252 projects on file, including joint ventures this contractor is part of.
Total projects
252
Total budget
₱5B
Average progress
99.5%
Completion rate
94.0%
Average risk score
19.8
Low risk on average, out of 100
Flagged as unusual
6
2.4% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region XII | 252 | ₱5B | 19.8 | 6 | 99.5% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 131 | ₱361.9M | 6.0 | 0 | 100.0% |
| Flood Control and Drainage | 47 | ₱2.1B | 29.5 | 0 | 100.0% |
| Roads | 42 | ₱1.2B | 26.5 | 0 | 99.9% |
| Bridges | 16 | ₱356M | 25.8 | 0 | 100.0% |
| GAA 2025 OO-2 | 6 | ₱713.3M | 91.2 | 0 | 95.1% |
| GAA 2025 OO-1 | 6 | ₱304.2M | 91.2 | 5 | 87.6% |
| Water Provision and Storage | 2 | ₱6.8M | 18.4 | 0 | 100.0% |
| GAA 2025 SSP | 1 | ₱8.1M | 76.1 | 0 | 100.0% |
| OTHER | 1 | ₱34.1M | 74.3 | 1 | 80.3% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25MH0010CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE - ISULAN JCT-NINOY AQUINO RD - K1800+500 - K1800+515, K1802+324 - K1802+344, K1808+552 - K1808+577, K1808+900 - K1808+935, K1809+640 - K1809+690, K1810+090 - K1810+115, K1810+245 - K1810+260, K1813+360 - K18 | Region XII | Sultan Kudarat 2nd DEO | On-Going | ₱102.6M | 77% | High risk94 | Flagged0.017 |
| 25MH0007CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE - AWANG-UPI-LEBAK-KALAMANSIG-PALIMBANG-SARANGANI RD - K1961+224 - K1961+270, K1961+431 - K1961+450, K1962+223 - K1962+271, K1962+979 - K1963+029, K1963+055 - K1963+080, K1963+130 - K1963+143, K1963+551 - K19 | Region XII | Region XII | On-Going | ₱81.7M | 81% | High risk92 | Flagged0.012 |
| 25MF0011CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, BUAYAN RIVER, DOWNSTREAM (R/S), LUTAYAN, SULTAN KUDARAT | Region XII | Sultan Kudarat 1st DEO | On-Going | ₱96.4M | 87% | High risk92 | —-0.003 |
| 25MF0010CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, ALA RIVER, PUROK MABUHAY, BRGY. BAMBAD, ISULAN, SULTAN KUDARAT | Region XII | Sultan Kudarat 1st DEO | On-Going | ₱144.7M | 99% | High risk91 | —-0.001 |
| 25MH0025CONSTRUCTION OF RIVER BANK PROTECTION AT BARANGAY GAPOK, SENATOR NINOY AQUINO, SULTAN KUDARAT | Region XII | Sultan Kudarat 2nd DEO | On-Going | ₱106.1M | 100% | High risk91 | —-0.007 |
| 25MH0024CONSTRUCTION OF RIVER BANK PROTECTION AT UPPER MONO RIVER, BARANGAY TITULOK, BAGUMBAYAN, SULTAN KUDARAT | Region XII | Sultan Kudarat 2nd DEO | On-Going | ₱100.8M | 85% | High risk91 | —-0.002 |
| 25MF0009CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, ALA RIVER, TAGA SECTION - UPSTREAM (L/S),LAMBAYONG, SULTAN KUDARAT | Region XII | Sultan Kudarat 1st DEO | On-Going | ₱144.6M | 100% | High risk91 | —-0.002 |
| 25MH0022CONSTRUCTION OF RIVER BANK PROTECTION (UPSTREAM LEFT SIDE), BARANGAY BARONGIS, PALIMBANG, SULTAN KUDARAT | Region XII | Sultan Kudarat 2nd DEO | On-Going | ₱120.6M | 100% | High risk91 | —-0.004 |
| 25MH0005RECONSTRUCTION TO CONCRETE PAVEMENT - AWANG-UPI-LEBAK-KALAMANSIG-PALIMBANG-SARANGANI RD - K2029+246 - K2030+000, K2044+087 - K2044+387 | Region XII | Sultan Kudarat 2nd DEO | On-Going | ₱18.4M | 98% | High risk90 | Flagged0.002 |
