Contractor dossier
115 projects on file, including joint ventures this contractor is part of.
Total projects
115
Total budget
₱4B
Average progress
99.0%
Completion rate
92.2%
Average risk score
46.3
Medium risk on average, out of 100
Flagged as unusual
2
1.7% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region II | 115 | ₱4B | 46.3 | 2 | 99.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Flood Control and Drainage | 46 | ₱2.4B | 49.5 | 0 | 99.3% |
| Roads | 40 | ₱1.1B | 45.8 | 0 | 99.8% |
| Buildings and Facilities | 25 | ₱188M | 34.8 | 0 | 99.6% |
| GAA 2025 OO-2 | 2 | ₱192.9M | 94.2 | 1 | 90.5% |
| GAA 2025 OO-1 | 1 | ₱38M | 92.9 | 1 | 57.5% |
| Bridges, Roads | 1 | ₱108.6M | 61.1 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25BF0032OO2: FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS CONSTRUCTION OF MALLIG RIVER FLOOD CONTROL PROJECT, (SANTIAGO SECTION PHASE 2), BARANGAY SANTIAGO, QUIRINO, ISABELA | Region II | Isabela 2nd DEO | On-Going | ₱96.4M | 91% | High risk94 | Flagged0.000 |
| 25BG0020OO2:PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL PROJECT ALONG GANANO RIVER, BARANGAY DAGUPAN, ALICIA, ISABELA | Region II | Isabela 3rd DEO | On-Going | ₱96.4M | 90% | High risk94 | —-0.003 |
| 25BF0086ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - ROXAS BYPASS ROAD, ISABELA, ROXAS, ISABELA | Region II | Isabela 2nd DEO | On-Going | ₱38M | 57% | High risk93 | Flagged0.006 |
| 17BF0026NETWORK DEVELOPMENT-IMPROVEMENT/WIDENING OF NATIONAL ROADS PRIMARY ROADS-OTHER PRIMARY ROADS ALONG SANTIAGO-TUGUEGARAO ROAD (S00760LZ), K0405-000-K0407+000, QUEZON, ISABELA | Region II | Isabela 2nd DEO | Completed | ₱54.9M | 100% | High risk67 | —-0.048 |
| 17BG0043MFO 2: FLOOD MANAGEMENT SERVICES - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CAGAYAN RIVER FLOOD CONTROL PROJECT, CENTRO, ANGADANAN SECTION, ISABELA, CENTRO II, ANGADANAN, ISABEL | Region II | Isabela 3rd DEO | Completed | ₱19.1M | 100% | High risk67 | —-0.044 |
| 17BF0025CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS: CONSTRUCTION OF SIFFU RIVER FLOOD CONTROL PROJECT (BRGY. ANAO SECTION), STA.0+000-STA.0+600, ROXAS, ISABELA, BRGY. ANAO, ROXAS, ISABELA | Region II | Isabela 2nd DEO | Completed | ₱18.6M | 100% | High risk67 | —-0.023 |
| 17BG0023ASSET PRESERVATION OF NATIONAL ROADS - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED NATIONAL ROADS BASED ON PAVEMENT MANAGEMENT SYSTEM/HIGHWAY DEVELOPMENT MANAGEMENT-4 (HDM-4) - PRIMARY - SANTIAGO-TUGUEGARAO RD. K0356+611 - K0357+000, DIAMANTI | Region II | Isabela 3rd DEO | Completed | ₱5.1M | 100% | High risk66 | —-0.056 |
| 17BF0008REPAIR/REHABILITATION/CONCRETING OF ROAD, BRGY. GANGALAN-BRGY. DEL PILAR, SAN MARIANO, ISABELA 2ND LD, SAN MARIANO, ISABELA | Region II | Isabela 2nd DEO | Completed | ₱9.4M | 100% | High risk65 | —-0.053 |
| 17BF0054ROAD CONCRETING, BRGY. CABARUAN TO QUINALABASA, CABARUAN, NAGUILIAN, ISABELA, CABARUAN, NAGUILIAN, ISABELA | Region II | Isabela 2nd DEO | Completed | ₱9.4M | 100% | High risk65 | —-0.056 |
| 15BF0160NETWORK DEV'T: OFF-CARRIAGEWAY IMPV'T(PAVING/SEALING OF SHOULDER) INCLUDING RD. SLOPE PROTECTION & D | Region II | Isabela 2nd DEO | Completed | ₱31.2M | 100% | High risk65 | —-0.036 |
