125 projects on file, including joint ventures this contractor is part of.
Total projects
125
Total budget
₱1.9B
Average progress
100.0%
Completion rate
99.2%
Average risk score
19.8
Low risk on average, out of 100
Flagged as unusual
3
2.4% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region XII | 107 | ₱1.6B | 16.4 | 3 | 100.0% |
| Region VI | 16 | ₱297.6M | 43.4 | 0 | 100.0% |
| Region X | 2 | ₱3.8M | 8.7 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 74 | ₱463.7M | 11.1 | 3 | 100.0% |
| Roads | 39 | ₱1.3B | 32.8 | 0 | 100.0% |
| Bridges | 7 | ₱73.5M | 22.4 | 0 | 100.0% |
| Flood Control and Drainage | 3 | ₱57.4M | 31.0 | 0 | 100.0% |
| OTHER | 1 | ₱19.3M | 74.1 | 0 | 100.0% |
| Water Provision and Storage | 1 | ₱9.7M | 45.8 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24MF0037TACURONG EAST BY-PASS ROAD FROM BRGY. SAN ANTONIO-D'LEDESMA-SAN PABLO CONNECTING TO BRGY. KALANDAGAN BARANGAY ROAD IN SUPPORT OF BANANA AND PALM OIL INDUSTRIES, TACURONG CITY, SULTAN KUDARAT | Region XII | Sultan Kudarat 1st DEO | Completed | ₱19.3M | 100% | High risk74 | —-0.034 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 16MG0126CONSTRUCTION OF 2UNITS - 1STY 3CL AT BLIT ES, LAKE SEBU, SOUTH COTABATO | Region XII | South Cotabato 2nd DEO | Completed | ₱6.6M | 100% | Low risk16 | Flagged0.001 |
| 16MG0137CONSTRUCTION OF 1UNIT- 1STY 3CL AT T'BOYUNG ES, LAKE SEBU, SOUTH COTABATO | Region XII | South Cotabato 2nd DEO | Completed | ₱3.2M | 100% | Low risk3 | Flagged0.001 |
| 16MG0133CONSTRUCTION OF 2 UNITS-1STY 2CL AT PULO SUBONG INTEGRATED HS, LAKE SEBU, SOUTH COTABATO | Region XII | South Cotabato 2nd DEO | Completed | ₱4.5M | 100% | Low risk3 | Flagged0.000 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 76 | 19KB0064CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HALL), BRGY PANGANAN, KITAOTAO, BUKIDNON | Region X | Bukidnon 2nd DEO | Completed | ₱1.9M | 100% | Low risk9 | —-0.092 |
| 77 | 19KB0076CONSTRUCTION OF MULTI-PURPOSE BUILDING (WAREHOUSE WITH SOLAR DRIER), BRGY TANGKULAN, DAMULOG, BUKIDNON | Region X | Bukidnon 2nd DEO | Completed | ₱1.9M | 100% | Low risk9 | —-0.093 |
| 78 | 18MF0011CONSTRUCTION OF BARANGAY HALL AT BRGY. CARIDAD, LAMBAYONG, SULTAN KUDARAT. | Region XII | Sultan Kudarat 1st DEO | Completed | ₱2.6M | 100% | Low risk8 | —-0.087 |
| 79 | 18MF0010CONSTRUCTION OF BARANGAY HALL AT BRGY. PINGUIAMAN, LAMBAYONG, SULTAN KUDARAT. | Region XII | Sultan Kudarat 1st DEO | Completed | ₱2.6M | 100% | Low risk8 | —-0.088 |
| 80 | 18MF0020CONSTRUCTION OF BARANGAY HALL AT BRGY. ESTRELLA, PRES. QUIRINO, SULTAN KUDARAT. | Region XII | Sultan Kudarat 1st DEO | Completed | ₱2.6M | 100% | Low risk7 | —-0.086 |
| 81 | 18MF0017CONSTRUCTION OF BARANGAY HALL AT BRGY. BAUMOL, LAMBAYONG, SULTAN KUDARAT. | Region XII | Sultan Kudarat 1st DEO | Completed | ₱2.6M | 100% | Low risk7 | —-0.087 |
| 82 | 19MF0015CONST. OF MULTI-PURPOSE BUILDING (NEW BRGY. HALL) AT SAN PABLO, TACURONG CITY, SULTAN KUDARAT | Region XII | Sultan Kudarat 1st DEO | Completed | ₱2.9M | 100% | Low risk7 | —-0.086 |
| 83 | 19MF0019CONST. OF MULTI-PURPOSE BUILDING (NEW BRGY. HALL) AT BRGY. NEW LAGAO, TACURONG CITY, SULTAN KUDARAT | Region XII | Sultan Kudarat 1st DEO | Completed | ₱2.9M | 100% | Low risk7 | —-0.086 |
