Contractor dossier
136 projects on file, including joint ventures this contractor is part of.
Total projects
136
Total budget
₱5.2B
Average progress
95.3%
Completion rate
86.8%
Average risk score
48.2
Medium risk on average, out of 100
Flagged as unusual
1
0.7% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| National Capital Region | 129 | ₱5B | 48.4 | 1 | 95.0% |
| Region IV-A | 6 | ₱171.2M | 47.3 | 0 | 100.0% |
| Region III | 1 | ₱86.8M | 36.9 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Flood Control and Drainage | 81 | ₱3.9B | 49.7 | 0 | 97.1% |
| Buildings and Facilities | 30 | ₱780.2M | 45.3 | 0 | 97.1% |
| Roads | 20 | ₱393.8M | 41.0 | 0 | 90.0% |
| GAA 2025 OO-2 | 2 | ₱69.4M | 80.6 | 0 | 92.5% |
| OTHER | 2 | ₱28.3M | 51.6 | 0 | 100.0% |
| GAA 2025 SSP | 1 | ₱5.8M | 91.0 | 1 | 0.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25OG0104REHABILITATION OF ROAD, BARANGAY DIOQUINO ZOBEL, PACKAGE 2, QUEZON CITY | National Capital Region | Quezon City 2nd DEO | On-Going | ₱5.8M | 0% | High risk91 | Flagged0.027 |
| 25OB0096CONSTRUCTION (COMPLETION) OF FLOOD CONTROL STRUCTURE ALONG ERMITAÑO CREEK, BARANGAY ADDITION HILLS, SAN JUAN CITY | National Capital Region | Metro Manila 1st DEO | On-Going | ₱21.9M | 85% | High risk81 | —-0.019 |
| 25OB0260REHABILITATION OF HAKBANGAN CREEK, PASIG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱47.5M | 100% | High risk80 | —-0.055 |
| 25OE0060CONSTRUCTION OF RETARDING BASIN AT ESTERO DE KABULUSAN, PHASE II, TONDO, MANILA CITY | National Capital Region | North Manila DEO | On-Going | ₱142.1M | 40% | High risk67 | —-0.024 |
| 24OE0015CONSTRUCTION OF RETARDING BASIN AT ESTERO DE MAYPAJO (PHASE III), TONDO, MANILA CITY | National Capital Region | North Manila DEO | On-Going | ₱144.7M | 100% | High risk67 | —-0.032 |
| 24OB0185CONSTRUCTION OF SLOPE PROTECTION ALONG TAGUIG RIVER LAKESHORE AREA (PHASE 1), TAGUIG CITY | National Capital Region | Metro Manila 1st DEO | On-Going | ₱94.6M | 100% | High risk65 | —-0.044 |
| 24OB0214CONSTRUCTION OF SLOPE PROTECTION ALONG PINAGSAMA RIVER, TAGUIG CITY (PHASE 2) | National Capital Region | Metro Manila 1st DEO | Completed | ₱125.8M | 100% | High risk65 | —-0.069 |
| 25OB0257CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG LABASAN RIVER (WEST BANK), PHASE 2, PACKAGE 7, TAGUIG CITY | National Capital Region | Metro Manila 1st DEO | On-Going | ₱93.6M | 100% | High risk65 | —-0.052 |
| 24OB0182CONSTRUCTION OF SLOPE PROTECTION ALONG TAGUIG RIVER (PHASE 1), TAGUIG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱94.6M | 100% | High risk64 | —-0.077 |
| 22OB0104CONSTRUCTION OF SLOPE PROTECTION ALONG TAGUIG RIVER, FACING DOWNSTREAM (WEST BANK), PACKAGE 3, TAGUIG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱96.5M | 100% | High risk63 | —-0.077 |
| 22OG0135IMPROVEMENT OF SAN JUAN RIVER (PHASE XIII), QUEZON CITY | National Capital Region | Quezon City 2nd DEO | Completed | ₱92.6M | 100% | High risk62 | —-0.075 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25OG0104REHABILITATION OF ROAD, BARANGAY DIOQUINO ZOBEL, PACKAGE 2, QUEZON CITY | National Capital Region | Quezon City 2nd DEO | On-Going | ₱5.8M | 0% | High risk91 | Flagged0.027 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 51 | 22OE0090BANK IMPROVEMENT (STEEL SHEET PILE) ALONG ESTERO DE KABULUSAN, BARANGAY 154 AND BARANGAY 157, TONDO, MANILA CITY | National Capital Region | North Manila DEO | Completed | ₱49M | 100% | Medium risk49 | —-0.088 |
| 52 | 18OB0390INSTALLATION OF FLOODGATES ALONG SAN JUAN RIVER, SAN JUAN CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱4.8M | 100% | Medium risk49 | —-0.044 |
| 53 | 17OB0121REHABILITATION OF SLOPE PROTECTION OF ILUGIN CREEK, PASIG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱36.9M | 100% | Medium risk49 | —-0.063 |
| 54 | 22OB0155BANK IMPROVEMENT/PROTECTION ALONG PANDAY RIVER (WEST BANK), TAGUIG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱49M | 100% | Medium risk49 | —-0.088 |
| 55 | 20OB0347CONSTRUCTION OF SPED FACILITIES, BRGY. CALZADA, TIPAS, TAGUIG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱19M | 100% | Medium risk48 | —-0.101 |
