Contractor dossier
51 projects on file, including joint ventures this contractor is part of.
Total projects
51
Total budget
₱1.4B
Average progress
88.4%
Completion rate
70.6%
Average risk score
50.8
Medium risk on average, out of 100
Flagged as unusual
1
2.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region IV-A | 32 | ₱664.9M | 52.8 | 1 | 81.7% |
| National Capital Region | 13 | ₱275.8M | 47.0 | 0 | 100.0% |
| Region III | 5 | ₱371.3M | 45.1 | 0 | 98.9% |
| Central Office | 1 | ₱46.3M | 65.0 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 22 | ₱691.9M | 51.9 | 0 | 81.6% |
| Flood Control and Drainage | 20 | ₱498.7M | 47.9 | 0 | 93.0% |
| Buildings and Facilities | 7 | ₱134.5M | 46.6 | 0 | 99.5% |
| GAA 2025 SSP | 1 | ₱23.8M | 94.5 | 1 | 61.9% |
| OTHER | 1 | ₱9.6M | 70.6 | 0 | 95.4% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25DN0079CONSTRUCTION OF ROAD, BLK. 2, 3, 4, 5 AND 6, PUROK 4 LUPANG ARENDA, BARANGAY STA. ANA, TAYTAY, RIZAL (FIRST DISTRICT) | Region IV-A | Rizal 1st DEO | On-Going | ₱23.8M | 62% | High risk95 | Flagged0.005 |
| 24C00106FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BULO RIVER, BARANGAY PINAMBARAN (DOWNSTREAM), SAN MIGUEL, BULACAN | Region III | Region III | On-Going | ₱48.2M | 94% | High risk74 | —-0.027 |
| 24DN0148CONSTRUCTION OF MULTI-PURPOSE BUILDING (MULTI-PURPOSE HALL) AT BARANGAY SAN ISIDRO - KALAYAAN) ANGONO, RIZAL (FIRST DISTRICT) | Region IV-A | Rizal 1st DEO | On-Going | ₱9.6M | 96% | High risk72 | —-0.037 |
| 24DN0163CONSTRUCTION OF MULTI - PURPOSE BUILDING TAYTAY, RIZAL (FIRST DISTRICT) | Region IV-A | Rizal 1st DEO | On-Going | ₱9.6M | 95% | High risk71 | —-0.009 |
| 24DN0167CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - KULASISI - PANTAY ROAD (PHASE 3), BARANGAY SAN LUIS ANTIPOLO CITY, RIZAL (SECOND DISTRICT) | Region IV-A | Rizal 1st DEO | On-Going | ₱48M | 91% | High risk69 | —-0.040 |
| 25DN0040CONSTRUCTION OF FLOOD CONTROL STRUCTURE (PHASE 2) AT MALALIM NA SAPA 2, BINANGONAN, RIZAL (FIRST DISTRICT) | Region IV-A | Rizal 1st DEO | On-Going | ₱28.2M | 30% | High risk68 | —-0.011 |
| 25DN0045CONSTRUCTION OF FLOOD CONTROL STRUCTURE, MALALIM NA SAPA 2, BINANGONAN, RIZAL (FIRST DISTRICT) | Region IV-A | Rizal 1st DEO | On-Going | ₱28.2M | 35% | High risk68 | —-0.012 |
| 25DN0092CONSTRUCTION OF ROAD, BLK. 14, 15, 16, 17 AND 18, PUROK 4, LUPANG ARENDA, BARANGAY STA. ANA, TAYTAY, RIZAL (FIRST DISTRICT) | Region IV-A | Rizal 1st DEO | On-Going | ₱24.7M | 11% | High risk66 | —-0.022 |
| 25DN0069CONSTRUCTION OF ROAD AT ROAD 11, 12, 13, 14, 15, 16 AND 17, PUROK 3, LUPANG ARENDA, BARANGAY STA. ANA, TAYTAY, RIZAL (FIRST DISTRICT) | Region IV-A | Rizal 1st DEO | On-Going | ₱19M | 15% | High risk66 | —-0.023 |
| 25DN0094ROAD WIDENING - TERTIARY ROADS - MARIKINA - INFANTA RD - K0028+385 - K0029+000, ANTIPOLO CITY (SECOND DISTRICT) | Region IV-A | Rizal 1st DEO | On-Going | ₱42.6M | 0% | High risk66 | —-0.020 |
| 24DN0160REHABILITATION OF ROAD WITH DRAINAGE SYSTEM, KULASISI - PANTAY ROAD (PHASE 2), BARANGAY SAN LUIS ANTIPOLO CITY, RIZAL (SECOND DISTRICT) | Region IV-A | Rizal 1st DEO | On-Going | ₱11.5M | 91% | High risk66 | —-0.040 |
| 21CC0280IMPLEMENTATION OF CIVIL WORKS FOR THE CONCRETE SLOPE PROTECTION OF PLARIDEL BYPASS ACCESS ROAD NO. 2 UNDER THE ANNUAL WORK PROGRAM 3 ASSET PRESERVATION CONTRACT (APC) COMPONENT, ROAD UPGRADING AND PRESERVATION PROJECT, JICA LOAN AGREEMENT NO PH-P247, PLAR | Central Office | Roads Management Cluster I (Bilateral) | Completed | ₱46.3M | 100% | High risk65 | —-0.089 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25DN0079CONSTRUCTION OF ROAD, BLK. 2, 3, 4, 5 AND 6, PUROK 4 LUPANG ARENDA, BARANGAY STA. ANA, TAYTAY, RIZAL (FIRST DISTRICT) | Region IV-A | Rizal 1st DEO | On-Going | ₱23.8M | 62% | High risk95 | Flagged0.005 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 51 | 19DO0125LOCAL PROGRAM - LOCAL INFRASTRUCTURE PROGRAM - BUILDINGS AND OTHER STRUCTURES - MULTIPURPOSE/FACILITIES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, SAN GUILLERMO ELEMENTARY SCHOOL, BRGY. SAN GUILLERMO, MORONG, RIZAL | Region IV-A | Rizal 2nd DEO | Completed | ₱1.3M | 100% | Low risk16 | —-0.099 |