Opening the dossier…
Opening the dossier…
Contractor dossier
17 projects on file, including joint ventures this contractor is part of.
Total projects
17
Total budget
₱2.7B
Average progress
89.0%
Completion rate
76.5%
Average risk score
60.1
High risk on average, out of 100
Flagged as unusual
3
17.6% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region IV-A | 11 | ₱964.5M | 58.8 | 2 | 83.3% |
| Region X | 4 | ₱578.8M | 59.7 | 0 | 100.0% |
| Central Office | 1 | ₱872.9M | 75.6 | 1 | 96.1% |
| Region IV-B | 1 | ₱234.3M | 60.9 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Flood Control and Drainage | 6 | ₱508.7M | 54.0 | 0 | 100.0% |
| Roads | 4 | ₱611.1M | 58.2 | 0 | 89.6% |
| Bridges | 3 | ₱291.1M | 61.7 | 1 | 86.0% |
| OTHER | 2 | ₱178.4M | 70.1 | 1 | 50.0% |
| Buildings and Facilities | 1 | ₱872.9M | 75.6 | 1 | 96.1% |
| Bridges, Roads | 1 | ₱188.5M | 64.5 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 18Z00037CONSTRUCTION OF THE PROFESSIONAL REGULATION COMMISSION (PRC) BUILDING, PHASE I | Central Office | Buildings and Special Projects Management Cluster | On-Going | ₱872.9M | 96% | High risk76 | Flagged0.001 |
| 18DF0092LOCAL PROGRAM -CONSTRUCTION/ REPAIR/ REHABILITATION/ IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS, LOCAL ROADS AND BRIDGES, LOCAL ROADS, REMULLA AVENUE CONNECTION ROAD TO TRES CRUSES, TANZA, CAVITE | Region IV-A | Cavite 1st DEO | Completed | ₱137.5M | 100% | High risk71 | —-0.018 |
| 17D00021MFO-1 NATIONAL ROAD NETWORK SERVICES NETWORK DEV'T. IMPROVEMENT/WIDENING OF NATIONAL ROADS PRIMARY ROADS - OTHER PRIMARY ROADS MANILA-CAVITE (NCR BDRY-JCT. CAVITE CITY SECT.) INCL. RROW, CAVITE | Region IV-A | Region IV-A | On-Going | ₱40.8M | 0% | High risk69 | Flagged0.051 |
| 23D00042CONSTRUCTION OF BY-PASS AND DIVERSION ROADS MANILA-CAVITE BY-PASS ROAD, KAWIT SECTION CAVITE | Region IV-A | Region IV-A | Completed | ₱154.4M | 100% | High risk66 | —-0.040 |
| 17K00319COMPL. OF THE EAST WEST LATERAL RD CONNECTING AGUSAN DEL SUR TO BUK JCT. CDO CITY CAMP KIBARITAN DOM | Region X | Region X | Completed | ₱188.5M | 100% | High risk64 | —-0.002 |
| 18K00238CLUSTER 37 CONST./UPGRADING/REHAB. OF DRAINAGE ALONG NATIONAL ROADS IN BUKIDNON | Region X | Region X | Completed | ₱207.3M | 100% | High risk62 | —-0.057 |
| 18E00040ROAD WIDENING OF PTO. PRINCESA NORTH ROAD (PPNR), RBIA STATION: KO014+000-KO015+373; KO015+508-KO020+433; SURVEY STATION: KO014+000-KO015+368; KO015+503-KO020+420, PTO. PRINCESA CITY, PALAWAN | Region IV-B | Region IV-B | Completed | ₱234.3M | 100% | High risk61 | —-0.023 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 17D00021MFO-1 NATIONAL ROAD NETWORK SERVICES NETWORK DEV'T. IMPROVEMENT/WIDENING OF NATIONAL ROADS PRIMARY ROADS - OTHER PRIMARY ROADS MANILA-CAVITE (NCR BDRY-JCT. CAVITE CITY SECT.) INCL. RROW, CAVITE | Region IV-A | Region IV-A | On-Going | ₱40.8M | 0% | High risk69 | Flagged0.051 |
| 17DF0031MFO1 NATIONAL ROAD NETWORK SERVICES - CONSTRUCTION AND MAINTENANCE OF BRIDGES ALONG NATIONAL ROAD, WIDENING OF PERMANENT BRIDGES, INCLUDING ROW TO MORE THAN 2 LANES, KANLURAN BRIDGE (B03406LZ); PAG-ASA BRIDGE (B03407LZ) AND GAHAK BRIDGE (B03408LZ) ALONG | Region IV-A | Cavite 1st DEO | On-Going | ₱31.4M | 58% | Medium risk59 | Flagged0.037 |
| 18Z00037CONSTRUCTION OF THE PROFESSIONAL REGULATION COMMISSION (PRC) BUILDING, PHASE I | Central Office | Buildings and Special Projects Management Cluster | On-Going | ₱872.9M | 96% | High risk76 | Flagged0.001 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 18Z00037CONSTRUCTION OF THE PROFESSIONAL REGULATION COMMISSION (PRC) BUILDING, PHASE I | Central Office | Buildings and Special Projects Management Cluster | On-Going | ₱872.9M | 96% | High risk76 | Flagged0.001 |
| 2 | 18DF0092LOCAL PROGRAM -CONSTRUCTION/ REPAIR/ REHABILITATION/ IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS, LOCAL ROADS AND BRIDGES, LOCAL ROADS, REMULLA AVENUE CONNECTION ROAD TO TRES CRUSES, TANZA, CAVITE | Region IV-A | Cavite 1st DEO | Completed | ₱137.5M | 100% | High risk71 | —-0.018 |
