Contractor dossier
66 projects on file, including joint ventures this contractor is part of.
Total projects
66
Total budget
₱2.8B
Average progress
97.2%
Completion rate
84.8%
Average risk score
51.7
Medium risk on average, out of 100
Flagged as unusual
3
4.5% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region VIII | 65 | ₱2.8B | 52.0 | 3 | 97.2% |
| Region III | 1 | ₱27.9M | 29.1 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 38 | ₱1.5B | 50.7 | 0 | 99.1% |
| Flood Control and Drainage | 12 | ₱484M | 47.7 | 0 | 99.9% |
| Bridges | 6 | ₱164.5M | 45.9 | 0 | 100.0% |
| Buildings and Facilities | 5 | ₱159.5M | 48.3 | 0 | 96.2% |
| OTHER | 3 | ₱355.5M | 84.2 | 2 | 76.9% |
| GAA 2025 OO-1 | 1 | ₱96.5M | 95.1 | 1 | 38.8% |
| Bridges, Roads | 1 | ₱45M | 48.0 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25IA0010NETWORK DEVELOPMENT-CONSTRUCTION OF BY-PASS AND DIVERSION ROADS-PAWIKAN- ESPERANZA DIVERSION RD, BILIRAN | Region VIII | Biliran DEO | On-Going | ₱96.5M | 39% | High risk95 | Flagged0.014 |
| 24I00401NETWORK DEVELOPMENT - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - CONSTRUCTION OF ROAD, TACLOBAN - PALO DIVERSION ROAD INCLUDING DRAINAGE SYSTEM, PACKAGE B-1 | Region VIII | Region VIII | On-Going | ₱182.9M | 33% | High risk92 | Flagged0.082 |
| 23I00117SIPAG - INTERJURISDICTIONAL ROADS AND/OR ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTION - CONSTRUCTION OF TACLOBAN - PALO DIVERSION ROAD INCLUDING DRAINAGE SYSTEM, PACKAGE B - BARANGAY PAWING, PALO, LEYTE | Region VIII | Region VIII | On-Going | ₱144.6M | 98% | High risk83 | Flagged0.025 |
| 17ID0029ASSET PRESERVATION OF NATIONAL ROADS REHABILITATION /RECONSTRUCTION/UPGRADING OF DAMAGED PAVED NATIONAL ROADS INCLUDING DRAINAGE BASED ON PAVEMENT MANAGEMENT SYSTEM/HIGHWAY DEVELOPMENT AND MANAGEMENT -4(HDM-4)- STA. FE-PASTRANA-DAGAMI | Region VIII | Leyte 2nd DEO | Completed | ₱27.9M | 100% | High risk78 | —-0.038 |
| 24IC0071CONSTRUCTION OF FLOOD CONTROL ALONG LIMBUHAN RIVER, BRGY. LIMBUHAN DAKU, TANAUAN, LEYTE | Region VIII | Leyte 1st DEO | Completed | ₱144.7M | 100% | High risk67 | —-0.061 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24I00401NETWORK DEVELOPMENT - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - CONSTRUCTION OF ROAD, TACLOBAN - PALO DIVERSION ROAD INCLUDING DRAINAGE SYSTEM, PACKAGE B-1 | Region VIII | Region VIII | On-Going | ₱182.9M | 33% | High risk92 | Flagged0.082 |
| 23I00117SIPAG - INTERJURISDICTIONAL ROADS AND/OR ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTION - CONSTRUCTION OF TACLOBAN - PALO DIVERSION ROAD INCLUDING DRAINAGE SYSTEM, PACKAGE B - BARANGAY PAWING, PALO, LEYTE | Region VIII | Region VIII | On-Going | ₱144.6M | 98% | High risk83 | Flagged0.025 |
| 25IA0010NETWORK DEVELOPMENT-CONSTRUCTION OF BY-PASS AND DIVERSION ROADS-PAWIKAN- ESPERANZA DIVERSION RD, BILIRAN | Region VIII | Biliran DEO | On-Going | ₱96.5M | 39% | High risk95 | Flagged0.014 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 51 | 19ID0039WIDENING OF PERMANENT BRIDGES-ATIPOLO DACO BRIDGE(B00002LT)ALONG PALO-CARIGARA-ORMOC ROAD | Region VIII | Leyte 2nd DEO | Completed | ₱15.1M | 100% | Medium risk49 | —-0.060 |