| 25MH0012CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE - SNA-LEBAK-KALAMANSIG RD - K1851+050 - K1851+115, K1851+110 - K1851+160, K1851+495 - K1851+585, K1851+854 - K1851+875 | Region XII | Sultan Kudarat 2nd DEO | On-Going | ₱34.2M | 92% | High risk90 | Flagged0.003 |
| 25MH0003RECONSTRUCTION TO CONCRETE PAVEMENT - AWANG-UPI-LEBAK-KALAMANSIG-PALIMBANG-SARANGANI RD - K1998+000 - K1999+197 | Region XII | Sultan Kudarat 2nd DEO | On-Going | ₱21M | 99% | High risk90 | —-0.001 |
| 25MH0019WIDENING OF BRIDGE - BARANAYAN BR. (B00335MN) ALONG AWANG-UPI-LEBAK-KALAMANSIG-PALIMBANG-SARANGANI RD | Region XII | Sultan Kudarat 2nd DEO | On-Going | ₱46.2M | 79% | High risk90 | Flagged0.009 |
| 25MH0101CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY KULAMAN, SEN. NINOY AQUINO, SULTAN KUDARAT | Region XII | Sultan Kudarat 2nd DEO | Completed | ₱8.1M | 100% | High risk76 | —-0.019 |
| 25MF0018CONSTRUCTION OF CONCRETE ROAD - TACURONG EAST BY-PASS ROAD FROM BRGY. SAN ANTONIO-D'LEDESMA-SAN PABLO CONNECTING TO BRGY. KALANDAGAN BARANGAY ROAD IN SUPPORT OF BANANA AND PALM OIL INDUSTRIES, TACURONG CITY, SULTAN KUDARAT | Region XII | Sultan Kudarat 1st DEO | On-Going | ₱34.1M | 80% | High risk74 | Flagged0.005 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25MH0010CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE - ISULAN JCT-NINOY AQUINO RD - K1800+500 - K1800+515, K1802+324 - K1802+344, K1808+552 - K1808+577, K1808+900 - K1808+935, K1809+640 - K1809+690, K1810+090 - K1810+115, K1810+245 - K1810+260, K1813+360 - K18 | Region XII | Sultan Kudarat 2nd DEO | On-Going | ₱102.6M | 77% | High risk94 | Flagged0.017 |
| 25MH0007CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE - AWANG-UPI-LEBAK-KALAMANSIG-PALIMBANG-SARANGANI RD - K1961+224 - K1961+270, K1961+431 - K1961+450, K1962+223 - K1962+271, K1962+979 - K1963+029, K1963+055 - K1963+080, K1963+130 - K1963+143, K1963+551 - K19 | Region XII | Region XII | On-Going | ₱81.7M | 81% | High risk92 | Flagged0.012 |
| 25MH0019WIDENING OF BRIDGE - BARANAYAN BR. (B00335MN) ALONG AWANG-UPI-LEBAK-KALAMANSIG-PALIMBANG-SARANGANI RD | Region XII | Sultan Kudarat 2nd DEO | On-Going | ₱46.2M | 79% | High risk90 | Flagged0.009 |
| 25MF0018CONSTRUCTION OF CONCRETE ROAD - TACURONG EAST BY-PASS ROAD FROM BRGY. SAN ANTONIO-D'LEDESMA-SAN PABLO CONNECTING TO BRGY. KALANDAGAN BARANGAY ROAD IN SUPPORT OF BANANA AND PALM OIL INDUSTRIES, TACURONG CITY, SULTAN KUDARAT | Region XII | Sultan Kudarat 1st DEO | On-Going | ₱34.1M | 80% | High risk74 | Flagged0.005 |
| 25MH0012CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE - SNA-LEBAK-KALAMANSIG RD - K1851+050 - K1851+115, K1851+110 - K1851+160, K1851+495 - K1851+585, K1851+854 - K1851+875 | Region XII | Sultan Kudarat 2nd DEO | On-Going | ₱34.2M | 92% | High risk90 | Flagged0.003 |
