Contractor dossier
64 projects on file, including joint ventures this contractor is part of.
Total projects
64
Total budget
₱1.5B
Average progress
99.8%
Completion rate
96.9%
Average risk score
29.7
Low risk on average, out of 100
Flagged as unusual
1
1.6% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region III | 64 | ₱1.5B | 29.7 | 1 | 99.8% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 31 | ₱757.4M | 30.9 | 1 | 99.6% |
| Buildings and Facilities | 16 | ₱91.5M | 24.0 | 0 | 100.0% |
| Flood Control and Drainage | 14 | ₱520.7M | 29.2 | 0 | 100.0% |
| Bridges | 2 | ₱54.8M | 42.6 | 0 | 100.0% |
| OTHER | 1 | ₱43.5M | 63.8 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 20CE0178CONCRETING OF TALUGTUG - LUPAO ROAD VIA MAASIN, TALUGTUG AND LUPAO, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | Completed | ₱23.8M | 100% | High risk65 | —-0.068 |
| 19CF0042CONCRETING OF ROAD WITH SLOPE PROTECTION, TABON -STO. CRISTO NORTE ROAD, PHASE I, SAN ISIDRO, NUEVA ECIJA | Region III | Nueva Ecija 2nd DEO | Completed | ₱43.5M | 100% | High risk64 | —-0.039 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24CE0312CONCRETING OF BRGY. NAGMISAHAN, CUYAPO TO BRGY. CABAWANGAN, CUYAPO TO BRGY. CABADUCAN EAST, NAMPICUAN FMR, BRGY. NAGMISAHAN, CUYAPO, BRGY. CABAWANGAN, CUYAPO AND BRGY. CABADUCAN EAST, NAMPICUAN, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | On-Going | ₱49.3M | 87% | Medium risk39 | Flagged0.003 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 20CE0178CONCRETING OF TALUGTUG - LUPAO ROAD VIA MAASIN, TALUGTUG AND LUPAO, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | Completed | ₱23.8M | 100% | High risk65 | —-0.068 |
| 2 | 19CF0042CONCRETING OF ROAD WITH SLOPE PROTECTION, TABON -STO. CRISTO NORTE ROAD, PHASE I, SAN ISIDRO, NUEVA ECIJA | Region III | Nueva Ecija 2nd DEO | Completed | ₱43.5M | 100% | High risk64 | —-0.039 |
| 3 | 20CE0171RETROFITTING/STRENGTHENING OF PERMANENT BRIDGES - CAPINTALAN BR. 1 (B01982LZ) ALONG DAANG MAHARLIKA (LZ) | Region III | Nueva Ecija 1st DEO | Completed | ₱23.4M | 100% | Medium risk53 | —-0.027 |
| 4 | 24CF0101BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF PEÑARANDA - MAKABAKLAY ROAD, PEÑARANDA, NUEVA ECIJA (PHASE I) | Region III | Nueva Ecija 2nd DEO | Completed | ₱95M | 100% | Medium risk51 | —-0.092 |
| 5 | 17CE0248CONSTRUCTION OF 2 CLASSROOMS WORKSHOP BUILDING, MUÑOZ NATIONAL HIGH SCHOOL (ANNEX), SCIENCE CITY OF MUÑOZ NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | Completed | ₱9M | 100% | Medium risk45 | —-0.026 |
| 6 | 17CE0249CONSTRUCTION OF 2 CLASSROOMS WORKSHOP BUILDING, MUÑOZ NATIONAL HIGH SCHOOL (ANNEX), SCIENCE CITY OF MUÑOZ NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | Completed | ₱9M | 100% | Medium risk45 | —-0.026 |
| 7 | 23CC0152NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - BALAGTAS DIVERSION ROAD (PHASE 5), BULACAN, BALAGTAS, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱72.4M | 100% | Medium risk41 | —-0.099 |
| 8 | 24CE0312CONCRETING OF BRGY. NAGMISAHAN, CUYAPO TO BRGY. CABAWANGAN, CUYAPO TO BRGY. CABADUCAN EAST, NAMPICUAN FMR, BRGY. NAGMISAHAN, CUYAPO, BRGY. CABAWANGAN, CUYAPO AND BRGY. CABADUCAN EAST, NAMPICUAN, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | On-Going | ₱49.3M | 87% | Medium risk39 | Flagged0.003 |
| 9 | 22CE0061ASSET PRESERVATION - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - TERTIARY ROADS - GUIMBA - TALUGTUG - UMINGAN RD CHAINAGE 10983 - CHAINAGE 12946 | Region III | Nueva Ecija 1st DEO | Completed | ₱61.5M | 100% | Medium risk39 | —-0.098 |
