Contractor dossier
131 projects on file, including joint ventures this contractor is part of.
Total projects
131
Total budget
₱2.4B
Average progress
95.1%
Completion rate
83.2%
Average risk score
38.0
Medium risk on average, out of 100
Flagged as unusual
12
9.2% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region XIII | 130 | ₱2.4B | 38.0 | 12 | 95.1% |
| Region VIII | 1 | ₱39.2M | 45.9 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 48 | ₱286.8M | 21.6 | 0 | 99.8% |
| Roads | 32 | ₱502.3M | 38.6 | 0 | 99.7% |
| Flood Control and Drainage | 26 | ₱1.2B | 41.0 | 1 | 94.9% |
| GAA 2025 SSP | 8 | ₱39.2M | 94.7 | 7 | 54.4% |
| OTHER | 7 | ₱235.9M | 75.1 | 4 | 85.1% |
| Bridges | 6 | ₱110.9M | 41.2 | 0 | 97.3% |
| Water Provision and Storage | 3 | ₱12.1M | 25.4 | 0 | 100.0% |
| Bridges, Roads | 1 | ₱22.5M | 39.4 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25NG0093CONSTRUCTION OF MULTI PURPOSE BUILDING, BRGY. TAGANITO, CLAVER, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 2nd DEO | On-Going | ₱4.9M | 44% | High risk95 | Flagged0.022 |
| 25NG0087CONSTRUCTION OF EVACUATION CENTER, BRGY. SAPA, CLAVER, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 2nd DEO | On-Going | ₱4.9M | 61% | High risk95 | Flagged0.019 |
| 25NG0062CONSTRUCTION OF ROAD AT SITIO SABANG, BRGY. TAYAGA, CLAVER, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 2nd DEO | On-Going | ₱4.9M | 3% | High risk95 | Flagged0.034 |
| 25NG0105CONSTRUCTION OF EVACUATION CENTER, BRGY. MAGALLANES, CLAVER, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 2nd DEO | On-Going | ₱4.9M | 82% | High risk95 | Flagged0.013 |
| 25NG0101CONSTRUCTION OF SAN PEDRO - SAN ISIDRO - MAYAG ROAD, SISON, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 2nd DEO | On-Going | ₱4.9M | 7% | High risk95 | Flagged0.031 |
| 25NG0027CONSTRUCTION OF MULTI PURPOSE BUILDING, BRGY. SAN PABLO, SISON, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 2nd DEO | On-Going | ₱4.9M | 66% | High risk95 | Flagged0.014 |
| 25NG0099CONSTRUCTION OF CAPAYAHAN-MARGA- SAN PABLO ROAD LEADING TO TOURISM AREA, TUBOD, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 2nd DEO | On-Going | ₱4.9M | 73% | High risk95 | Flagged0.013 |
| 25NG0064CONSTRUCTION OF ROAD, BRGY. SABANG, SURIGAO CITY, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 2nd DEO | Completed | ₱4.9M | 100% | High risk95 | —-0.022 |
| 24NG0092CONSTRUCTION OF ANOMAR FLOOD MITIGATING STRUCTURE/ BARANGAY ANOMAR, SURIGAO CITY, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 2nd DEO | On-Going | ₱86.8M | 84% | High risk89 | Flagged0.050 |
| 24NG0045CONSTRUCTION OF BINOCARAN - MALIMONO FLOOD MITIGATION STRUCTURE AT BARANGAY BINOCARAN, MALIMONO, SURIGAO DEL NORTE / BRGY. BINOCARAN, MALIMONO, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 2nd DEO | On-Going | ₱86M | 97% | High risk77 | Flagged0.006 |
| 16NF0149CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG SURIGAO-SAN JUAN COASTAL ROAD/SURIGAO CITY, K1119+485 - K1119+625.03, L/S K1119+633.09 - K1119+730.90, L/S, K1119+740 - K1119+813.25, L/S, K1119+823.45 - K1119+951, L/S | Region XIII | Surigao del Norte 2nd DEO | Completed | ₱9.7M | 100% | High risk74 | —-0.023 |