| 3 | 17D00021MFO-1 NATIONAL ROAD NETWORK SERVICES NETWORK DEV'T. IMPROVEMENT/WIDENING OF NATIONAL ROADS PRIMARY ROADS - OTHER PRIMARY ROADS MANILA-CAVITE (NCR BDRY-JCT. CAVITE CITY SECT.) INCL. RROW, CAVITE | Region IV-A | Region IV-A | On-Going | ₱40.8M | 0% | High risk69 | Flagged0.051 |
| 4 | 23D00042CONSTRUCTION OF BY-PASS AND DIVERSION ROADS MANILA-CAVITE BY-PASS ROAD, KAWIT SECTION CAVITE | Region IV-A | Region IV-A | Completed | ₱154.4M | 100% | High risk66 | —-0.040 |
| 5 | 17K00319COMPL. OF THE EAST WEST LATERAL RD CONNECTING AGUSAN DEL SUR TO BUK JCT. CDO CITY CAMP KIBARITAN DOM | Region X | Region X | Completed | ₱188.5M | 100% | High risk64 | —-0.002 |
| 6 | 18K00238CLUSTER 37 CONST./UPGRADING/REHAB. OF DRAINAGE ALONG NATIONAL ROADS IN BUKIDNON | Region X | Region X | Completed | ₱207.3M | 100% | High risk62 | —-0.057 |
| 7 | 18E00040ROAD WIDENING OF PTO. PRINCESA NORTH ROAD (PPNR), RBIA STATION: KO014+000-KO015+373; KO015+508-KO020+433; SURVEY STATION: KO014+000-KO015+368; KO015+503-KO020+420, PTO. PRINCESA CITY, PALAWAN | Region IV-B | Region IV-B | Completed | ₱234.3M | 100% | High risk61 | —-0.023 |
| 8 | 21K00088WIDENING OF PERMANENT BRIDGES, AGUS PARALLEL BR. ALONG OVERTON-BURU-UN BDRY ROAD | Region X | Region X | Completed | ₱105.3M | 100% | Medium risk60 | —-0.038 |
| 9 | 17DF0031MFO1 NATIONAL ROAD NETWORK SERVICES - CONSTRUCTION AND MAINTENANCE OF BRIDGES ALONG NATIONAL ROAD, WIDENING OF PERMANENT BRIDGES, INCLUDING ROW TO MORE THAN 2 LANES, KANLURAN BRIDGE (B03406LZ); PAG-ASA BRIDGE (B03407LZ) AND GAHAK BRIDGE (B03408LZ) ALONG | Region IV-A | Cavite 1st DEO | On-Going | ₱31.4M | 58% | Medium risk59 | Flagged0.037 |
| 10 | 18DF0086ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM,NETWORK DEVELOPMENT PROGRAM, CONSTRUCTION OF MISSING LINKS/NEW ROADS, GENERALAGUINALDO-MAGALLANES-NASUGBU ROAD (EAST-WEST ROAD), AMADEO SECTION, CAVITE | Region IV-A | Cavite 1st DEO | On-Going | ₱91.7M | 58% | Medium risk57 | —-0.017 |
| 11 | 22DF0064ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODSFLOOD MANAGEMENT PROGRAMCONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMSCONSTRUCTION OF REVETMENT ALONG MANILA BAY, BRGY. SAN RAFAEL 4, PHASE 3, N | Region IV-A | Cavite 1st DEO | Completed | ₱89.7M | 100% | Medium risk54 | —-0.068 |
| 12 | 22DF0063ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODSFLOOD MANAGEMENT PROGRAMCONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMSCONSTRUCTION OF REVETMENT ALONG MANILA BAY, BRGY. WAWA 3, ROSARIO, CAVITE | Region IV-A | Cavite 1st DEO | Completed | ₱89.7M | 100% | Medium risk54 | —-0.068 |
| 13 | 22DF0043ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODSFLOOD MANAGEMENT PROGRAMCONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMSCONSTRUCTION OF REVETMENT ALONG MANILA BAY, BARANGAY LIGTONG 1, ROSARIO, C | Region IV-A | Cavite 1st DEO | Completed | ₱89.7M | 100% | Medium risk54 | —-0.068 |
| 14 | 22DF0062ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODSFLOOD MANAGEMENT PROGRAMCONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMSCONSTRUCTION OF REVETMENT ALONG MANILA BAY, BRGY. WAWA 2, ROSARIO, CAVITE | Region IV-A | Cavite 1st DEO | Completed | ₱89.7M | 100% | Medium risk54 | —-0.068 |
| 15 | 22DF0301ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODSFLOOD MANAGEMENT PROGRAMCONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMSCONSTRUCTION OF REVETMENT ALONG PANAMITAN RIVER, BRGY. PANAMITAN, KAWIT, | Region IV-A | Cavite 1st DEO | Completed | ₱89.7M | 100% | Medium risk54 | —-0.075 |
| 16 | 21K00049CONST. OF BYPASS & DIVERSION ROADS, JCT. MARAMAG-MARADUGAO ROAD JCT. LAMPANUSAN ROAD EXT. (JCT. SAYR | Region X | Region X | Completed | ₱77.8M | 100% | Medium risk52 | —-0.080 |
| 17 | 22DF0021ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODSFLOOD MANAGEMENT PROGRAMCONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMSCONSTRUCTION OF REVETMENT ALONG PANAMITAN RIVER, BRGY. BATONG DALIG, KAWIT | Region IV-A | Cavite 1st DEO | Completed | ₱59.9M | 100% | Medium risk52 | —-0.084 |