QUEZON | Region IV-A | Quezon 4th DEO | Completed | ₱14.3M | 100% | High risk66 | —-0.046 |
| 84 | 17DO0016MFO1-NATIONAL ROAD NETWORK SERVICES-NETWORK DEVELOPMENT-OF-CARRIAGEWAY IMPROVMENT INCLUDING DRAINAGE-TERTIARY ROADS-TANAY-SAMPALOC RD (SO1584LZ) K0068+316-K0069+085, TANAY RIZAL | Region IV-A | Rizal 2nd DEO | Completed | ₱27.5M | 100% | High risk66 | —-0.072 |
| 85 | 18D00045ENSURE SAFE & RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM, CONSTRUCTION OF BY-PASS & DIVERSION ROADS, BATANGAS CITY-SAN PASCUAL-BAUAN ROAD (SECTION 1), PACKAGE B, INCL. ROW & BRIDGE, BATANGAS | Region IV-A | Region IV-A | Completed | ₱121.7M | 100% | High risk66 | —-0.071 |
| 86 | 22FL0007CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT GUBAT, SORSOGON (CLUSTER III), BRGY, ARIMAN GUBAT, SORSOGON AND BRGY. NAAGTAN, GUBAT, SORSOGON | Region V | Sorsogon 2nd DEO | Completed | ₱96.2M | 100% | High risk66 | —-0.075 |
| 87 | 22FK0012NETWORK DEVELOPMENT-CONSTRUCTION OF BY-PASS AND DIVERSION ROADS-SORSOGON CITY COASTAL BYPASS ROAD, PACKAGE 10, SORSOGON CITY | Region V | Sorsogon DEO | Completed | ₱93.4M | 100% | High risk66 | —-0.088 |
| 88 | 22FK0013NETWORK DEVELOPMENT-CONSTRUCTION OF BY-PASS AND DIVERSION ROADS-SORSOGON CITY COASTAL BYPASS ROAD, PACKAGE 11, SORSOGON CITY | Region V | Sorsogon DEO | Completed | ₱93.4M | 100% | High risk66 | —-0.088 |
| 89 | 22FK0060CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP)-CONSTRUCTION_IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM-TRIP) DONSOL-PILAR-CASTILLA-SORSOGON CITY (DONPICASO) TOURISM HIGHWAY, SORSOGON, PACKAGE | Region V | Sorsogon DEO | On-Going | ₱94.1M | 100% | High risk66 | —-0.041 |
| 90 | 20O00003WIDENING OF PERMANENT BRIDGE, R-10 BRIDGE 2 (B01745LZ)ALONG R-10, MANILA CITY | National Capital Region | National Capital Region | Completed | ₱144.7M | 100% | High risk66 | —-0.032 |
| 91 | 23A00267CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF SABO DAM ALONG SOLSONA RIVER, SOLSONA, ILOCOS NORTE | Region I | Region I | On-Going | ₱112.3M | 49% | High risk66 | Flagged0.008 |
| 92 | 17P00053CONSTRUCTION AND MAINTENANCE OF BRIDGE ALONG NATIONAL ROADS - REPLACEMENT OF PERMANENT WEAK BRIDGES, IBULAO BRIDGE (BO2203LZ) ALONG NUEVA VIZCAYA-IFUGAO-MT. PROVINCE ROAD | Cordillera Administrative Region | Cordillera Administrative Region | Completed | ₱96.5M | 100% | High risk66 | Flagged0.000 |
| 93 | 18FK0006CONSTRUCTION/IMPV'T. OF ACCESS ROAD LEADING TO DECLARED TOURISM DESTINATIONS MATNOG-BULAN, MAGALLANES TOURISM WEST COAST HIGHWAY, MAGALLANES, SORSOGON | Region V | Sorsogon DEO | Completed | ₱93M | 100% | High risk66 | —-0.088 |
| 94 | 25HK0067ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - REHABILITATION OF FLOOD CONTROL STRUCTURE, BARANGAY SAN ISIDRO, TANJAY | Negros Island Region | Negros Oriental 2nd DEO | On-Going | ₱141.1M | 52% | High risk66 | —-0.011 |
| 95 | 18FK0018NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, BARCELONA-CASIGURAN DIVERSION ROAD (CASIGURAN SECTION), CASIGURAN, SORSOGON | Region V | Sorsogon DEO | Completed | ₱93M | 100% | High risk65 | —-0.087 |
| 96 | 25DD0022CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDING/FACILITIES, CONSTRUCTION OF LIPA CITY-MATAASNAKAHOY DIVE | Region IV-A | Batangas 4th DEO | On-Going | ₱140.6M | 15% | High risk65 | —-0.026 |
| 97 | 25DD0008CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDING/FACILITIES, CONSTRUCTION OF LIPA CITY-MATAASNAKAHOY DIVE | Region IV-A | Batangas 4th DEO | On-Going | ₱140.5M | 22% | High risk65 | —-0.032 |
| 98 | 24D00209CONSTRUCTION OF BALETE - SAN JOSE DIVERSION ROAD, MATAAS NA KAHOY SECTION (PHASE I), BATANGAS | Region IV-A | Region IV-A | On-Going | ₱188.2M | 0% | High risk65 | —-0.015 |
| 99 | 25OD0127IMPROVEMENT OF FLOOD CONTROL RIVER WALL ALONG TULLAHAN RIVER, STA. 02+350 TO STA. 02+700, VALENZUELA CITY | National Capital Region | Metro Manila 3rd DEO | On-Going | ₱94.8M | 61% | High risk65 | —-0.037 |
| 100 | 25OE0179CONSTRUCTION OF RETARDING BASIN AT ESTERO DE QUIAPO (PHASE IV), MANILA CITY | National Capital Region | North Manila DEO | On-Going | ₱94.1M | 34% | High risk65 | —-0.032 |