| 56 | 20OB0337CONSTRUCTION OF MULTI-PURPOSE BUILDING AND SITE DEVELOPMENT, BRGY. WAWA, TAGUIG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱19.2M | 100% | Medium risk48 | —-0.101 |
| 57 | 17OB0343REHABILITATION/IMPROVEMENT OF DRAINAGE SYSTEM ALONG VELOSO, DIWA AND ASIÑAS STS., BRGY. SALAPAN, SAN JUAN CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱18.6M | 100% | Medium risk48 | —-0.063 |
| 58 | 17OB0015COMPLETION OF SLOPE PROTECTION ALONG PATEROS RIVER, BRGY. AGUHO, PATEROS-TAGUIG CITY, 1ST LD | National Capital Region | Metro Manila 1st DEO | Completed | ₱19M | 100% | Medium risk48 | —-0.063 |
| 59 | 17OB0096CONSTRUCTION OF M. ALMEDA AND VICINITY DRAINAGE OUTFALL, BRGY. STO. ROSARIO SILANGAN, PATEROS, TAGUIG-PATEROS 1ST LD | National Capital Region | Metro Manila 1st DEO | Completed | ₱14M | 100% | Medium risk48 | —-0.064 |
| 60 | 23OB0321CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. SAN ROQUE, TAGUIG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱9.5M | 100% | Medium risk48 | —-0.098 |
| 61 | 20OB0321CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BRGY. AGUHO, PATEROS | National Capital Region | Metro Manila 1st DEO | Completed | ₱9.5M | 100% | Medium risk48 | —-0.103 |
| 62 | 25OB0375REHABILITATION OF MULTI-PURPOSE BUILDING, CORONADO STREET, BARANGAY HULO, MANDALUYONG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱4.9M | 100% | Medium risk48 | —-0.102 |
| 63 | 25OB0066ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - TERTIARY ROADS - LOPEZ-JAENA - K0015 + (-266) - K0015 + 962 | National Capital Region | Metro Manila 1st DEO | On-Going | ₱46.5M | 0% | Medium risk47 | —-0.037 |
| 64 | 17OB0094IMPROVEMENT OF CREEK BED, MAHABANG ILOG CREEK, BRGY. MAYBUNGA AND BRGY. SAN MIGUEL, PASIG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱17.6M | 100% | Medium risk47 | —-0.064 |
| 65 | 20OB0382REHABILITATION OF ROADS, BARANGAY NORTH DAANGHARI, TAGUIG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱32.6M | 100% | Medium risk47 | —-0.096 |
| 66 | 17OB0129REHABILITATION OF MANGGAHAN FLOODWAY DRAINAGE OUTFALL ALONG EAST BANK ROAD, PASIG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱13.9M | 100% | Medium risk47 | —-0.064 |
| 67 | 22OB0021PREVENTIVE MAINTENANCE ALONG GEN KALENTONG-BLUMENTRITT-JOLO RD - K0008 + 259 - K0008 + 955, K0008 + 482 - K0011 + 602 | National Capital Region | Metro Manila 1st DEO | Completed | ₱36.6M | 100% | Medium risk47 | —-0.098 |
| 68 | 23DO0063ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - SECONDARY ROADS - MANILA EAST RD - K0047+305 - K0048+300 | Region IV-A | Rizal 2nd DEO | Completed | ₱39.5M | 100% | Medium risk47 | —-0.106 |
| 69 | 17OB0089CONSTRUCTION OF J. P. RIZAL DRAINAGE OUTFALL INCLUDING LATERALS, BRGY. STO. NIÑO, MARIKINA CITY 1ST LD | National Capital Region | Metro Manila 1st DEO | Completed | ₱18.5M | 100% | Medium risk47 | —-0.057 |
| 70 | 17OB0287CONSTRUCTION OF SLOPE PROTECTION ALONG CHAMPACA CREEK, BRGY. FORTUNE, MARIKINA CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱9.3M | 100% | Medium risk47 | —-0.065 |
| 71 | 17OB0102REHABILITATION AND DESILTING OF BULI CREEK BARANGAY STA. LUCIA, PASIG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱9.2M | 100% | Medium risk47 | —-0.065 |
| 72 | 17OB0101REHABILITATION OF SLOPE PROTECTION OF SAPANG MALAPIT CREEK, PASIG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱9.2M | 100% | Medium risk47 | —-0.065 |
| 73 | 24DO0050CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) - BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDING/FACILITIES - REHABILITATION OF ROAD, BARANGAY SAN ISIDRO, RODRIGUEZ, RIZA | Region IV-A | Rizal 2nd DEO | On-Going | ₱28.5M | 100% | Medium risk47 | —-0.066 |
| 74 | 18DO0101ORGANIZATIONAL OUTCOME 2:PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG UPPER MARIKINA RIVER, SAN MATEO | Region IV-A | Rizal 2nd DEO | Completed | ₱28.2M | 100% | Medium risk47 | —-0.080 |
| 75 | 18OB0463CONSTRUCTION OF FOUR (4) STOREY, EIGHT (8) CLASSROOM, STO. ROSARIO ELEMENTARY SCHOOL, PATEROS, MANILA | National Capital Region | Metro Manila 1st DEO | Completed | ₱31.8M | 100% | Medium risk47 | —-0.044 |