Opening the dossier…
Opening the dossier…
Contractor dossier
103 projects on file, including joint ventures this contractor is part of.
Total projects
103
Total budget
₱1.4B
Average progress
92.7%
Completion rate
82.5%
Average risk score
43.8
Medium risk on average, out of 100
Flagged as unusual
8
7.8% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region VIII | 103 | ₱1.4B | 43.8 | 8 | 92.7% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 43 | ₱626.7M | 42.8 | 1 | 93.1% |
| Buildings and Facilities | 34 | ₱295.7M | 37.9 | 0 | 96.1% |
| Bridges | 9 | ₱119.6M | 39.2 | 0 | 100.0% |
| Flood Control and Drainage | 8 | ₱145.8M | 38.1 | 0 | 100.0% |
| OTHER | 7 | ₱134M | 82.4 | 6 | 62.5% |
| GAA 2025 SSP | 1 | ₱29.1M | 95.7 | 1 | 42.3% |
| Water Provision and Storage | 1 | ₱41M | 49.4 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25II0046CONSTRUCTION OF BRGY. DALY-BRGY. BALUD ROAD, SAN ROQUE, NORTHERN SAMAR | Region VIII | Northern Samar 2nd DEO | On-Going | ₱29.1M | 42% | High risk96 | Flagged0.024 |
| 24IH0079CONCRETING OF SITIO PAL-OG, BRGY. POBLACION 5 TO BRGY. SAWANG FMR, BRGY. POBLACION 5 AND BRGY. SAWANG, CAPUL, NORTHERN SAMAR | Region VIII | Northern Samar 1st DEO | On-Going | ₱19.7M | 50% | High risk90 | Flagged0.057 |
| 25II0054CONCRETING OF SITIO CAMAMBANAN TO SITIO GUINBANDERAHAN, BRGY. BANTAYAN FMR, SAN ROQUE, NORTHERN SAMAR | Region VIII | Northern Samar 2nd DEO | On-Going | ₱14.9M | 52% | High risk89 | Flagged0.056 |
| 24I00351CONSTRUCTION OF NEW SUPER HEALTH CENTERS/RHU - CAPUL SUPER HEALTH CENTER, NORTHERN SAMAR, CAPUL, NORTHERN SAMAR | Region VIII | Region VIII | On-Going | ₱11.9M | 100% | High risk89 | Flagged0.037 |
| 23IH0184CONSTRUCTION OF SPORTS CENTER IN NORTHERN SAMAR, CATARMAN, NORTHERN SAMAR | Region VIII | Northern Samar 1st DEO | On-Going | ₱48.2M | 6% | High risk78 | Flagged0.028 |
| 25IH0012CONSTRUCTION/IMPROVEMENT OF CAPUL CIRCUMFERENTIAL ROAD, AGUIN-LANDUSAN-SAWANG-SAGAOSAWAN-JUBANG-OSON-POBLACION SECTION, CAPUL, NORTHERN SAMAR | Region VIII | Northern Samar 1st DEO | On-Going | ₱9.8M | 42% | High risk77 | Flagged0.010 |
| 24IH0059CONSTRUCTION OF MULTI-PURPOSE BUILDING, SAN VICENTE, NORTHERN SAMAR | Region VIII | Northern Samar 1st DEO | On-Going | ₱19.7M | 87% | High risk77 | Flagged0.000 |
| 21II0075CONCRETING/RECONSTRUCTION OF CONCRETE ROAD, POBLACION, LAS NAVAS, NORTHERN SAMAR | Region VIII | Northern Samar 2nd DEO | Completed | ₱9.8M | 100% | High risk76 | —-0.034 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24IH0079CONCRETING OF SITIO PAL-OG, BRGY. POBLACION 5 TO BRGY. SAWANG FMR, BRGY. POBLACION 5 AND BRGY. SAWANG, CAPUL, NORTHERN SAMAR | Region VIII | Northern Samar 1st DEO | On-Going | ₱19.7M | 50% | High risk90 | Flagged0.057 |
| 25II0054CONCRETING OF SITIO CAMAMBANAN TO SITIO GUINBANDERAHAN, BRGY. BANTAYAN FMR, SAN ROQUE, NORTHERN SAMAR | Region VIII | Northern Samar 2nd DEO | On-Going | ₱14.9M | 52% | High risk89 | Flagged0.056 |
| 24I00351CONSTRUCTION OF NEW SUPER HEALTH CENTERS/RHU - CAPUL SUPER HEALTH CENTER, NORTHERN SAMAR, CAPUL, NORTHERN SAMAR | Region VIII | Region VIII | On-Going | ₱11.9M | 100% | High risk89 | Flagged0.037 |