| 16BF0123NETWORK DEVELOPMENT: OFF-CARRIAGEWAY IMPROVEMENT INCLUDING DRAINAGE-TERTIARY ALONG ILAGAN-DELFIN ALBANO-MALLIG ROAD, K0443+742-K0443+863, K0443+892-K0445+009, K0445+045-K0446+300, MALLIG, ISABELA | Region II | Isabela 2nd DEO | Completed | ₱45.4M | 100% | High risk65 | —-0.051 |
| 25BG0161OO2:PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM- CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES W/N MAJOR RIVER BASINS AND PRINCIPAL RIVERS-CONSTRUCTION OF CAGAYAN RIVER FLOOD CONTROL STRUCTURE, BARANGAY MINANGA | Region II | Isabela 3rd DEO | On-Going | ₱93.6M | 100% | High risk63 | —-0.034 |
| 25BF0041OO2: FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS -CONSTRUCTION OF MALLIG RIVER FLOOD CONTROL PROJECT, (VILLA MIGUEL DOWNSTREAM SECTION), BARANGAY VILLA MIGUEL, QUIRINO, ISABELA | Region II | Isabela 2nd DEO | On-Going | ₱96.4M | 88% | High risk62 | —-0.025 |
| 25BF0037OO2: FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF SIFFU RIVER FLOOD CONTROL PROJECT, (RIZAL SECTION PHASE II) QUIRINO, ISABELA | Region II | Isabela 2nd DEO | On-Going | ₱96.4M | 98% | High risk62 | —-0.030 |
| 24BG0008OO2:PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS-CONSTRUCTION OF CAGAYAN RIVER FLOOD CONTROL PROJECT, BRGY. MAGSAYSAY, | Region II | Isabela 3rd DEO | Completed | ₱96.4M | 100% | High risk62 | —-0.053 |
| 24BG0060OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS- CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES W/N MAJOR RIVER BASINS & PRINCIPAL RIVERS-CONSTRUCTION OF CAGAYAN RIVER FLOOD CONTROL PROJ, BRGY MALALATANG GRANDE(STA0+000-STA0+468.30) | Region II | Isabela 3rd DEO | Completed | ₱96.4M | 100% | High risk62 | —-0.050 |
| 24BG0043OO2:PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS-CONSTRUCTION OF MAGAT RIVER FLOOD CONTROL, BRGY. MALLALATANG GRANDE, R | Region II | Isabela 3rd DEO | Completed | ₱96.4M | 100% | High risk62 | —-0.052 |
| 25BG0094OO2:PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM- CONSTRUCTION/REHAB OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS & PRINCIPAL RIVERS- CONSTRUCTION OF CAGAYAN RIVER FLOOD CONTROL STRUCTURE, BRGY. DISTRICT 2, PHASE3 | Region II | Isabela 3rd DEO | Completed | ₱96.4M | 100% | High risk62 | —-0.052 |
| 24BF0045ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF MALLIG RIVER FLOOD CO | Region II | Isabela 2nd DEO | Completed | ₱96.5M | 100% | High risk62 | —-0.052 |
| 19BF0102NETWORK DEVELOPMENT CONSTRUCTION OF BY-PASS AND DIVERSION ROADS ROXAS BYPASS ROAD, ISABELA, ROXAS, ISABELA | Region II | Isabela 2nd DEO | Completed | ₱108.6M | 100% | High risk61 | —-0.048 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25BF0086ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - ROXAS BYPASS ROAD, ISABELA, ROXAS, ISABELA | Region II | Isabela 2nd DEO | On-Going | ₱38M | 57% | High risk93 | Flagged0.006 |
