54 projects on file, including joint ventures this contractor is part of.
Total projects
54
Total budget
₱1.2B
Average progress
99.8%
Completion rate
96.3%
Average risk score
36.4
Medium risk on average, out of 100
Flagged as unusual
1
1.9% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region IV-B | 54 | ₱1.2B | 36.4 | 1 | 99.8% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 19 | ₱309.2M | 27.3 | 0 | 100.0% |
| Roads | 17 | ₱372.3M | 37.2 | 1 | 100.0% |
| Flood Control and Drainage | 12 | ₱361.5M | 38.9 | 0 | 99.7% |
| Bridges | 2 | ₱45.7M | 38.2 | 0 | 100.0% |
| GAA 2025 OO-1 | 1 | ₱13.3M | 91.4 | 0 | 93.7% |
| GAA 2025 OO-2 | 1 | ₱22.1M | 87.3 | 0 | 100.0% |
| Bridges, Roads | 1 | ₱91.7M | 54.7 | 0 | 100.0% |
| Water Provision and Storage | 1 | ₱9.8M | 36.6 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25EI0003CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - SECONDARY ROADS - CALAPAN SOUTH RD - K0153+480 - K0153+861, MANSALAY, ORIENTAL MINDORO | Region IV-B | Southern Mindoro DEO | On-Going | ₱13.3M | 94% | High risk91 | —-0.006 |
| 25EI0025CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION OF BALITE RIVER FLOOD CONTROL STRUCTURE, BARANGAY BUONG LUPA, GLORIA, ORIENTAL MINDORO | Region IV-B | Southern Mindoro DEO | Completed | ₱22.1M | 100% | High risk87 | —-0.040 |
| 22E00061SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-CONSTRUCTION OF CAGANCAN RIVER CONTROL, STA. 0+028-STA. 0+920 (RS); STA. 0+345-STA. 0+920 (LS), BRGY. DON PEDRO, MANSALAY, ORIENTAL MINDORO | Region IV-B | Region IV-B | Completed | ₱144.7M | 100% | High risk66 | —-0.052 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 17EI0190CONSTRUCTION/OPENING WITH SPOT CONCRETING OF ALL WEATHER ROAD FROM SITIO PROPER TO SITIO SINARIRI, BRGY. PANAYTAYAN, MANSALAY, ORIENTAL MINDORO | Region IV-B | Southern Mindoro DEO | Completed | ₱48.7M | 100% | Medium risk59 | Flagged0.003 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 51 | 22EI0026CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY ROSARIO, PINAMALAYAN, ORIENTAL MINDORO | Region IV-B | Southern Mindoro DEO | Completed | ₱1.9M | 100% | Low risk12 | —-0.086 |
| 52 | 20EI0146CONSTRUCTION/REHABILITATION OF MULTI-PURPOSE BUILDING, BRGY. ROMA, MANSALAY, ORIENTAL MINDORO | Region IV-B | Southern Mindoro DEO | Completed | ₱999.9K | 100% | Low risk11 | —-0.085 |
| 53 | 18EI0169COMPLETION OF SCHOOL BUILDING 2 UNIT 2 STY ICT & 2 STY SCI LAB AT BALUGO NHS, MANSALAY, ORIENTAL MINDORO | Region IV-B | Southern Mindoro DEO | Completed | ₱165.3K | 100% | Low risk10 | —-0.041 |
| 54 | 18EI0172COMPLETION OF SCHOOL BUILDING 2 UNITS ICT & 2 STY SCI LAB AT MANAUL NATIONAL HIGH SCHOOL, MANSALAY, ORIENTAL MINDORO | Region IV-B | Southern Mindoro DEO | Completed | ₱82.1K | 100% | Low risk10 | —-0.041 |