Contractor dossier
13 projects on file, including joint ventures this contractor is part of.
Total projects
13
Total budget
₱321.6M
Average progress
68.1%
Completion rate
30.8%
Below 70%
Average risk score
52.0
Medium risk on average, out of 100
Flagged as unusual
0
0.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region III | 13 | ₱321.6M | 52.0 | 0 | 68.1% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 8 | ₱93.7M | 45.2 | 0 | 54.1% |
| Buildings and Facilities | 2 | ₱10.9M | 42.7 | 0 | 100.0% |
| GAA 2025 OO-2 | 1 | ₱28.3M | 80.9 | 0 | 72.3% |
| Flood Control and Drainage | 1 | ₱142.5M | 80.2 | 0 | 79.8% |
| OTHER | 1 | ₱46.2M | 68.9 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25CO0003FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF SLOPE PROTECTION STRUCTURE AT DALAO CIS, DINALUPIHAN, BATAAN | Region III | Bataan 3rd DEO | On-Going | ₱28.3M | 72% | High risk81 | —-0.016 |
| 24C00003FLOOD MANAGEMENT PROGRAM-CONST./MAINT. OF FLOOD MITIGATION STRUCTURES & DRAINAGE SYSTEMS-CONST. OF SLOPE PROTECTION STRUCTURES ALONG DILA-DILA CREEK, DINALUPIHAN CENTRAL BUSINESS DIST. SAPANG PUTOL (TRIBUTARY TO COLO CREEK), DINALUPIHAN, BATAAN | Region III | Region III | On-Going | ₱142.5M | 80% | High risk80 | —-0.002 |
| 24C00169CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI PURPOSE BLDG/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. BANGAL, DINALUPIHAN, BATAAN | Region III | Region III | Completed | ₱7.9M | 100% | High risk72 | —-0.069 |
| 25CO0012SUSTAINABLE INFRASTUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD, BRGY NEW SAN JOSE, DINALUPIHAN, BATAAN | Region III | Bataan 3rd DEO | On-Going | ₱8.5M | 0% | High risk69 | —-0.013 |
| 23C00261FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL PROJECT ALONG BANGAL RIVER, BRGY. BANGAL PHASE - IGD, DINALUPIHAN, BATAAN | Region III | Region III | On-Going | ₱46.2M | 100% | High risk69 | —-0.001 |
| 25CO0069ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - PRIMARY ROADS - JOSE ABAD SANTOS AVE (JASA) - DINALUPIHAN, BATAAN | Region III | Bataan 3rd DEO | On-Going | ₱8M | 4% | High risk69 | —-0.016 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
Nothing to report.
No flagged projects here.
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25CO0003FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF SLOPE PROTECTION STRUCTURE AT DALAO CIS, DINALUPIHAN, BATAAN | Region III | Bataan 3rd DEO | On-Going | ₱28.3M | 72% | High risk81 | —-0.016 |
| 2 | 24C00003FLOOD MANAGEMENT PROGRAM-CONST./MAINT. OF FLOOD MITIGATION STRUCTURES & DRAINAGE SYSTEMS-CONST. OF SLOPE PROTECTION STRUCTURES ALONG DILA-DILA CREEK, DINALUPIHAN CENTRAL BUSINESS DIST. SAPANG PUTOL (TRIBUTARY TO COLO CREEK), DINALUPIHAN, BATAAN | Region III | Region III | On-Going | ₱142.5M | 80% | High risk80 | —-0.002 |
| 3 | 24C00169CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI PURPOSE BLDG/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. BANGAL, DINALUPIHAN, BATAAN | Region III | Region III | Completed | ₱7.9M | 100% | High risk72 | —-0.069 |
| 4 | 25CO0012SUSTAINABLE INFRASTUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD, BRGY NEW SAN JOSE, DINALUPIHAN, BATAAN | Region III | Bataan 3rd DEO | On-Going | ₱8.5M | 0% | High risk69 | —-0.013 |
| 5 | 23C00261FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL PROJECT ALONG BANGAL RIVER, BRGY. BANGAL PHASE - IGD, DINALUPIHAN, BATAAN | Region III | Region III | On-Going | ₱46.2M | 100% | High risk69 | —-0.001 |
| 6 | 25CO0069ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - PRIMARY ROADS - JOSE ABAD SANTOS AVE (JASA) - DINALUPIHAN, BATAAN | Region III | Bataan 3rd DEO | On-Going | ₱8M | 4% | High risk69 | —-0.016 |
| 7 | 25CO0007CONVERGENCE & SPECIAL SUPPORT PROG - CONST./IMPROV. OF ACCESS RD LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES (RDS LEVERAGING LINKAGES FOR INDUSTRY & TRADE INFRASTRUCTURE PROG - ROLL IT) BRGY.TUBO-TUBO RD LEADING TO AGRO-TOURISM AREA, DINALUPIHAN, BAT | Region III | Bataan 3rd DEO | On-Going | ₱2.4M | 0% | Medium risk49 | —-0.012 |
| 8 | 23C00204ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROAD - JCT LAYAC-BALANGA-MARIVELES PORT RD - MARIVELES, BATAAN | Region III | Region III | Completed | ₱18M | 100% | Medium risk44 | —-0.101 |
| 9 | 23C00260CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES, AND ECONOMIC ZONES (ROLL-IT) - BRGY. TUBO-TUBO ROAD LEADING TO AGRO-TOURISM AREA, DINALUPIHAN, BATAAN | Region III | Region III | On-Going | ₱48.3M | 29% | Medium risk40 | —-0.039 |
| 10 | 24C00055CONVERGENCE & SPECIAL SUPPORT PROG - CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES & ECONOMIC ZONES (ROLL-IT) - BRGY. TUBO-TUBO ROAD LEADING TO AGRO-TOURISM AREA. DINALUPIHAN, BATAAN | Region III | Region III | On-Going | ₱1.9M | 100% | Medium risk40 | —-0.034 |
| 11 | 24CA0005BASIC INFRASTRUCTURE PROGRAM - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - REHABILITATION OF SIONGCO ROAD, BARANGAY OMBOY, ABUCAY, BATAAN | Region III | Bataan 1st DEO | Completed | ₱4.9M | 100% | Medium risk39 | —-0.099 |
| 12 | 23C00217CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (BARANGAY HEALTH CENTER), BARANGAY TUBO-TUBO, DINALUPIHAN, BATAAN | Region III | Region III | On-Going | ₱3M | 100% | Low risk13 | —-0.060 |
| 13 | 24CA0002ASSET PRESERVATION PROGRAM -REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS - JOSE ABAD SANTOS AVE (JASA) - KO097+956-KO098+057, HERMOSA, BATAAN | Region III | Bataan 1st DEO | Completed | ₱1.8M | 100% | Low risk12 | —-0.100 |