| 25NG0024NRJ BRGY. CAMPO-BRGY. PAYAPAG ROAD LEADING TO SITIO LITTLE BAGUIO FALLS AND FARM, BACUAG, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 2nd DEO | On-Going | ₱4.9M | 19% | High risk74 | Flagged0.018 |
| 24NG0007CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES INDUSTRIES AND ECONOMIC ZONES, CAMPO-CABUGAO ROAD IN SUPPORT TO AGRIBUSINESS INDUSTRY, BACUAG, SURIGAO DEL NORTE / BACUAG, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 2nd DEO | Completed | ₱32.6M | 100% | High risk74 | —-0.019 |
| 16NF0141WIDENING OF PERMANENT BRIDGES TO MORE THAN TWO (2) LANES/SIANA BRIDGE (B00859MN) ALONG DAANG MAHARLIKA (SURIGAO-AGUSAN SECTION) K1157+163.00 - K1157+179.00 | Region XIII | Surigao del Norte 2nd DEO | Completed | ₱15M | 100% | High risk74 | —-0.023 |
| 24NG0106CONSTRUCTION OF DRRM BUILDING, MAINIT, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 2nd DEO | On-Going | ₱979.3K | 96% | High risk64 | Flagged0.037 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24NG0092CONSTRUCTION OF ANOMAR FLOOD MITIGATING STRUCTURE/ BARANGAY ANOMAR, SURIGAO CITY, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 2nd DEO | On-Going | ₱86.8M | 84% | High risk89 | Flagged0.050 |
| 24NG0106CONSTRUCTION OF DRRM BUILDING, MAINIT, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 2nd DEO | On-Going | ₱979.3K | 96% | High risk64 | Flagged0.037 |
| 25NG0062CONSTRUCTION OF ROAD AT SITIO SABANG, BRGY. TAYAGA, CLAVER, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 2nd DEO | On-Going | ₱4.9M | 3% | High risk95 | Flagged0.034 |
| 25NG0101CONSTRUCTION OF SAN PEDRO - SAN ISIDRO - MAYAG ROAD, SISON, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 2nd DEO | On-Going | ₱4.9M | 7% | High risk95 | Flagged0.031 |
| 25NG0093CONSTRUCTION OF MULTI PURPOSE BUILDING, BRGY. TAGANITO, CLAVER, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 2nd DEO | On-Going | ₱4.9M | 44% | High risk95 | Flagged0.022 |
| 25NG0087CONSTRUCTION OF EVACUATION CENTER, BRGY. SAPA, CLAVER, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 2nd DEO | On-Going | ₱4.9M | 61% | High risk95 | Flagged0.019 |
| 25NG0024NRJ BRGY. CAMPO-BRGY. PAYAPAG ROAD LEADING TO SITIO LITTLE BAGUIO FALLS AND FARM, BACUAG, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 2nd DEO | On-Going | ₱4.9M | 19% | High risk74 | Flagged0.018 |
| 23NG0155REPAIR OF CABUGAO FLOOD CONTROL / BRGY. CABUGAO, BACUAG, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 2nd DEO | On-Going | ₱30M | 0% | Medium risk59 | Flagged0.016 |
| 25NG0027CONSTRUCTION OF MULTI PURPOSE BUILDING, BRGY. SAN PABLO, SISON, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 2nd DEO | On-Going | ₱4.9M | 66% | High risk95 | Flagged0.014 |
| 25NG0099CONSTRUCTION OF CAPAYAHAN-MARGA- SAN PABLO ROAD LEADING TO TOURISM AREA, TUBOD, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 2nd DEO | On-Going | ₱4.9M | 73% | High risk95 | Flagged0.013 |