| 84 | 18MF0012CONSTRUCTION OF BARANGAY HALL AT BRGY. KENRAM, ISULAN, SULTAN KUDARAT. | Region XII | Sultan Kudarat 1st DEO | Completed | ₱2.6M | 100% | Low risk7 | —-0.086 |
| 85 | 19MF0027CONSTRUCTION OF MULTI - PURPOSE BUILDING (MINI GYM), AT BRGY. CARIDAD, LAMBAYONG, SULTAN KUDARAT. | Region XII | Sultan Kudarat 1st DEO | Completed | ₱2.2M | 100% | Low risk7 | —-0.086 |
| 86 | 18MF0022CONSTRUCTION OF BARANGAY HALL AT BRGY. SUCOB, COLUMBIO, SULTAN KUDARAT. | Region XII | Sultan Kudarat 1st DEO | Completed | ₱2.6M | 100% | Low risk7 | —-0.085 |
| 87 | 20MF0040CONSTRUCTION OF MULTI - PURPOSE BUILDING AT BRGY. NEW PASSI, TACURONG CITY, SULTAN KUDARAT | Region XII | Sultan Kudarat 1st DEO | Completed | ₱3M | 100% | Low risk7 | —-0.088 |
| 88 | 18MF0018CONSTRUCTION OF BARANGAY HALL AT BRGY. BANTANGAN, COLUMBIO, SULTAN KUDARAT. | Region XII | Sultan Kudarat 1st DEO | Completed | ₱2.6M | 100% | Low risk7 | —-0.084 |
| 89 | 19MF0016CONST. OF MULTI-PURPOSE BUILDING (NEW BRGY. HALL) AT BRGY. EDAY, COLOMBIO, SULTAN KUDARAT | Region XII | Sultan Kudarat 1st DEO | Completed | ₱2.9M | 100% | Low risk7 | —-0.084 |
| 90 | 20MF0046CONSTRUCTION OF MULTI - PURPOSE BUILDING AT BRGY. TANANZANG, LUTAYAN, SULTAN KUDARAT | Region XII | Sultan Kudarat 1st DEO | Completed | ₱2.9M | 100% | Low risk6 | —-0.084 |
| 91 | 19MF0014CONST. OF MULTI-PURPOSE BUILDING (NEW BRGY. HALL) AT BRGY. BAYASONG, LUTAYAN, SULTAN KUDARAT | Region XII | Sultan Kudarat 1st DEO | Completed | ₱2.9M | 100% | Low risk6 | —-0.085 |
| 92 | 20MF0042CONSTRUCTION OF MULTI - PURPOSE BUILDING AT BRGY. PUNOL, LUTAYAN, SULTAN KUDARAT | Region XII | Sultan Kudarat 1st DEO | Completed | ₱2.9M | 100% | Low risk6 | —-0.087 |
| 93 | 18MF0001CONST. OF MINI GYM @ AS BERNARDO NHS, BRGY. BARAS | Region XII | Sultan Kudarat 1st DEO | Completed | ₱2.2M | 100% | Low risk5 | —-0.087 |
| 94 | 18MF0007CONSTRUCTION OF MINI GYM @ PUROK MANGUDADATU, LUTAYAN PROPER | Region XII | Sultan Kudarat 1st DEO | Completed | ₱2.2M | 100% | Low risk5 | —-0.087 |
| 95 | 20MF0038CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BRGY. LUTAYAN PROPER, LUTAYAN, SULTAN KUDARAT | Region XII | Sultan Kudarat 1st DEO | Completed | ₱2.5M | 100% | Low risk5 | —-0.086 |
| 96 | 20MF0075CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BRGY. LUTAYAN PROPER, LUTAYAN, SULTAN KUDARAT | Region XII | Sultan Kudarat 1st DEO | Completed | ₱2.5M | 100% | Low risk5 | —-0.086 |
| 97 | 18MF0008CONSTRUCTION OF MINI GYM @ BRGY. MAMALI | Region XII | Sultan Kudarat 1st DEO | Completed | ₱2.2M | 100% | Low risk5 | —-0.087 |
| 98 | 18MF0004CONSTRUCTION OF MINI GYM @ DIONESIO LOTILLA E/S | Region XII | Sultan Kudarat 1st DEO | Completed | ₱998.5K | 100% | Low risk5 | —-0.086 |
| 99 | 18MF0006CONSTRUCTION OF MINI GYM @ KAMANGA E/S, BRGY. LAGUILAYAN | Region XII | Sultan Kudarat 1st DEO | Completed | ₱997.5K | 100% | Low risk4 | —-0.087 |
| 100 | 18MF0077CONST. OF 1-STY 2-CLASSROOMS SCHOOL BUILDING AT SUMAPAL E/S, LUTAYAN, SULTAN KUDARAT. | Region XII | Sultan Kudarat 1st DEO | Completed | ₱2.8M | 100% | Low risk4 | —-0.042 |