| 25MH0005RECONSTRUCTION TO CONCRETE PAVEMENT - AWANG-UPI-LEBAK-KALAMANSIG-PALIMBANG-SARANGANI RD - K2029+246 - K2030+000, K2044+087 - K2044+387 | Region XII | Sultan Kudarat 2nd DEO | On-Going | ₱18.4M | 98% | High risk90 | Flagged0.002 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 226 | 17MH0261CONSTRUCTION OF UNIQUE WORKSHOP (7X22.5) BUILDING AT MANGUDADATU NATIONAL HIGH SCHOOL - VILLAMONTE ANNEX LEBAK, SULTAN KUDARAT | Region XII | Sultan Kudarat 2nd DEO | Completed | ₱3.3M | 100% | Low risk3 | —-0.011 |
| 227 | 17MH0202CONSTRUCTION OF UNIQUE WORKSHOP BUILDING (7X22.5) AT MANGUDADATU NATIONAL HIGH SCHOOL - VILLAMONTE ANNEX LEBAK, SULTAN KUDARAT | Region XII | Sultan Kudarat 2nd DEO | Completed | ₱3.3M | 100% | Low risk3 | —-0.011 |
| 228 | 17MH0307CONSTRUCTION OF ONE (1) STOREY - TWO (2) CLASSROOMS SCHOOL BUILDING WITH TOILET AT LIFI-LIFIAN ELEMENTARY SCHOOL ESPERANZA, SULTAN KUDARAT | Region XII | Sultan Kudarat 2nd DEO | Completed | ₱2.9M | 100% | Low risk3 | —-0.018 |
| 229 | 17MH0220CONSTRUCTION OF ONE (1) STOREY - THREE (3) CLASSROOMS SCHOOL BUILDING WITH TOILET AT TUKA ES BAGUMBAYAN, SULTAN KUDARAT | Region XII | Sultan Kudarat 2nd DEO | Completed | ₱4M | 100% | Low risk3 | —-0.018 |
| 230 | 17MH0260CONSTRUCTION OF ONE (1) STOREY - TWO (2) CLASSROOMS SCHOOL BUILDING AT MANGUDADATU NATIONAL HIGH SCHOOL - VILLAMONTE ANNEX LEBAK, SULTAN KUDARAT | Region XII | Sultan Kudarat 2nd DEO | Completed | ₱2.9M | 100% | Low risk2 | —-0.011 |
| 231 | 17MH0259CONSTRUCTION OF ONE (1) STOREY - TWO (2) CLASSROOMS SCHOOL BUILDING WITH TOILET AT MANGUDADATU NATIONAL HIGH SCHOOL - VILLAMONTE ANNEX LEBAK, SULTAN KUDARAT | Region XII | Sultan Kudarat 2nd DEO | Completed | ₱2.9M | 100% | Low risk2 | —-0.011 |
| 232 | 17MH0158CONSTRUCTION OF ONE (1) STOREY - TWO (2) CLASSROOMS SCHOOL BUILDING AT DATUMANGGONG PRIMARY SCHOOL LEBAK, SULTAN KUDARAT | Region XII | Sultan Kudarat 2nd DEO | Completed | ₱2.7M | 100% | Low risk2 | —-0.011 |
| 233 | 16MH0047CONSTRUCTION OF BIRTHING HOMES, DATU WASAY BHS, KALAMANSIG, SULTAN KUDARAT | Region XII | Sultan Kudarat 2nd DEO | Completed | ₱1.7M | 100% | Low risk2 | —-0.020 |
| 234 | 17MH0276CONSTRUCTION OF UNIQUE WORKSHOP (7X22.5) BUILDING AT LANGGAL NATIONAL HIGH SCHOOL SEN. NINOY AQUINO, SULTAN KUDARAT | Region XII | Sultan Kudarat 2nd DEO | Completed | ₱3.8M | 100% | Low risk2 | —-0.013 |
| 235 | 17MH0274CONSTRUCTION OF UNIQUE WORKSHOP (7X22.5) BUILDING AT DATU WASAY NATIONAL HIGH SCHOOL KALAMANSIG, SULTAN KUDARAT | Region XII | Sultan Kudarat 2nd DEO | Completed | ₱3.4M | 100% | Low risk2 | —-0.007 |
| 236 | 17MH0191CONSTRUCTION OF UNIQUE WORKSHOP BUILDING (7X22.5) AT DATU WASAY NATIONAL HIGH SCHOOL KALAMANSIG, SULTAN KUDARAT | Region XII | Sultan Kudarat 2nd DEO | Completed | ₱3.4M | 100% | Low risk2 | —-0.010 |
| 237 | 17ME0100CONST. OF (1) STOREY (2) CL BLDG. @ ANICETO C. LOPEZ, SR. NHS, MAASIM, SARANGANI PROVINCE | Region XII | Sarangani DEO | Completed | ₱2.5M | 100% | Low risk2 | —-0.013 |
