Opening the dossier…
Opening the dossier…
Contractor dossier
7 projects on file, including joint ventures this contractor is part of.
Total projects
7
Total budget
₱263.7M
Average progress
85.7%
Completion rate
85.7%
Average risk score
47.1
Medium risk on average, out of 100
Flagged as unusual
0
0.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region III | 5 | ₱242.3M | 47.0 | 0 | 80.0% |
| Region I | 1 | ₱14.7M | 51.2 | 0 | 100.0% |
| National Capital Region | 1 | ₱6.7M | 43.5 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 4 | ₱132.4M | 45.5 | 0 | 100.0% |
| Roads | 2 | ₱117.7M | 59.1 | 0 | 50.0% |
| Bridges | 1 | ₱13.6M | 29.6 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25CH0074CONSTRUCTION OF ROAD WITH DRAINAGE SYSTEM AT THE NEW PORAC MUNICIPAL HALL, BARANGAY CANGATBA PORAC, PAMPANGA | Region III | Pampanga 2nd DEO | On-Going | ₱97.9M | 0% | High risk75 | —-0.002 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
Nothing to report.
No flagged projects here.
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25CH0074CONSTRUCTION OF ROAD WITH DRAINAGE SYSTEM AT THE NEW PORAC MUNICIPAL HALL, BARANGAY CANGATBA PORAC, PAMPANGA | Region III | Pampanga 2nd DEO | On-Going | ₱97.9M | 0% | High risk75 | —-0.002 |
| 2 | 23CH0101CONSTRUCTION OF MULTI-PURPOSE FACILITY (PUBLIC MARKET), PORAC, PAMPANGA | Region III | Pampanga 2nd DEO | Completed | ₱99M | 100% | Medium risk52 | —-0.079 |
| 3 | 19AH0216CONSTRUCTION OF MPB AT BINMALEY CENTRAL SCHOOL, BRGY. POBLACION, BINMALEY, PANGASINAN | Region I | Pangasinan 2nd DEO | Completed | ₱14.7M | 100% | Medium risk51 | —-0.082 |
| 4 | 18OA0129COMPLETION OF FOUR (4) STOREY SIXTEEN (16) CL.RM. SB BANGKULASI ES, NAVOTAS CITY | National Capital Region | Malabon-Navotas DEO | Completed | ₱6.7M | 100% | Medium risk44 | —-0.050 |
| 5 | 24CB0093CONSTRUCTION OF ROAD, BRGY. CUPANG, BALANGA, BATAAN | Region III | Bataan 2nd DEO | Completed | ₱19.8M | 100% | Medium risk43 | —-0.101 |
| 6 | 18CB0108CONSTRUCTION OF TWO(2) STOREY SIX(6) CLASSROOM AT BASECO ELEMENTARY SCHOOL, MARIVELES, BATAAN | Region III | Bataan 2nd DEO | Completed | ₱12.1M | 100% | Medium risk35 | —-0.051 |
| 7 | 18CJ0180BRIDGE PROGRAM REPLACEMENT OF PERMANENT WEAK BRIDGES BALBALATO BR. (B01195LZ) ALONG VICTORIA - PURA RD | Region III | Tarlac DEO | Completed | ₱13.6M | 100% | Low risk30 | —-0.065 |