| 23IH0184CONSTRUCTION OF SPORTS CENTER IN NORTHERN SAMAR, CATARMAN, NORTHERN SAMAR | Region VIII | Northern Samar 1st DEO | On-Going | ₱48.2M | 6% | High risk78 | Flagged0.028 |
| 25II0046CONSTRUCTION OF BRGY. DALY-BRGY. BALUD ROAD, SAN ROQUE, NORTHERN SAMAR | Region VIII | Northern Samar 2nd DEO | On-Going | ₱29.1M | 42% | High risk96 | Flagged0.024 |
| 25IH0012CONSTRUCTION/IMPROVEMENT OF CAPUL CIRCUMFERENTIAL ROAD, AGUIN-LANDUSAN-SAWANG-SAGAOSAWAN-JUBANG-OSON-POBLACION SECTION, CAPUL, NORTHERN SAMAR | Region VIII | Northern Samar 1st DEO | On-Going | ₱9.8M | 42% | High risk77 | Flagged0.010 |
| 19IH0066CONSTRUCTION OF ROAD, BRGY. MAKIWALO MONDRAGON, NORTHERN SAMAR | Region VIII | Northern Samar 1st DEO | On-Going | ₱2M | 21% | Low risk23 | Flagged0.002 |
| 24IH0059CONSTRUCTION OF MULTI-PURPOSE BUILDING, SAN VICENTE, NORTHERN SAMAR | Region VIII | Northern Samar 1st DEO | On-Going | ₱19.7M | 87% | High risk77 | Flagged0.000 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 26 | 22IH0093CONSTRUCTION OF MULTI-PURPOSE BUILDING (EVACUATION CENTER), BARANGAY MARAGAT, SAN VICENTE, NORTHERN SAMAR | Region VIII | Northern Samar 1st DEO | Completed | ₱8.7M | 100% | Medium risk49 | —-0.097 |
| 27 | 23IH0153CONSTRUCTION OF 1STY3CL, OSON ES, CAPUL, NORTHERN SAMAR | Region VIII | Northern Samar 1st DEO | Completed | ₱10.3M | 100% | Medium risk49 | —-0.054 |
| 28 | 19II0018RETROFITTING/STRENGTHENING OF PERMANENT BRIDGES, KALAW BR. (B00554SM) ALONG SAN POLICARPO-ARTECHE-LAPINIG RD, LAPINIG, NORTHERN SAMAR | Region VIII | Northern Samar 2nd DEO | Completed | ₱28.5M | 100% | Medium risk49 | —-0.058 |
| 29 | 22IH0108CONSTRUCTION OF MULTIPURPOSE BUILDING, BRGY. JAMOOG, ROSARIO, NORTHERN SAMAR | Region VIII | Northern Samar 1st DEO | Completed | ₱6.8M | 100% | Medium risk49 | —-0.094 |
| 30 | 19IH0133CONSTRUCTION OF 2 STY. 2ICT LAB SCHOOL BUILDING, CAPUL AGRO-INDUSTRIAL SCHOOL, CAPUL, N. SAMAR | Region VIII | Northern Samar 1st DEO | Completed | ₱12.7M | 100% | Medium risk49 | —-0.053 |
| 31 | 18II0131CONSTRUCTION OF TWO (2) UNITS, THREE (3) STOREY - THREE (3) CLASSROOM REGULAR WORKSHOP BUILDING @ GALA VOCATIONAL SCHOOL, GAMAY, NORTHERN SAMAR | Region VIII | Northern Samar 2nd DEO | Completed | ₱34.1M | 100% | Medium risk49 | —-0.042 |
| 32 | 24IH0044CONSTRUCTION/IMPROVEMENT OF CAPUL CIRCUMFERENTIAL ROAD, AGUIN - LANDUSAN - SAWANG - SAGAOSAWAN - JUBANG - OSON - POBLACION SECTION, CAPUL, NORTHERN SAMAR | Region VIII | Northern Samar 1st DEO | On-Going | ₱14.7M | 91% | Medium risk49 | —-0.053 |
| 33 | 18II0051RETROFITTING/STRENGTHENING OF PERMANENT BRIDGES, GAMAY BRIDGE (B00312SM) ALONG PANGPANG-PALAPAG-MAPANAS0GAMAY-LAPINIG ROAD, GAMAY, NORTHERN SAMAR | Region VIII | Northern Samar 2nd DEO | Completed | ₱22.9M | 100% | Medium risk49 | —-0.059 |
| 34 | 22II0047WIDENING OF PERMANENT BRIDGES, SIMORA BR. (B00318SM) ALONG RAWIS - CATUBIG RD., LAOANG, NORTHERN SAMAR | Region VIII | Northern Samar 2nd DEO | Completed | ₱14.4M | 100% | Medium risk48 | —-0.057 |
| 35 | 24IH0010CONSTRUCTION/IMPROVEMENT OF ACCESS ROAD FROM POBLACION (BRGY. SILA) LEADING TO PINK BEACH, BRGY. SILA, SAN VICENTE, NORTHERN SAMAR | Region VIII | Northern Samar 1st DEO | On-Going | ₱14.7M | 77% | Medium risk48 | —-0.048 |
