Contractor dossier
111 projects on file, including joint ventures this contractor is part of.
Total projects
111
Total budget
₱5B
Average progress
97.8%
Completion rate
87.4%
Average risk score
49.5
Medium risk on average, out of 100
Flagged as unusual
6
5.4% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region VII | 101 | ₱4.4B | 49.2 | 5 | 98.2% |
| Region XIII | 7 | ₱339.2M | 44.8 | 0 | 100.0% |
| Negros Island Region | 2 | ₱187M | 84.4 | 1 | 83.4% |
| Region IV-B | 1 | ₱98.8M | 50.5 | 0 | 70.1% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 83 | ₱3B | 45.1 | 0 | 99.9% |
| OTHER | 6 | ₱426.8M | 67.6 | 2 | 90.4% |
| Flood Control and Drainage | 6 | ₱555.1M | 57.2 | 0 | 92.9% |
| Bridges | 6 | ₱318.6M | 51.6 | 0 | 100.0% |
| GAA 2025 OO-1 | 4 | ₱449.7M | 91.5 | 3 | 86.3% |
| Buildings and Facilities | 4 | ₱135.2M | 47.8 | 0 | 90.2% |
| GAA 2025 SSP | 1 | ₱98M | 95.7 | 1 | 60.7% |
| Water Provision and Storage | 1 | ₱29.7M | 44.5 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25HC0055SPECIAL ROAD FUND- MOTOR VEHICLE USERS CHARGE (MVUC) AS PER R.A. 11239: INSTALLATION OF ROADWAY LIGHTING STRUCTURES ALONG SAGBAYAN DANAO ROAD (SDR) PASSING ALL INABANGA NATIONAL ROADS, BOHOL | Region VII | Bohol 2nd DEO | On-Going | ₱98M | 61% | High risk96 | Flagged0.029 |
| 25HL0031ORGANIZATIONAL OUTCOME 001: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: BRIDGE PROGRAM: WIDENING OF PERMANENT BRIDGES: MALOH BR. (B00020NR) ALONG DUMAGUETE SOUTH RD, SIATON, NEGROS ORIENTAL | Negros Island Region | Negros Oriental 3rd DEO | On-Going | ₱114.6M | 67% | High risk95 | Flagged0.012 |
| 25HC0085ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM: ROAD WIDENING- SECONDARY ROADS- THE PRESIDENT CARLOS P. GARCIA CIRCUMFERENTIAL RD - K0087+721-K0089+021, K0095+383-K0095+603, GETAFE, BOHOL | Region VII | Bohol 2nd DEO | On-Going | ₱49.9M | 78% | High risk94 | Flagged0.005 |
| 25H00067OO 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS, THE PRESIDENT CARLOS P. GARCIA CIRCUMFERENTIAL RD (S00104BH) - K0112+226 - K0112+434, K0113+531 - K0114 + 210, K0115+000-K0116+370 | Region VII | Region VII | On-Going | ₱142.6M | 100% | High risk89 | Flagged0.012 |
| 25H00068ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS, LOAY INTERIOR RD (S00100BH) - K0139 + 765 - K0140 + 570, K0146 + 356 - K0147 + 069, K0151 + 522 - K0152 + 705 | Region VII | Region VII | Completed | ₱142.6M | 100% | High risk88 | —-0.009 |
| 18H00033ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE ROAD SYSTEM, BRIDGE PROGRAM REPLACEMENT OF PERMANENT WEAK BRIDGES BACONG BR. (B00005BH) ALONG TAGBILARAN JETAFE SECTION, BOHOL PROVINCE | Region VII | Region VII | Completed | ₱159.3M | 100% | High risk77 | Flagged0.012 |
| 24HL0014ORGANIZATIONAL OUTCOME 001: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: WIDENING OF PERMANENT BRIDGES: MAYABON BR. (B00013NR) ALONG DUMAGUETE SOUTH RD, ZAMBOANGUITA, NEGROS ORIENTAL | Negros Island Region | Negros Oriental 3rd DEO | Completed | ₱72.4M | 100% | High risk74 | —-0.027 |
| 25HA0037CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM - TRIP) - ABATAN-AGAHAY-BUSAO-TORIL-AGHAO ROAD (CABAWAN) LEADING TO SEVERAL TOURISM SITES, MARIBOJOC, BOHOL | Region VII | Bohol 1st DEO | On-Going | ₱25.9M | 92% | High risk66 | —-0.001 |