| 25NG0105CONSTRUCTION OF EVACUATION CENTER, BRGY. MAGALLANES, CLAVER, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 2nd DEO | On-Going | ₱4.9M | 82% | High risk95 | Flagged0.013 |
| 24NG0045CONSTRUCTION OF BINOCARAN - MALIMONO FLOOD MITIGATION STRUCTURE AT BARANGAY BINOCARAN, MALIMONO, SURIGAO DEL NORTE / BRGY. BINOCARAN, MALIMONO, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 2nd DEO | On-Going | ₱86M | 97% | High risk77 | Flagged0.006 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25NG0093CONSTRUCTION OF MULTI PURPOSE BUILDING, BRGY. TAGANITO, CLAVER, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 2nd DEO | On-Going | ₱4.9M | 44% | High risk95 | Flagged0.022 |
| 2 | 25NG0087CONSTRUCTION OF EVACUATION CENTER, BRGY. SAPA, CLAVER, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 2nd DEO | On-Going | ₱4.9M | 61% | High risk95 | Flagged0.019 |
| 3 | 25NG0062CONSTRUCTION OF ROAD AT SITIO SABANG, BRGY. TAYAGA, CLAVER, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 2nd DEO | On-Going | ₱4.9M | 3% | High risk95 | Flagged0.034 |
| 4 | 25NG0105CONSTRUCTION OF EVACUATION CENTER, BRGY. MAGALLANES, CLAVER, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 2nd DEO | On-Going | ₱4.9M | 82% | High risk95 | Flagged0.013 |
| 5 | 25NG0101CONSTRUCTION OF SAN PEDRO - SAN ISIDRO - MAYAG ROAD, SISON, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 2nd DEO | On-Going | ₱4.9M | 7% | High risk95 | Flagged0.031 |
| 6 | 25NG0027CONSTRUCTION OF MULTI PURPOSE BUILDING, BRGY. SAN PABLO, SISON, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 2nd DEO | On-Going | ₱4.9M | 66% | High risk95 | Flagged0.014 |
| 7 | 25NG0099CONSTRUCTION OF CAPAYAHAN-MARGA- SAN PABLO ROAD LEADING TO TOURISM AREA, TUBOD, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 2nd DEO | On-Going | ₱4.9M | 73% | High risk95 | Flagged0.013 |
| 8 | 25NG0064CONSTRUCTION OF ROAD, BRGY. SABANG, SURIGAO CITY, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 2nd DEO | Completed | ₱4.9M | 100% | High risk95 | —-0.022 |
| 9 | 24NG0092CONSTRUCTION OF ANOMAR FLOOD MITIGATING STRUCTURE/ BARANGAY ANOMAR, SURIGAO CITY, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 2nd DEO | On-Going | ₱86.8M | 84% | High risk89 | Flagged0.050 |
| 10 | 24NG0045CONSTRUCTION OF BINOCARAN - MALIMONO FLOOD MITIGATION STRUCTURE AT BARANGAY BINOCARAN, MALIMONO, SURIGAO DEL NORTE / BRGY. BINOCARAN, MALIMONO, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 2nd DEO | On-Going | ₱86M | 97% | High risk77 | Flagged0.006 |
| 11 | 16NF0149CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG SURIGAO-SAN JUAN COASTAL ROAD/SURIGAO CITY, K1119+485 - K1119+625.03, L/S K1119+633.09 - K1119+730.90, L/S, K1119+740 - K1119+813.25, L/S, K1119+823.45 - K1119+951, L/S | Region XIII | Surigao del Norte 2nd DEO | Completed | ₱9.7M | 100% | High risk74 | —-0.023 |
| 12 | 25NG0024NRJ BRGY. CAMPO-BRGY. PAYAPAG ROAD LEADING TO SITIO LITTLE BAGUIO FALLS AND FARM, BACUAG, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 2nd DEO | On-Going | ₱4.9M | 19% | High risk74 | Flagged0.018 |
