Contractor dossier
34 projects on file, including joint ventures this contractor is part of.
Total projects
34
Total budget
₱381M
Average progress
92.9%
Completion rate
79.4%
Average risk score
42.4
Medium risk on average, out of 100
Flagged as unusual
2
5.9% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region VIII | 34 | ₱381M | 42.4 | 2 | 92.9% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 17 | ₱86.7M | 37.8 | 1 | 97.6% |
| Roads | 6 | ₱77.2M | 43.2 | 0 | 100.0% |
| Water Provision and Storage | 5 | ₱25.1M | 46.9 | 0 | 80.0% |
| Flood Control and Drainage | 3 | ₱173.5M | 53.0 | 0 | 100.0% |
| Bridges | 2 | ₱11.6M | 34.9 | 0 | 100.0% |
| OTHER | 1 | ₱6.8M | 77.5 | 1 | 0.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24IC0105REHABILITATION OF ROAD (DEL PILAR ST., BABULA ST., AND ROXAS ST.), BRGY. LIBTONG, SAN MIGUEL, LEYTE | Region VIII | Leyte 1st DEO | On-Going | ₱6.8M | 0% | High risk78 | Flagged0.028 |
| 25IE0081CONSTRUCTION OF WATER SUPPLY SYSTEM, BARANGAY ABIJAO, VILLABA, LEYTE | Region VIII | Leyte 3rd DEO | On-Going | ₱4.9M | 100% | High risk66 | —-0.011 |
| 23IC0112FLOOD MANAGEMENT PROGRAM - CONST./MAINT. OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONST. OF FLOOD CONTROL ALONG LIBTONG BRIDGE (DOWNSTREAM), BRGY. LIBTONG, SAN MIGUEL, LEYTE | Region VIII | Leyte 1st DEO | Completed | ₱96.4M | 100% | High risk63 | —-0.070 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24IC0105REHABILITATION OF ROAD (DEL PILAR ST., BABULA ST., AND ROXAS ST.), BRGY. LIBTONG, SAN MIGUEL, LEYTE | Region VIII | Leyte 1st DEO | On-Going | ₱6.8M | 0% | High risk78 | Flagged0.028 |
| 23IE0110CONSTRUCTION OF 1-UNIT 2STY4CL SCHOOL BUILDING, VILLABA NATIONAL COMPREHENSIVE HIGH SCHOOL, VILLABA, LEYTE | Region VIII | Leyte 3rd DEO | On-Going | ₱10M | 65% | Medium risk52 | Flagged0.003 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 24IC0105REHABILITATION OF ROAD (DEL PILAR ST., BABULA ST., AND ROXAS ST.), BRGY. LIBTONG, SAN MIGUEL, LEYTE | Region VIII | Leyte 1st DEO | On-Going | ₱6.8M | 0% | High risk78 | Flagged0.028 |
| 2 | 25IE0081CONSTRUCTION OF WATER SUPPLY SYSTEM, BARANGAY ABIJAO, VILLABA, LEYTE | Region VIII | Leyte 3rd DEO | On-Going | ₱4.9M | 100% | High risk66 | —-0.011 |
| 3 | 23IC0112FLOOD MANAGEMENT PROGRAM - CONST./MAINT. OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONST. OF FLOOD CONTROL ALONG LIBTONG BRIDGE (DOWNSTREAM), BRGY. LIBTONG, SAN MIGUEL, LEYTE | Region VIII | Leyte 1st DEO | Completed | ₱96.4M | 100% | High risk63 | —-0.070 |
| 4 | 25IE0070CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY HALL, BARANGAY LIBAGONG, VILLABA, LEYTE | Region VIII | Leyte 3rd DEO | On-Going | ₱4.9M | 100% | Medium risk53 | —-0.066 |
| 5 | 23IE0110CONSTRUCTION OF 1-UNIT 2STY4CL SCHOOL BUILDING, VILLABA NATIONAL COMPREHENSIVE HIGH SCHOOL, VILLABA, LEYTE | Region VIII | Leyte 3rd DEO | On-Going | ₱10M | 65% | Medium risk52 | Flagged0.003 |
| 6 | 23IE0046CONSTRUCTION OF MULTI-PURPOSE BUILDING AT IGANG ELEMENTARY SCHOOL, BARANGAY IGANG, CALUBIAN, LEYTE | Region VIII | Leyte 3rd DEO | Completed | ₱4.9M | 100% | Medium risk52 | —-0.098 |
| 7 | 20IC0059CONSTRUCTION OF SAN MIGUEL INTEGRATED TRANSPORT TERMINAL, SAN MIGUEL, LEYTE | Region VIII | Leyte 1st DEO | Completed | ₱14.7M | 100% | Medium risk52 | —-0.096 |
| 8 | 24IC0179CONCRETING OF SITIO CASAGUINGAN, BRGY. BAIRAN TO BRGY. MALAGUINABOT FMR, BRGY. BAIRAN AND BRGY. MALAGUINABOT, SAN MIGUEL, LEYTE | Region VIII | Leyte 1st DEO | Completed | ₱23.8M | 100% | Medium risk51 | —-0.042 |