| 22H00075CSSP-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-RETROFITTING OF JACINTO BORJA 1 BRIDGE, (B00001BH), TAGBILARAN CITY, BOHOL | Region VII | Region VII | On-Going | ₱96.5M | 51% | High risk65 | Flagged0.012 |
| 24H00134CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDING/FACILITIES, CONSTRUCTION OF STORM SURGE PROTECTION STRUCTURE AT BARANGAY PITOGO, CARLOS P. GARCIA, BOHOL | Region VII | Region VII | On-Going | ₱197.6M | 82% | High risk64 | —-0.004 |
| 24H00014OO 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM, PREVENTIVE MAINTENANCE-TERTIARY ROADS, JCT. (TNR) CORTES-BALILIHAN-CATIGBIAN-MACAAS RD, K0017+000-K0017+065, K0017+572-K0018+000, K0019+000-K0019+906, K0024+000-K0025+000,K0 | Region VII | Region VII | Completed | ₱193M | 100% | High risk64 | —-0.064 |
| 22HA0044CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINANGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE, POBLACION AND POBLACION WESTE, STA. 000+000.00 - STA. 006+366.890, CATIGBIAN, BOHOL | Region VII | Bohol 1st DEO | Completed | ₱95.4M | 100% | High risk64 | —-0.067 |
| 22HA0106CONSTRUCTION OF SLOPE PROTECTION STRUCTURE AT ULBUJAN-CAMIAS-CANGGUHA-SAMPOANGON ROAD, CALAPE, BOHOL | Region VII | Bohol 1st DEO | Completed | ₱99M | 100% | High risk63 | —-0.066 |
| 21H00007ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, BRIDGE PROGRAM, WIDENING OF PERMANENT BRIDGES, ABATAN PARALLEL BR. ALONG TAGBILARAN NORTH ROAD (TAGBILARAN-JETAFE SECTION), K010+051.122-K010+425.00, BOHOL PROVINCE | Region VII | Region VII | Completed | ₱115.8M | 100% | High risk63 | —-0.026 |
| 23H00093OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM, PREVENTIVE MAINTENANCE-SECONDARY ROADS, TAGBILARAN EAST ROAD (TAGBILARAN-JAGNA)-K0125+996-K0127+007, K0135+488-K0136+000, K0136+280-K0138+000, K0149+000-K0150+000, BOHOL PROVI | Region VII | Region VII | Completed | ₱159.2M | 100% | High risk63 | —-0.013 |
| 19HB0123ASSET PRESERVATION-PREVENTIVE MAINTENANCE-SECONDARY ROADS-LOAY INTERIOR ROAD KO155+548-KO156+239, KO192+216-KO192+470, KO105+928-KO186+624 | Region VII | Bohol 3rd DEO | Completed | ₱40M | 100% | High risk62 | —-0.030 |
| 19HC0020001: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: ASSET PRESERVATION- PREVENTIVE MAINTENANCE- SECONDARY ROAD AT LOAY INTERIOR ROAD K0148+000-K0149+000 AND K0149+000-K0150+000, DAGOHOY, BOHOL | Region VII | Bohol 2nd DEO | Completed | ₱32.7M | 100% | High risk61 | —-0.028 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25HC0055SPECIAL ROAD FUND- MOTOR VEHICLE USERS CHARGE (MVUC) AS PER R.A. 11239: INSTALLATION OF ROADWAY LIGHTING STRUCTURES ALONG SAGBAYAN DANAO ROAD (SDR) PASSING ALL INABANGA NATIONAL ROADS, BOHOL | Region VII | Bohol 2nd DEO | On-Going | ₱98M | 61% | High risk96 | Flagged0.029 |
| 25H00067OO 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS, THE PRESIDENT CARLOS P. GARCIA CIRCUMFERENTIAL RD (S00104BH) - K0112+226 - K0112+434, K0113+531 - K0114 + 210, K0115+000-K0116+370 | Region VII | Region VII | On-Going | ₱142.6M | 100% | High risk89 | Flagged0.012 |
| 18H00033ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE ROAD SYSTEM, BRIDGE PROGRAM REPLACEMENT OF PERMANENT WEAK BRIDGES BACONG BR. (B00005BH) ALONG TAGBILARAN JETAFE SECTION, BOHOL PROVINCE | Region VII | Region VII | Completed | ₱159.3M | 100% | High risk77 | Flagged0.012 |