| 10 | 23CF0085CONSTRUCTION (CONCRETING) OF SOLEDAD - LAS PIÑAS NIA ACCESS ROAD, STA. ROSA AND PEÑARANDA (PHASE II) | Region III | Nueva Ecija 2nd DEO | Completed | ₱88.2M | 100% | Medium risk38 | —-0.093 |
| 11 | 21CE0103NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, GUIMBA-TALUGTUG-UMINGAN ROAD, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | Completed | ₱48.1M | 100% | Medium risk36 | —-0.099 |
| 12 | 19CF0061CONSTRUCTION OF SLOPE PROTECTION STRUCTURE - CONSTRUCTION/MAINTENANCE OF PAMPANGA RIVER FLOOD CONTROL, EARTH DIKE AND CONCRETE SLOPE PROTECTION, BRGY. SAN JOSEF SUR, CABANATUAN CITY, NUEVA ECIJA | Region III | Nueva Ecija 2nd DEO | Completed | ₱74.9M | 100% | Medium risk36 | —-0.088 |
| 13 | 18CF0092NETWORK DEVELOPMENT - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS FELIPE VERGARA BY PASS ROAD, NUEVA ECIJA | Region III | Nueva Ecija 2nd DEO | Completed | ₱48.8M | 100% | Medium risk36 | —-0.103 |
| 14 | 17CE0090ASSET PRESERVATION OF NATIONAL ROADS, REHABILITATION/RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - TERTIARY: REHABILITATION/MAJOR REPAIR OF ROAD SLOPE PROTECTION STRUCTURE, JCT. PINAGPANAAN-RIZAL-PANTABANGAN RD. KO160+357.40 | Region III | Nueva Ecija 1st DEO | Completed | ₱2.1M | 100% | Medium risk35 | —-0.064 |
| 15 | 18CF0097REHABILITATION/IMPROVEMENT OF PAMPANGA RIVER CONTROL, BRGY. SAPANG BUHO, PALAYAN CITY | Region III | Nueva Ecija 2nd DEO | Completed | ₱48M | 100% | Medium risk35 | —-0.091 |
| 16 | 18CF0096FLOOD CONTROL STRUCTURES/FACILITIES, CONSTRUCTION/MAINTENANCE OF PAMPANGA RIVER CONTROL, BRGY. POPOLON, PALAYAN CITY | Region III | Nueva Ecija 2nd DEO | Completed | ₱48M | 100% | Medium risk35 | —-0.091 |
| 17 | 18CF0053CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF SLOPE PROTECTION ALONG DIGMALA RIVER CONTROL, ARIENDO SECTION, BONGABON, NUEVA ECIJA | Region III | Nueva Ecija 2nd DEO | Completed | ₱48.9M | 100% | Medium risk34 | —-0.090 |
| 18 | 20CF0097CONSTRUCTION OF MULTI-PURPOSE BUILDING, NEUST-GENERAL TINIO (PAPAYA) OFF CAMPUS, BARANGAY CONCEPCION, GENERAL TINIO, NUEVA ECIJA | Region III | Nueva Ecija 2nd DEO | Completed | ₱7.4M | 100% | Medium risk34 | —-0.106 |
| 19 | 24CE0303ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - TERTIARY ROADS - GUIMBA - TALUGTUG - UMINGAN RD - K0165+352 - K0165+798, K0166+047 - K0167+280 | Region III | Nueva Ecija 1st DEO | Completed | ₱45.4M | 100% | Medium risk34 | —-0.100 |
| 20 | 20CF0111CONSTRUCTION OF HOMOGENEOUS CLOSING EARTH LEVEE (EARTH DIKE ALONG PAMPANGA RIVER) FROM BRGY. PAGAS TO BRGY. SAN JOSEF NORTE, CABANATUAN CITY, NUEVA ECIJA | Region III | Nueva Ecija 2nd DEO | Completed | ₱48.9M | 100% | Medium risk33 | —-0.092 |
| 21 | 24CE0085CONSTRUCTION OF MULTI PURPOSE BUILDING BRGY. AGLIPAY, RIZAL, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | Completed | ₱4.9M | 100% | Medium risk33 | —-0.104 |
| 22 | 18CF0093CONSTRUCTION OF SLOPE PROTECTION ALONG PAMPANGA RIVER FLOOD CONTROL, STA. ROSA, NUEVA ECIJA | Region III | Nueva Ecija 2nd DEO | Completed | ₱48.7M | 100% | Medium risk33 | —-0.090 |
| 23 | 24CE0291CONCRETING OF BRGY. POBLACION SUR TO BRGY. CABUCBUCAN FMR, BRGY. POBLACION SUR, RIZAL, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | Completed | ₱14.8M | 100% | Medium risk33 | —-0.043 |
| 24 | 24CE0137REHABILITATION OF ROAD, CLSU ROAD NETWORK, CLSU COMPOUND, SCIENCE CITY OF MUÑOZ, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | Completed | ₱19.6M | 100% | Medium risk32 | —-0.104 |
| 25 | 18CF0153LOCAL ROADS AND BRIDGES- LOCAL ROADS - CONCRETING OF AULO JUNCTION TO AULO DAM ECO-TOURISM AREA AND ESTATE, PALAYAN CITY, NUEVA ECIJA | Region III | Nueva Ecija 2nd DEO | Completed | ₱25.9M | 100% | Medium risk32 | —-0.104 |