Contractor dossier
109 projects on file, including joint ventures this contractor is part of.
Total projects
109
Total budget
₱7.4B
Average progress
98.6%
Completion rate
87.2%
Average risk score
47.8
Medium risk on average, out of 100
Flagged as unusual
7
6.4% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region XIII | 102 | ₱7B | 47.5 | 7 | 99.3% |
| Region X | 4 | ₱179.4M | 48.2 | 0 | 86.2% |
| Region VII | 2 | ₱125.3M | 53.6 | 0 | 100.0% |
| Region VIII | 1 | ₱144.7M | 68.4 | 0 | 73.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 44 | ₱2.9B | 44.2 | 2 | 98.0% |
| Flood Control and Drainage | 37 | ₱2.8B | 44.4 | 0 | 99.3% |
| Bridges | 12 | ₱556.3M | 39.9 | 0 | 100.0% |
| Bridges, Roads | 6 | ₱507.5M | 46.2 | 0 | 99.0% |
| GAA 2025 SSP | 4 | ₱292.6M | 95.0 | 4 | 92.9% |
| OTHER | 3 | ₱217M | 77.4 | 0 | 100.0% |
| GAA 2025 OO-2 | 2 | ₱145.2M | 82.6 | 0 | 100.0% |
| GAA 2025 OO-1 | 1 | ₱32.8M | 92.0 | 1 | 97.3% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25NH0057CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY BAYAN, MARIHATAG, SURIGAO DEL SUR | Region XIII | Surigao del Sur 1st DEO | On-Going | ₱48.1M | 97% | High risk96 | Flagged0.019 |
| 25N00080CONSTRUCTION OF LIANGA-BAYABAS BY-PASS ROAD, PHASE IV, BARANGAY SAN PEDRO, LIANGA, SURIGAO DEL SUR | Region XIII | Region XIII | On-Going | ₱140.4M | 82% | High risk95 | Flagged0.031 |
| 25N00079CONSTRUCTION OF ROAD, MARIHATAG - LIANGA, PHASE 3, LIANGA, SURIGAO DEL SUR | Region XIII | Region XIII | On-Going | ₱65.6M | 96% | High risk95 | Flagged0.019 |
| 25NH0060CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY PAYASAN, LIANGA, SURIGAO DEL SUR | Region XIII | Surigao del Sur 1st DEO | On-Going | ₱38.6M | 97% | High risk94 | Flagged0.017 |
| 25N00076LIANGA COASTAL BYPASS ROAD (SDCR ALTERNATE ROUTE), SURIGAO DEL SUR | Region XIII | Region XIII | On-Going | ₱32.8M | 97% | High risk92 | Flagged0.005 |
| 25NB0004CONSTRUCTION OF BANK PROTECTION ALONG WAWA RIVER (POBLACION-SIBAGAT SECTION), SIBAGAT, AGUSAN DEL SUR, SIBAGAT, AGUSAN DEL SUR | Region XIII | Agusan del Sur 1st DEO | Completed | ₱48.9M | 100% | High risk83 | —-0.039 |
| 25NB0017CONSTRUCTION OF BANK PROTECTION ALONG AZPETIA RIVER, DOWNSTREAM, PROSPERIDAD, AGUSAN DEL SUR, PROSPERIDAD, AGUSAN DEL SUR | Region XIII | Agusan del Sur 1st DEO | Completed | ₱96.3M | 100% | High risk83 | —-0.027 |
| 21N00012LANUZA- TANDAG BYPASS ROAD (SDCR ALTERNATE ROUTE), SURIGAO DEL SUR | Region XIII | Region XIII | Completed | ₱101.3M | 100% | High risk78 | —-0.011 |
| 17NH0014COMPLETION OF SEAWALL AT POBLACION, MARIHATAG, SURIGAO DEL SUR | Region XIII | Surigao del Sur 1st DEO | Completed | ₱48.1M | 100% | High risk77 | —-0.021 |
| 22NC0036CONSTRUCTION OF ROAD, JCT BINUCAYAN-PANGIAN-MANDANAO-MABUHAY ROAD, BRGY. BINUCAYAN, LORETO, AGUSAN DEL SUR | Region XIII | Agusan del Sur 2nd DEO | Completed | ₱67.6M | 100% | High risk77 | —-0.020 |
| 24IM0010CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG KAWAYAN RIVER, TACLOBAN CITY | Region VIII | Tacloban City DEO | On-Going | ₱144.7M | 73% | High risk68 | —-0.009 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25N00080CONSTRUCTION OF LIANGA-BAYABAS BY-PASS ROAD, PHASE IV, BARANGAY SAN PEDRO, LIANGA, SURIGAO DEL SUR | Region XIII | Region XIII | On-Going | ₱140.4M | 82% | High risk95 | Flagged0.031 |