| 22H00075CSSP-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-RETROFITTING OF JACINTO BORJA 1 BRIDGE, (B00001BH), TAGBILARAN CITY, BOHOL | Region VII | Region VII | On-Going | ₱96.5M | 51% | High risk65 | Flagged0.012 |
| 25HL0031ORGANIZATIONAL OUTCOME 001: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: BRIDGE PROGRAM: WIDENING OF PERMANENT BRIDGES: MALOH BR. (B00020NR) ALONG DUMAGUETE SOUTH RD, SIATON, NEGROS ORIENTAL | Negros Island Region | Negros Oriental 3rd DEO | On-Going | ₱114.6M | 67% | High risk95 | Flagged0.012 |
| 25HC0085ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM: ROAD WIDENING- SECONDARY ROADS- THE PRESIDENT CARLOS P. GARCIA CIRCUMFERENTIAL RD - K0087+721-K0089+021, K0095+383-K0095+603, GETAFE, BOHOL | Region VII | Bohol 2nd DEO | On-Going | ₱49.9M | 78% | High risk94 | Flagged0.005 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 101 | 18NG0037OFF-CARRIAGEWAY IMPROVEMENT - TERTIARY ROAD PAVING OF SHOULDER JCT. DEL CARMEN-STA. MONICA - SAN ISIDRO ROAD (K0019+-362-K0020+120,K0020+142-K0022+4170, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 1st DEO | Completed | ₱51.1M | 100% | Medium risk42 | —-0.080 |
| 102 | 20NF0003ASSET PRESERVATION-REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS-TERTIARY ROADS ALONG JCT. CANCOHOY-DEL CARMEN RD (S00024SG) | Region XIII | Surigao del Norte 1st DEO | Completed | ₱22M | 100% | Medium risk39 | —-0.083 |
| 103 | 18NG0019REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROAD, DAPA - GEN. LUNA ROAD (K0008+120 - K0009+000) SURIGAO DEL NORTE | Region XIII | Surigao del Norte 1st DEO | Completed | ₱20.7M | 100% | Medium risk38 | —-0.080 |
| 104 | 24HA0007PREVENTIVE MAINTENANCE - SECONDARY ROADS - JCT (TER) DAUIS-PANGLAO RD - K0013+400 - K0013+484 | Region VII | Bohol 1st DEO | Completed | ₱3M | 100% | Low risk22 | —-0.092 |
| 105 | 23HA0038PREVENTIVE MAINTENANCE - TERTIARY ROADS - JCT (TNR) MARIBOJOC-ANTEQUERA-CATAGBACAN (LOON) - K0017+298 - K0017+442 | Region VII | Bohol 1st DEO | Completed | ₱3.4M | 100% | Low risk22 | —-0.093 |
| 106 | 21HC0002ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE -SECONDARY ROADS- TAGBILARAN NORTH RD (TAGBILARAN-JETAFE SECT)- K0116+036-K0116+361, TALIBON, BOHOL | Region VII | Bohol 2nd DEO | Completed | ₱4.6M | 100% | Low risk20 | —-0.096 |
| 107 | 20HA0007PREVENTIVE MAINTENANCE - BALILIHAN-HANOPOL-BATUAN ROAD - K0032+713-K0032+991 | Region VII | Bohol 1st DEO | Completed | ₱2.4M | 100% | Low risk20 | —-0.092 |
| 108 | 19HC0046003 - CONVERGENCE AND SPECIAL SUPPORT PROGRAM CONSTRUCTION/IMPROVEMENT OF ACCESS ROAD LEADING TO DECLARED TOURISM DESTINATIONS - TAMING TO VILLAANUNCIADO ROAD LEADING TO HIGHLAND TOURISM, BRGY. TAMING, DANAO, BOHOL | Region VII | Bohol 2nd DEO | Completed | ₱4.7M | 100% | Low risk20 | —-0.094 |
| 109 | 21HC0003OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM- ASSET PRESERVATION- PREVENTIVE MAINTENANCE- SECONDARY ROAD: TAGBILARAN EAST RD (TAGBILARAN-JAGNA) - K0138+000-K0138+264, UBAY, BOHOL | Region VII | Bohol 2nd DEO | Completed | ₱4.5M | 100% | Low risk20 | —-0.096 |
| 110 | 24HA0041PREVENTIVE MAINTENANCE - SECONDARY ROADS - TAGBILARAN EAST RD (TAGBILARAN-JAGNA) - K0259 + 1341 - K0260 + 000 | Region VII | Bohol 1st DEO | Completed | ₱1.6M | 100% | Low risk18 | —-0.091 |
| 111 | 20HA0056ASPHALTING OF LUCAS ALFARERO ST., PUROK 1, BRGY. SAN ISIDRO, TAGBILARAN CITY, BOHOL | Region VII | Bohol 1st DEO | Completed | ₱954.6K | 100% | Low risk18 | —-0.091 |