| 9 | 25IE0039CONSTRUCTION OF MULTI-PURPOSE BUILDING, SCHOOL BUILDING, CASILION ELEMENTARY SCHOOL, BARANGAY CASILION, VILLABA, LEYTEVILLABA, LEYTE | Region VIII | Leyte 3rd DEO | On-Going | ₱4.9M | 94% | Medium risk51 | —-0.061 |
| 10 | 23IE0104CONSTRUCTION OF 1-UNIT 3CL SCHOOL BUILDING, VILLABA NATIONAL HIGH SCHOOL (LNCAST), VILLABA, LEYTE | Region VIII | Leyte 3rd DEO | Completed | ₱7.5M | 100% | Medium risk51 | —-0.055 |
| 11 | 21IG0099CONCRETING OF BRGY. STO. ÑINO, BATO TO BRGY. TIGBAO, MATALOM FMR, BRGY. STO. ÑINO, BATO AND BRGY. TIGBAO, MATALOM, LEYTE | Region VIII | Leyte 5th DEO | Completed | ₱16.9M | 100% | Medium risk50 | —-0.042 |
| 12 | 25IE0062CONSTRUCTION OF WATER SUPPLY SYSTEM, BARANGAY TABING, TABANGO, LEYTE | Region VIII | Leyte 3rd DEO | On-Going | ₱4.9M | 0% | Medium risk50 | —-0.006 |
| 13 | 25IE0068CONSTRUCTION OF WATER SUPPLY SYSTEM, BARANGAY SANTA ROSA, TABANGO, LEYTE | Region VIII | Leyte 3rd DEO | On-Going | ₱4.9M | 100% | Medium risk50 | —-0.034 |
| 14 | 24IE0076CONSTRUCTION OF 1-STOREY 2-CLASSROOM SCHOOL BUILDING IN PAYAO ELEMENTARY SCHOOL, BARANGAY PAYAO, VILLABA, LEYTE | Region VIII | Leyte 3rd DEO | Completed | ₱5M | 100% | Medium risk50 | —-0.055 |
| 15 | 24IE0077CONSTRUCTION OF 1-STOREY 2-CLASSROOM SCHOOL BUILDING IN HINABUYAN HIGH SCHOOL ANNEX, BARANGAY HINABUYAN, VILLABA, LEYTE | Region VIII | Leyte 3rd DEO | Completed | ₱5M | 100% | Medium risk50 | —-0.055 |
| 16 | 20IC0048FLOOD CONTROL AND DRAINAGE - FLOOD CONTROL STRUCTURES/FACILITIES - CONST. OF FLOOD CONTROL ALONG SAPINITON RIVER, BRGY. BAHAY, SAN MIGUEL, LEYTE | Region VIII | Leyte 1st DEO | Completed | ₱48.2M | 100% | Medium risk49 | —-0.082 |
| 17 | 21IC0007BUILDING AND OTHER STRUCTURE - MULTI-PURPOSE/FACILITIES - LOCAL INFRASTRUCTURE PROGRAM - CONST. OF MULTI-PURPOSE BUILDING (COVERED COURT), BRGY. PITOGO, STA. FE, LEYTE | Region VIII | Leyte 1st DEO | Completed | ₱5.5M | 100% | Medium risk49 | —-0.097 |
| 18 | 18IC0054CONST. OF MULTI-PURPOSE BUILDING (SENIOR CITIZENS CENTER) BRGY. PAWING, PALO,LEYTE | Region VIII | Leyte 1st DEO | Completed | ₱4.8M | 100% | Medium risk49 | —-0.096 |
| 19 | 20IC0068WATER MANAGEMENT FACILITIES-WATER SUPPLY-CONST./REPAIR/REHAB./IMPROV. OF VARIOUS INFRA. INCLUDING LOCAL PROJECTS-CONST. OF WATER SUPPLY SYS. -CONST. OF GROUND WATER TANK WITH PE LINER, SAN MIGUEL, LEYTE | Region VIII | Leyte 1st DEO | Completed | ₱8.8M | 100% | Medium risk49 | —-0.063 |
| 20 | 23IC0050CONCRETING OF CARAYCARAY TO IMPO ROAD, SAN MIGUEL, LEYTE | Region VIII | Leyte 1st DEO | Completed | ₱9.8M | 100% | Medium risk48 | —-0.096 |
| 21 | 20IC0022CONST./MAINT. OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONST. OF SLOPE PROTECTION ALONG SAPINITON RIVER (CARAYCARAY BRIDGE DOWNSTREAM) STA. 004+925 - STA. 005+381, BRGY. CARAYCARAY, SAN MIGUEL, LEYTE | Region VIII | Leyte 1st DEO | Completed | ₱28.9M | 100% | Medium risk47 | —-0.082 |
| 22 | 17IC0002RETROFITTING/STRENGTHENING OF PERMANENT BRIDGES, TELEGRAFO 1 BRIDGE (B00039LT) ALONG DAANG MAHARLIKA (LT), TOLOSA, LEYTE | Region VIII | Leyte 1st DEO | Completed | ₱7.3M | 100% | Medium risk45 | —-0.033 |
| 23 | 21IC0054CONCRETING OF BRGY. CARAYCARAY TO BRGY. KINALUMSAN FMR, BRGY. CARAYCARAY AND BRGY. KINALUMSAN, SAN MIGUEL, LEYTE. | Region VIII | Leyte 1st DEO | Completed | ₱12.4M | 100% | Medium risk45 | —-0.046 |
| 24 | 22IC0083CONCRETING OF BRGY. CARAYCARAY TO BRGY. KINALUMSAN FMR PHASE II, BRGY. CARAYCARAY AND BRGY. KINALUMSAN, SAN MIGUEL, LEYTE | Region VIII | Leyte 1st DEO | Completed | ₱12.4M | 100% | Medium risk45 | —-0.043 |
| 25 | 25IE0037CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, PHASE 2, BARANGAY CABUNGAHAN, VILLABA, LEYTE | Region VIII | Leyte 3rd DEO | Completed | ₱2M | 100% | Low risk26 | —-0.098 |