Contractor dossier
12 projects on file, including joint ventures this contractor is part of.
Total projects
12
Total budget
₱243.6M
Average progress
53.9%
Completion rate
25.0%
Below 70%
Average risk score
47.2
Medium risk on average, out of 100
Flagged as unusual
1
8.3% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| National Capital Region | 8 | ₱165.5M | 45.9 | 1 | 56.5% |
| Region VIII | 4 | ₱78M | 49.7 | 0 | 48.8% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 11 | ₱224.4M | 47.3 | 1 | 56.1% |
| Flood Control and Drainage | 1 | ₱19.1M | 45.7 | 0 | 30.5% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
Nothing to report.
No high-risk projects here.
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24OF0273REHABILITATION/IMPROVEMENT OF FREEDOM PARK ROAD, BARANGAY BATASAN HILLS, QUEZON CITY | National Capital Region | Quezon City 1st DEO | On-Going | ₱19.2M | 0% | Medium risk49 | Flagged0.020 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 24IE0055ROAD CONCRETING, BRGY. JALAS TO BRGY. BUGA BUGA VILLABA, LEYTE | Region VIII | Leyte 3rd DEO | On-Going | ₱48.6M | 95% | Medium risk53 | —-0.052 |
| 2 | 25IE0050CONSTRUCTION OF ROAD, BARANGAY MATAGOK, CALUBIAN, LEYTE | Region VIII | Leyte 3rd DEO | On-Going | ₱4.9M | 0% | Medium risk49 | —-0.032 |
| 3 | 25IE0051CONSTRUCTION OF ROAD, BARANGAY CRISTINA, CALUBIAN, LEYTE | Region VIII | Leyte 3rd DEO | On-Going | ₱4.9M | 0% | Medium risk49 | —-0.032 |
| 4 | 25IE0024CONSTRUCTION OF JNR BALITE-SAN VICENTE-CATAGBACAN ROAD, VILLABA, LEYTE | Region VIII | Leyte 3rd DEO | On-Going | ₱19.6M | 100% | Medium risk49 | —-0.064 |
| 5 | 24OF0273REHABILITATION/IMPROVEMENT OF FREEDOM PARK ROAD, BARANGAY BATASAN HILLS, QUEZON CITY | National Capital Region | Quezon City 1st DEO | On-Going | ₱19.2M | 0% | Medium risk49 | Flagged0.020 |
| 6 | 25OF0031IMPROVEMENT OF ROAD, BARANGAY BATASAN HILLS, QUEZON CITY | National Capital Region | Quezon City 1st DEO | On-Going | ₱24.4M | 22% | Medium risk46 | —-0.043 |
| 7 | 25OF0030IMPROVEMENT OF ROAD, BARANGAY BAGONG SILANGAN, QUEZON CITY | National Capital Region | Quezon City 1st DEO | On-Going | ₱24.3M | 25% | Medium risk46 | —-0.043 |
| 8 | 25OF0032IMPROVEMENT OF ROAD, BARANGAY COMMONWEALTH, QUEZON CITY | National Capital Region | Quezon City 1st DEO | On-Going | ₱24.2M | 74% | Medium risk46 | —-0.061 |
| 9 | 24OF0102IMPROVEMENT OF ROAD, BRGY. COMMONWEALTH, QUEZON CITY | National Capital Region | Quezon City 1st DEO | Completed | ₱20.4M | 100% | Medium risk46 | —-0.097 |
| 10 | 24OF0042IMPROVEMENT OF ROAD, BRGY. BAGONG SILANGAN, QUEZON CITY | National Capital Region | Quezon City 1st DEO | Completed | ₱24.3M | 100% | Medium risk46 | —-0.099 |
| 11 | 25OF0071CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG SAN FRANCISCO RIVER (PHASE IV), QUEZON CITY | National Capital Region | Quezon City 1st DEO | On-Going | ₱19.1M | 30% | Medium risk46 | —-0.038 |
| 12 | 23OF0194CONSTRUCTION OF ROAD AT ACACIA TO TALISAY, BRGY. PAYATAS, QUEZON CITY | National Capital Region | Quezon City 1st DEO | Completed | ₱9.6M | 100% | Medium risk42 | —-0.045 |