| 36 | 21IH0066CONSTRUCTION OF ROAD, SAN VICENTE, NORTHERN SAMAR | Region VIII | Northern Samar 1st DEO | On-Going | ₱9.9M | 27% | Medium risk48 | —-0.005 |
| 37 | 23IH0048CONSTRUCTION/IMPROVEMENT OF CAPUL CIRCUMFERENTIAL ROAD, AGUIN-LANDUSAN- SAWANG-SAGAOSAWAN-JUBANG-OSON-POBLACION SECTION, CAPUL, NORTHERN SAMAR | Region VIII | Northern Samar 1st DEO | Completed | ₱9.8M | 100% | Medium risk48 | —-0.094 |
| 38 | 24IH0020CONSTRUCTION OF ROAD, PHASE I, BARANGAY POBLACION 5 TO BARANGAY SAWANG, CAPUL, NORTHERN SAMAR | Region VIII | Northern Samar 1st DEO | On-Going | ₱11.9M | 91% | Medium risk48 | —-0.050 |
| 39 | 22IH0070CONSTRUCTION / IMPROVEMENT OF ACCESS ROADS LEADING TO CAPUL CIRCUMFERENTIAL ROAD, AGUIN-LANDUSAN-SAWANG-SAGAOSAWAN-JUBANG-OSON-POBLACION SECTION, CAPUL, NORTHERN SAMAR | Region VIII | Northern Samar 1st DEO | On-Going | ₱7.2M | 95% | Medium risk48 | —-0.035 |
| 40 | 18II0128CONSTRUCTION OF THREE (3) STOREY - THREE (3) CLASSROOM REGULAR WORKSHOP BUILDING @ CATUBIG VALLEY NATIONAL HIGH SCHOOL, CATUBIG, NORTHERN SAMAR | Region VIII | Northern Samar 2nd DEO | Completed | ₱16.8M | 100% | Medium risk48 | —-0.048 |
| 41 | 20II0024WIDENING OF PERMANENT BRIDGES, OPONG BR. (B00323SM) ALONG RAWIS CATUBIG RD., CATUBIG, NORTHERN SAMAR | Region VIII | Northern Samar 2nd DEO | Completed | ₱14M | 100% | Medium risk48 | —-0.056 |
| 42 | 22II0006PREVENTIVE MAINTENANCE, TERTIARY ROADS, ARTECHE-LAS NAVAS-RAWIS RD., K0810+710 - K0813+000, 2ND DISTRICT, NORTHERN SAMAR | Region VIII | Northern Samar 2nd DEO | Completed | ₱28.9M | 100% | Medium risk48 | —-0.092 |
| 43 | 18II0070REHABILITATION OF RAWIS MULTI-PURPOSE BUILDING (COVERED COURT), BRGY. RAWIS, LAOANG, NORTHERN SAMAR | Region VIII | Northern Samar 2nd DEO | Completed | ₱14M | 100% | Medium risk48 | —-0.093 |
| 44 | 20IH0094CONSTRUCTION OF ROAD, BRGY. POLANGI - PATICUA -SAN PASCUAL, CATARMAN, NORTHERN SAMAR | Region VIII | Northern Samar 1st DEO | Completed | ₱14.8M | 100% | Medium risk48 | —-0.094 |
| 45 | 21II0071CONSTRUCTION OF SAN FRANCISCO-QUIRINO ROAD, LAS NAVAS, NORTHERN SAMAR | Region VIII | Northern Samar 2nd DEO | Completed | ₱19.4M | 100% | Medium risk48 | —-0.092 |
| 46 | 20II0025WIDENING OF PERMANENT BRIDGES, TABONON BR. (B00294SM) ALONG CATARMAN - LAOANG RD, SAN ROQUE, NORTHERN SAMAR | Region VIII | Northern Samar 2nd DEO | Completed | ₱17.6M | 100% | Medium risk48 | —-0.058 |
| 47 | 19II0086CONSTRUCTION OF MULTI-PURPOSE BUILDING (LEGISLATIVE BUILDING), PALAPAG, NORTHERN SAMAR | Region VIII | Northern Samar 2nd DEO | Completed | ₱10.5M | 100% | Medium risk48 | —-0.092 |
| 48 | 19II0078REPAIR/REHABILITATION/CONCRETING OF ROAD, BRGY. POBLACION, LAS NAVAS, NORTHERN SAMAR | Region VIII | Northern Samar 2nd DEO | Completed | ₱14.1M | 100% | Medium risk48 | —-0.093 |
| 49 | 22II0001PREVENTIVE MAINTENANCE, SECONDARY ROADS, CATARMAN-LAOANG ROAD, K0765+600-K0766+621; K0766+639-K0767+131 | Region VIII | Northern Samar 2nd DEO | Completed | ₱16M | 100% | Medium risk47 | —-0.094 |
| 50 | 23IH0053CONSTRUCTION/IMPROVEMENT OF ACCESS ROAD FROM POBLACION (BRGY. SILA) LEADING TO PINK BEACH, BRGY. SILA, SAN VICENTE, NORTHERN SAMAR | Region VIII | Northern Samar 1st DEO | Completed | ₱9.8M | 100% | Medium risk47 | —-0.096 |