| 13 | 24NG0007CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES INDUSTRIES AND ECONOMIC ZONES, CAMPO-CABUGAO ROAD IN SUPPORT TO AGRIBUSINESS INDUSTRY, BACUAG, SURIGAO DEL NORTE / BACUAG, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 2nd DEO | Completed | ₱32.6M | 100% | High risk74 | —-0.019 |
| 14 | 16NF0141WIDENING OF PERMANENT BRIDGES TO MORE THAN TWO (2) LANES/SIANA BRIDGE (B00859MN) ALONG DAANG MAHARLIKA (SURIGAO-AGUSAN SECTION) K1157+163.00 - K1157+179.00 | Region XIII | Surigao del Norte 2nd DEO | Completed | ₱15M | 100% | High risk74 | —-0.023 |
| 15 | 24NG0106CONSTRUCTION OF DRRM BUILDING, MAINIT, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 2nd DEO | On-Going | ₱979.3K | 96% | High risk64 | Flagged0.037 |
| 16 | 23NG0155REPAIR OF CABUGAO FLOOD CONTROL / BRGY. CABUGAO, BACUAG, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 2nd DEO | On-Going | ₱30M | 0% | Medium risk59 | Flagged0.016 |
| 17 | 25NG0051CONSTRUCTION OF SITIO SANGAY ANOMAR FLOOD MITIGATING STRUCTURE, BRGY. ANOMAR, SURIGAO CITY, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 2nd DEO | On-Going | ₱98.4M | 69% | Medium risk51 | —-0.022 |
| 18 | 23NG0039CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG TAGANA-AN RIVER, TAGANA-AN, SURIGAO DEL NORTE / TAGANA-AN, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 2nd DEO | Completed | ₱96.5M | 100% | Medium risk50 | —-0.061 |
| 19 | 23NG0043CONSTRUCTION OF FLOOD CONTROL IN BARANGAY MASGAD, MALIMONO, SURIGAO DEL NORTE/BRGY. MASGAD, MALIMONO, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 2nd DEO | Completed | ₱96.5M | 100% | Medium risk47 | —-0.061 |
| 20 | 21NG0039CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG SURIGAO RIVER/BRGY. TRINIDAD, SURIGAO CITY, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 2nd DEO | Completed | ₱91.7M | 100% | Medium risk46 | —-0.061 |
| 21 | 24NG0046CONSTRUCTION OF MAGTANGALI FLOOD MITIGATION STRUCTURE ALONG ANAO-AON RIVER, BARANGAY MAGTANGALI, SAN FRANCISCO, SURIGAO DEL NORTE / BRGY. MAGTANGALI, SAN FRANCISCO, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 2nd DEO | Completed | ₱86.8M | 100% | Medium risk46 | —-0.065 |
| 22 | 20IL0041CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF CANTURING FLOOD CONTROL | Region VIII | Southern Leyte 1st DEO | Completed | ₱39.2M | 100% | Medium risk46 | —-0.079 |
| 23 | 20NE0039PAVING OF UNPAVED ROAD ALONG DINAGT-LORETO ROAD K0068+310-K0068+389,K0068+723-K0068+933,K0071+048-K0071+080,K0071+226-K0071+352,K0073+278-K0073+428.23,K0073+475-K0074+000,K0074+215-K0074+433,K0077+779-K0077+850, DINAGAT ISLANDS | Region XIII | Dinagat Islands DEO | Completed | ₱60.3M | 100% | Medium risk45 | —-0.082 |
| 24 | 17NH0051CONSTRUCTION OF BARANGAY POBLACION SITIO BATO-BATO FMR, BARANGAY POBLACION, CARMEN, SURIGAO DEL SUR | Region XIII | Surigao del Sur 1st DEO | Completed | ₱11.5M | 100% | Medium risk44 | —-0.001 |
| 25 | 21NH0035SURIGAO-DAVAO COASTAL ROAD - K1241+000 - K1242+886 | Region XIII | Surigao del Sur 1st DEO | Completed | ₱54.6M | 100% | Medium risk43 | —-0.081 |