| 25BF0032OO2: FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS CONSTRUCTION OF MALLIG RIVER FLOOD CONTROL PROJECT, (SANTIAGO SECTION PHASE 2), BARANGAY SANTIAGO, QUIRINO, ISABELA | Region II | Isabela 2nd DEO | On-Going | ₱96.4M | 91% | High risk94 | Flagged0.000 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 51 | 21B00017ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - PRIMARY ROADS - DAANG MAHARLIKA (LZ) | Region II | Region II | Completed | ₱39.8M | 100% | Medium risk45 | —-0.082 |
| 52 | 23BG0145OO1:ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - PRIMARY ROADS - DAANG MAHARLIKA (LZ) - K0374 + 185 - K0374 + 841 | Region II | Isabela 3rd DEO | Completed | ₱32.7M | 100% | Medium risk45 | —-0.083 |
| 53 | 20B00019ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT: CONSTRUCTION OF BYPASS ROADS AND DIVERSION ROADS-GUIBANG-GAMU BYPASS ROAD, ISABELA; STA. 000+000-STA. 001+239.62 | Region II | Region II | Completed | ₱41.1M | 100% | Medium risk45 | —-0.079 |
| 54 | 19BF0061ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT - CONSTRUCTION OF MISSING LINKS/NEW ROADS - NAGUILIAN (JCT. CVR) - PALANAN ROAD, ISABELA, SAN MARIANO, ISABELA | Region II | Isabela 2nd DEO | Completed | ₱41.9M | 100% | Medium risk44 | —-0.081 |
| 55 | 23BH0062CONVERGENCE AND SPECIAL SUPPORT PROGRAM-CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES (ROADS LEVERAGING LINKAGES FOR INDUSTRIES AND TRADE INFRASTRUCTURE PROGRAM - ROLL IT)-BRGY. BACULOD TO DISIMURAY ROAD, CAUAY | Region II | Isabela 4th DEO | Completed | ₱31.2M | 100% | Medium risk44 | —-0.082 |
| 56 | 18BF0071NETWORK DEVELOPMENT - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - ROXAS BY-PASS ROAD, INCL ROW, ISABELA, ROXAS, ISABELA | Region II | Isabela 2nd DEO | Completed | ₱44.3M | 100% | Medium risk44 | —-0.081 |
| 57 | 22BG0079CSSP - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG THE BANK OF CAGAYAN RIVER, CENTRO 1, ANGADANAN, ISABELA | Region II | Isabela 3rd DEO | Completed | ₱42M | 100% | Medium risk44 | —-0.066 |
| 58 | 22BF0017SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES: CONSTRUCTION OF SIFFU RIVER FLOOD CONTROL STRUCTURE (SUERTE SECTION PHASE II), BRGY. SUERTE, QUIRINO,ISABELA | Region II | Isabela 2nd DEO | Completed | ₱41.5M | 100% | Medium risk44 | —-0.066 |
| 59 | 22BF0004ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS: CONSTRUCTION OF SIFFU RIVER FLOOD CONTROL PROJECT (QUI-BUR BRIDGE ABUT | Region II | Isabela 2nd DEO | Completed | ₱39.2M | 100% | Medium risk44 | —-0.066 |
| 60 | 22BG0067CSSP - SIPAG - FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG THE BANK OF CAGAYAN RIVER, CUMU, ANGADANAN, ISABELA | Region II | Isabela 3rd DEO | Completed | ₱42.1M | 100% | Medium risk44 | —-0.067 |
| 61 | 22BF0002FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES CONSTRUCTION OF SIFFU RIVER FLOOD CONTROL STRUCTURE (CAMAAL SECTION PHASE II), BRGY. CAMAAL, QUIRINO, ISABELA | Region II | Isabela 2nd DEO | Completed | ₱41.5M | 100% | Medium risk44 | —-0.065 |
| 62 | 19BG0042OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS: CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF CAGAYAN RIVER FLOOD CONTROL PROJECT, CENTRO I, ANGADANAN, ISABELA | Region II | Isabela 3rd DEO | Completed | ₱18.6M | 100% | Medium risk44 | —-0.067 |