| 238 | 17MH0312CONSTRUCTION OF ONE (1) STOREY - TWO (2) CLASSROOMS SCHOOL BUILDING WITH TOILET AT LAGETEN PRIMARY SCHOOL SEN. NINOY AQUINO, SULTAN KUDARAT | Region XII | Sultan Kudarat 2nd DEO | Completed | ₱2.9M | 100% | Low risk2 | —-0.013 |
| 239 | 17MH0273CONSTRUCTION OF ONE (1) STOREY - TWO (2) CLASSROOMS SCHOOL BUILDING AT DATU WASAY NATIONAL HIGH SCHOOL KALAMANSIG, SULTAN KUDARAT | Region XII | Sultan Kudarat 2nd DEO | Completed | ₱2.9M | 100% | Low risk2 | —-0.010 |
| 240 | 17MH0235CONSTRUCTION OF ONE (1) STOREY - TWO (2) CLASSROOMS SCHOOL BUILDING WITH TOILET AT DIONESIO CAGADOC, SR. MEMORIAL ELEMENTARY SCHOOL PALIMBANG, SULTAN KUDARAT | Region XII | Sultan Kudarat 2nd DEO | Completed | ₱2.9M | 100% | Low risk2 | —-0.012 |
| 241 | 17MH0301CONSTRUCTION OF ONE (1) STOREY - TWO (2) CLASSROOMS SCHOOL BUILDING WITH TOILET AT DOÑA CATALINA MEMORIAL ELEMENTARY SCHOOL PALIMBANG, SULTAN KUDARAT | Region XII | Sultan Kudarat 2nd DEO | Completed | ₱2.9M | 100% | Low risk2 | —-0.018 |
| 242 | 17MH0210CONSTRUCTION OF UNIQUE WORKSHOP BUILDING (7X22.5) AT PALIMBANG NATIONAL HIGH SCHOOL - (C) PALIMBANG SULTAN KUDARAT | Region XII | Sultan Kudarat 2nd DEO | Completed | ₱3.3M | 100% | Low risk2 | —-0.019 |
| 243 | 17MH0209CONSTRUCTION OF UNIQUE WORKSHOP BUILDING (7X22.5) AT PALIMBANG NATIONAL HIGH SCHOOL - (B) PALIMBANG, SULTAN KUDARAT | Region XII | Sultan Kudarat 2nd DEO | Completed | ₱3.3M | 100% | Low risk2 | —-0.019 |
| 244 | 17MH0161CONSTRUCTION OF ONE (1) STOREY - TWO (2) CLASSROOMS SCHOOL BUILDING AT KIPONGET ELEMENTARY SCHOOL PALIMBANG, SULTAN KUDARAT | Region XII | Sultan Kudarat 2nd DEO | Completed | ₱2.7M | 100% | Low risk2 | —-0.018 |
| 245 | 17MH0172CONSTRUCTION OF ONE (1) UNIT, ONE (1) STOREY - TWO (2) CLASSROOMS SCHOOL BUILDING AT KUBO BANDAY ELEMENTARY SCHOOL - (A) KALAMANSIG, SULTAN KUDARAT | Region XII | Sultan Kudarat 2nd DEO | Completed | ₱2.7M | 100% | Low risk2 | —-0.011 |
| 246 | 17MH0173CONSTRUCTION OF ONE (1) UNIT, ONE (1) STOREY - TWO (2) CLASSROOMS SCHOOL BUILDING AT KUBO BANDAY ELEMENTARY SCHOOL - (B) KALAMANSIG, SULTAN KUDARAT | Region XII | Sultan Kudarat 2nd DEO | Completed | ₱2.7M | 100% | Low risk2 | —-0.011 |
| 247 | 17MH0160CONSTRUCTION OF ONE (1) STOREY - TWO (2) CLASSROOMS SCHOOL BUILDING AT DATUSIPOT ELEMENTARY SCHOOL PALIMBANG, SULTAN KUDARAT | Region XII | Sultan Kudarat 2nd DEO | Completed | ₱2.7M | 100% | Low risk2 | —-0.019 |
| 248 | 17MH0226CONSTRUCTION OF ONE (1) STOREY - TWO (2) CLASSROOMS SCHOOL BUILDING WITH TOILET AT MALEGDEG ELEMENTARY SCHOOL SEN. NINOY AQUINO, SULTAN KUDARAT | Region XII | Sultan Kudarat 2nd DEO | Completed | ₱2.8M | 100% | Low risk2 | —-0.013 |
| 249 | 17MH0300CONSTRUCTION OF ONE (1) STOREY - TWO (2) CLASSROOMS SCHOOL BUILDING WITH TOILET AT ISUKO ELEMENTARY SCHOOL PALIMBANG, SULTAN KUDARAT | Region XII | Sultan Kudarat 2nd DEO | Completed | ₱2.9M | 100% | Low risk2 | —-0.016 |
| 250 | 17MH0203CONSTRUCTION OF ONE (1) STOREY - TWO (2) CLASSROOMS SCHOOL BUILDING WITH TOILET AT ISUKO ELEMENTARY SCHOOL PALIMBANG, SULTAN KUDARAT | Region XII | Sultan Kudarat 2nd DEO | Completed | ₱2.9M | 100% | Low risk2 | —-0.016 |