| 52 | 18ID0019ASSET PRESERVATION PREVENTIVE MAINTENANCE TERTIARY ROAD-STA. FE-PASTRANA-DAGAMI ROAD ROAD,DAGAMI,LEYTE K0936+000.00-K0937+752.00 | Region VIII | Leyte 2nd DEO | Completed | ₱15.7M | 100% | Medium risk48 | —-0.095 |
| 53 | 18ID0084CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS POBLACION LA PAZ TO CALABATO HOT SPRING,INCLUDING BRIDGE(P00230310VS),LA PAZ,LEYTE | Region VIII | Leyte 2nd DEO | Completed | ₱45M | 100% | Medium risk48 | —-0.085 |
| 54 | 19IA0019RECONSTRUCTION OF BALAQUID FLOOD CONTROL STRUCTURES ALONG BILIRAN CIRCUMFERENTIAL ROAD, CABUCGAYAN, BILIRAN (124.537194°, 11.477034° TO 124.537040°, 11.377889°) | Region VIII | Biliran DEO | Completed | ₱28.5M | 100% | Medium risk47 | —-0.083 |
| 55 | 23IA0019REHABILITATION OF SANTOL FLOOD CONTROL ALONG BILIRAN CIRCUMFERENTIAL ROAD, PHASE III, BILIRAN, BILIRAN (124.470630°, 11.473965° - 124.471379°, 11.475627°), BILIRAN, BILIRAN | Region VIII | Biliran DEO | Completed | ₱19M | 100% | Medium risk47 | —-0.083 |
| 56 | 23IA0089CONSTRUCTION OF SANTOL FLOOD CONTROL ALONG BILIRAN CIRCUMFERENTIAL ROAD, PHASE 5, BILIRAN, BILIRAN | Region VIII | Biliran DEO | Completed | ₱19.1M | 100% | Medium risk47 | —-0.083 |
| 57 | 22IA0036CONSTRUCTION OF MOOG FLOOD CONTROL ALONG BILIRAN CIRCUMFERENTIAL ROAD, BILIRAN, BILIRAN(124.448127°, 11.487753° TO 124.447101°, 11.486432°) | Region VIII | Biliran DEO | Completed | ₱19.6M | 100% | Medium risk47 | —-0.083 |
| 58 | 23IA0017CONSTRUCTION OF MAINIT FLOOD CONTROL ALONG BILIRAN CIRCUMFERENTIAL ROAD, PHASE V, CAIBIRAN, BILIRAN (124.549162°, 11.568609° - 124.549375°, 11.570436°) | Region VIII | Biliran DEO | Completed | ₱24.5M | 100% | Medium risk47 | —-0.082 |
| 59 | 19ID0051CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS CONSTRUCTION OF LUAN SEAWALL,BRGY. LUAN,DULAG,LEYTE | Region VIII | Leyte 2nd DEO | Completed | ₱16.6M | 100% | Medium risk47 | —-0.078 |
| 60 | 19ID0027CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BINAHAAN RIVER K0002+232-K002+847,PASTRANA,LEYTE | Region VIII | Leyte 2nd DEO | Completed | ₱38M | 100% | Medium risk46 | —-0.081 |
| 61 | 22IM0050CONSTRUCTION OF ROAD, BARANGAY 97, PHASE 2, CABALAWAN, TACLOBAN CITY | Region VIII | Tacloban City DEO | Completed | ₱4.8M | 100% | Medium risk45 | —-0.095 |
| 62 | 18CC0155CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF REVETMENT ALONG ANGAT RIVER CALIZON, CALUMPIT, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱27.9M | 100% | Low risk29 | —-0.092 |
| 63 | 21IM0016REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - GOV BENJAMIN KOKOY T ROMUALDEZ DIV RD-(S00254LT) CHAINAGE 0-CHAINAGE 55 (S00255LT) K0908+997-K0909+030, TACLOBAN CITY | Region VIII | Tacloban City DEO | Completed | ₱2.4M | 100% | Low risk25 | —-0.089 |
| 64 | 18IM0027CONSTRUCTION OF BRIDGE - CONSTRUCTION OF FOOTBRIDGE, BRGY. PARAISO, TACLOBAN CITY | Region VIII | Tacloban City DEO | Completed | ₱2.8M | 100% | Low risk25 | —-0.058 |
| 65 | 19IM0016REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS PICAS-SN JOSE DZR AIRPORT RD-K0910+-926 TO K0910+-857, TACLOBAN CITY | Region VIII | Tacloban City DEO | Completed | ₱1.3M | 100% | Low risk21 | —-0.089 |
| 66 | 18IM0036CONSTRUCTION OF MANGROVE CONSERVATION TRAINING CENTER AND NETWORK DEVELOPMENT PROGRAM, BRGY. PARAISO, TACLOBAN CITY | Region VIII | Tacloban City DEO | Completed | ₱1.9M | 100% | Low risk16 | —-0.096 |