| 63 | 22BF0046FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES: CONSTRUCTION OF SIFFU RIVER FLOOD CONTROL PROJECT (QUIBUR BRIDGE DOWNSTREAM SECTION PHASE II), QUIRINO, ISABELA | Region II | Isabela 2nd DEO | Completed | ₱20.8M | 100% | Medium risk44 | —-0.069 |
| 64 | 18BG0048CONSTRUCTION OF MAGAT RIVER FLOOD CONTROL PROJET, PULAY, LUNA, ISABELA, STA. 0+000 - STA. 0+172.40 | Region II | Isabela 3rd DEO | Completed | ₱27.9M | 100% | Medium risk44 | —-0.070 |
| 65 | 18BG0042CONSTRUCTION OF MAGAT RIVER FLOOD CONTROL PROJECT, LALOG, LUNA, ISABELA, STA. 0+172.40 - STA. 0+344.80 | Region II | Isabela 3rd DEO | Completed | ₱27.9M | 100% | Medium risk44 | —-0.070 |
| 66 | 18BF0036NETWORK DEVELOPMENT OFF CARRIAGEWAY IMPROVEMENT TERTIARY ROADS ALONG ILAGAN - DELFIN ALBANO - MALLIG ROAD (S00761LZ), K0438+375-K0440+638, MALLIG, ISABELA | Region II | Isabela 2nd DEO | Completed | ₱21M | 100% | Medium risk44 | —-0.083 |
| 67 | 23BG0044OO2:PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM - CONST/ REHAB OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF CAGAYAN RIVER FLOOD CONTROL PROJECT, BRGY. DISTRICT 1, REINA MER | Region II | Isabela 3rd DEO | Completed | ₱43.5M | 100% | Medium risk44 | —-0.065 |
| 68 | 20BG0042OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF RIVER FLOOD CONTROL PROJECT, BRGY. QUEZON, DADDA SECTION, NAGUIILIAN, ISAB | Region II | Isabela 3rd DEO | Completed | ₱45.9M | 100% | Medium risk44 | —-0.065 |
| 69 | 20BG0034OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION / REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF CAGAYAN RIVER FLOOD CONTROL PROJECT PHASE II | Region II | Isabela 3rd DEO | Completed | ₱34M | 100% | Medium risk44 | —-0.066 |
| 70 | 19BF0047PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS: CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE-CONSTRUCTION OF FLOOD CONTROL ALONG RIVERBANK OF BRGY. QUEZON PHASE I, NAGUILIAN, IS | Region II | Isabela 2nd DEO | Completed | ₱28.5M | 100% | Medium risk44 | —-0.067 |
| 71 | 22BH0056SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES; CONSTRUCTION OF BRGY. CARABATAN GRANDE FLOOD CONTROL STRUCTURE, CAUAYAN CITY, ISABELA | Region II | Isabela 4th DEO | Completed | ₱45.1M | 100% | Medium risk44 | —-0.068 |
| 72 | 24BF0021NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - ROXAS BYPASS ROAD, ISABELA | Region II | Isabela 2nd DEO | Completed | ₱44M | 100% | Medium risk44 | —-0.081 |
| 73 | 23BF0043NETWORK DEVELOPMENT PROGRAM CONSTRUCTION OF BY-PASS AND DIVERSION ROADS ROXAS BYPASS ROAD, ISABELA, ROXAS, ISABELA | Region II | Isabela 2nd DEO | Completed | ₱43.7M | 100% | Medium risk44 | —-0.083 |
| 74 | 22BG0070CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES - CONSTRUCTION OF DRAINAGE CANAL, BARANGAY DISTRICT 1 - DISTRICT 2 POBLACION, REINA MERCEDES, ISABELA | Region II | Isabela 3rd DEO | Completed | ₱4.9M | 100% | Medium risk44 | —-0.069 |
| 75 | 18BF0004CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEM- CONSTRUCTION OF SIFFU RIVER FLOOD CONTROL PROJECT (QUILING SECTION), ROXAS, ISABELA, BRGY. QUILING, ROXAS, ISABELA | Region II | Isabela 2nd DEO | Completed | ₱27.9M | 100% | Medium risk44 | —-0.069 |