| 25N00079CONSTRUCTION OF ROAD, MARIHATAG - LIANGA, PHASE 3, LIANGA, SURIGAO DEL SUR | Region XIII | Region XIII | On-Going | ₱65.6M | 96% | High risk95 | Flagged0.019 |
| 25NH0057CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY BAYAN, MARIHATAG, SURIGAO DEL SUR | Region XIII | Surigao del Sur 1st DEO | On-Going | ₱48.1M | 97% | High risk96 | Flagged0.019 |
| 25NH0060CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY PAYASAN, LIANGA, SURIGAO DEL SUR | Region XIII | Surigao del Sur 1st DEO | On-Going | ₱38.6M | 97% | High risk94 | Flagged0.017 |
| 25N00076LIANGA COASTAL BYPASS ROAD (SDCR ALTERNATE ROUTE), SURIGAO DEL SUR | Region XIII | Region XIII | On-Going | ₱32.8M | 97% | High risk92 | Flagged0.005 |
| 17NH0100ADDITIONAL PAVEMENT WIDTH AND LINED CANAL ALONG SDCR (CARMEN - CORTES SECTION), K1247+000 TO K1272+000, CARMEN & CORTES, SURIGAO DEL SUR | Region XIII | Surigao del Sur 1st DEO | Completed | ₱21.8M | 100% | Medium risk44 | Flagged0.003 |
| 17NH0050CONSTRUCTION OF SITIO SABANG FMR BRGY. POBLACION, CORTES, SURIGAO DEL SUR | Region XIII | Surigao del Sur 1st DEO | Completed | ₱9.4M | 100% | Medium risk41 | Flagged0.001 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 101 | 18NH0074CONSTRUCTION OF DIKE REVETMENT ALONG TAGO RIVER BASIN (SAN MIGUEL PROPER SECTION) PROTECTING THE SAN MIGUEL BRIDGE & POBLACION, SAN MIGUEL, SURIGAO DEL SUR | Region XIII | Surigao del Sur 1st DEO | Completed | ₱32.6M | 100% | Medium risk37 | —-0.063 |
| 102 | 18NH0043CONST. OF DIKE REVETMENT ALONG TAGO RIVER BASIN (ALBA SECTION) PROTECTING THE NATIONAL HIGHWAY, TAGO,SURIGAO DEL SUR | Region XIII | Surigao del Sur 1st DEO | Completed | ₱32.6M | 100% | Medium risk37 | —-0.061 |
| 103 | 22NC0035CONSTRUCTION OF RIVER BANK PROTECTION ALONG IHAWAN RIVER PHASE III, 0+095.00 - 0+210.00, LORETO, AGUSAN DEL SUR | Region XIII | Agusan del Sur 2nd DEO | Completed | ₱33.8M | 100% | Medium risk37 | —-0.063 |
| 104 | 18NH0037NRJ SALVACION-BRITANIA LEADING TO SAN AGUSTIN (BRITANIA ISLANDS & ISLETS), SAN AGUSTIN, SURIGAO DEL SUR | Region XIII | Surigao del Sur 1st DEO | Completed | ₱18.6M | 100% | Medium risk37 | —-0.075 |
| 105 | 18NH0039CONSTRUCTION OF REVETMENT ALONG TAGO RIVER BASIN, TAGO, SURIGAO DEL SUR | Region XIII | Surigao del Sur 1st DEO | Completed | ₱32.5M | 100% | Medium risk37 | —-0.060 |
| 106 | 18NH0002CONSTRUCTION OF DIKE REVETMENT ALONG TAGO RIVER BASIN (GAMUT SECTION) PROTECTING GAMUT BRIDGE, GAMUT, TAGO, SURIGAO DEL SUR | Region XIII | Surigao del Sur 1st DEO | Completed | ₱32.5M | 100% | Medium risk37 | —-0.060 |
| 107 | 23NH0086REHAB. OF SLOPE PROTECTION HUBO BR. (B00733MN), K1362+701 (ABUTMENT B), BRGY. BUHISAN, SAN AGUSTIN, SURIGAO DEL SUR | Region XIII | Surigao del Sur 1st DEO | Completed | ₱9.5M | 100% | Medium risk37 | —-0.058 |
| 108 | 18NH0020KAAYONGAN BRIDGE (B00645MN) ALONG SDCR, CARRASCAL, SURIGAO DEL SUR | Region XIII | Surigao del Sur 1st DEO | Completed | ₱4.6M | 100% | Low risk19 | —-0.040 |
| 109 | 18NH0019HABUYO BRIDGE (B00646MN) ALONG SDCR, CARRASCAL, SURIGAO DEL SUR | Region XIII | Surigao del Sur 1st DEO | Completed | ₱2.8M | 100% | Low risk19 | —-0.046 |