Opening the dossier…
Opening the dossier…
Contractor dossier
32 projects on file, including joint ventures this contractor is part of.
Total projects
32
Total budget
₱680.5M
Average progress
100.0%
Completion rate
100.0%
Average risk score
43.3
Medium risk on average, out of 100
Flagged as unusual
0
0.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region XI | 24 | ₱561.8M | 43.8 | 0 | 100.0% |
| Region X | 5 | ₱82.9M | 37.3 | 0 | 100.0% |
| Region XIII | 3 | ₱35.7M | 49.4 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 16 | ₱322M | 45.0 | 0 | 100.0% |
| Buildings and Facilities | 8 | ₱197.8M | 32.2 | 0 | 100.0% |
| Flood Control and Drainage | 4 | ₱122.2M | 45.5 | 0 | 100.0% |
| OTHER | 2 | ₱25.7M | 73.4 | 0 | 100.0% |
| Bridges | 2 | ₱12.7M | 39.7 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 17NH0030NETWORK DEVELOPMENT - OFF - CARRIAGEWAY IMPROVEMENT INCLUDING (SAN AGUSTIN DIVERSION ROAD - K1361+625 - K1361+453), SAN AGUSTIN, SURIGAO DEL SUR | Region XIII | Surigao del Sur 1st DEO | Completed | ₱15.8M | 100% | High risk74 | —-0.021 |
| 17LC0028CONCRETING OF PUBLIC MARKET ROADS, ISING, CARMEN, DAVAO DEL NORTE | Region XI | Davao del Norte DEO | Completed | ₱9.9M | 100% | High risk73 | —-0.026 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
Nothing to report.
No flagged projects here.
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 17NH0030NETWORK DEVELOPMENT - OFF - CARRIAGEWAY IMPROVEMENT INCLUDING (SAN AGUSTIN DIVERSION ROAD - K1361+625 - K1361+453), SAN AGUSTIN, SURIGAO DEL SUR | Region XIII | Surigao del Sur 1st DEO | Completed | ₱15.8M | 100% | High risk74 | —-0.021 |
| 2 | 17LC0028CONCRETING OF PUBLIC MARKET ROADS, ISING, CARMEN, DAVAO DEL NORTE | Region XI | Davao del Norte DEO | Completed | ₱9.9M | 100% | High risk73 | —-0.026 |
| 3 | 17LC0020TAGUM-LIBUGANON RIVER FLOOD CONTROL STA. 5 + 600 - STA. 6 + 376, STA. 0 + 040- STA. 0+160, STA. 8 +739-STA. 8 + 879.20 INCLUDING RROW, DAVAO DEL NORTE | Region XI | Davao del Norte DEO | Completed | ₱36M | 100% | Medium risk50 | —-0.048 |
| 4 | 17LA0048RECHANNELING AND CONSTRUCTION OF DIKE IN KINGKING RIVER AT CEBULIDA SECTION (LEFT SIDE) PANTUKAN 2ND LD, COMPOSTELA VALLEY PROVINCE | Region XI | Davao de Oro 1st DEO | Completed | ₱45.3M | 100% | Medium risk50 | —-0.047 |
| 5 | 18LF0019REHABILITATION/RECONSTRUCTION OF ROAD WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE ALONG SURIGAO DEL SUR BDRY.- DAVAO ORIENTAL COASTAL RD. K1654+695- K1654+858, K1686+060-K1686+100, K1686+700 - K1686+745, K1686+940- K1687+032, FIRST DISTRICT, DAVAO ORIENTAL | Region XI | Davao Oriental 1st DEO | Completed | ₱32.9M | 100% | Medium risk47 | —-0.074 |
| 6 | 19LA0486CONCRETING OF PUROK 3, BRGY. POBLACION-BRGY. MACOPA FMR, BRGY. POBLACION AND BRGY. MACOPA, LAAK, COMPOSTELA VALLEY PROVINCE | Region XI | Davao de Oro 1st DEO | Completed | ₱17.9M | 100% | Medium risk46 | —-0.031 |
| 7 | 20LA0068BONGKILATON ROAD LEADING TO MANDAYA VILLAGE, PANSAN FALLS, BONGKILATON CAVE AND TAGBUBUNLAS FALSS, BRGY. NGAN, COMPOSTELA, COMPOSTELA VALLEY PROVINCE | Region XI | Davao de Oro 1st DEO | Completed | ₱33.4M | 100% | Medium risk46 | —-0.078 |
| 8 | 19LC0066CONSTRUCTION OF CONCRETE ROAD-SITIO PANDULIAN, MABANTAO-FLORIDA-SUAON ROAD LEADING TO KAPALONG WOODLAND RESORT, KAPALONG, DAVAO DEL NORTE | Region XI | Davao del Norte DEO | Completed | ₱29.4M | 100% | Medium risk46 | —-0.088 |
| 9 | 22LB0131CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE - JCT. ACACIA ROAD - PUROK NEW VISAYAS LEADING TO SAFARI LAND CROCODILE PARK, BRGY. ACACIA, DAVAO CITY | Region XI | Davao City DEO | Completed | ₱18.4M | 100% | Medium risk46 | —-0.091 |
| 10 | 18LF0042CONSTRUCTION/IMPROVEMENT OF JCT. (MAWAB-MARAGUSAN-CARAGA) TO BRGY. MERCEDES TO SITIO CABYAWAN LEADING TO MAGPAMANGAW FALLS, BRGY. MERCEDES, CARAGA, DAVAO ORIENTAL | Region XI | Davao Oriental 1st DEO | Completed | ₱18.9M | 100% | Medium risk46 | —-0.078 |
| 11 | 19LF0019JCT. MAWAB-MARAGUSAN-CARAGA TO BRGY. MERCEDES TO SITIO CABYAWAN LEADING TO MAGPAMANGAW FALLS, BRGY. MERCEDES, CARAGA, DAVAO ORIENTAL | Region XI | Davao Oriental 1st DEO | Completed | ₱19.6M | 100% | Medium risk46 | —-0.078 |
| 12 | 19LC0060CONSTRUCTION OF CONCRETE ROAD NRJ (CABALUNA ROAD) TO JUNCTION BRGY.CONSOLACION LEADING TO INLAND RESORTS OF BRGY. MALATIVAS,PANABO CITY,DAVAO DEL NORTE | Region XI | Davao del Norte DEO | Completed | ₱14.2M | 100% | Medium risk46 | —-0.093 |
| 13 | 19LF0034JUNCTION ROSARIO HILLS TO SITIO ENRIQUEZ, BRGY. SAN IGNACIO CONNECTING MANAY PUBLIC TERMINAL TO COCONUT, CACAO & BANANA CHIPS PROCESSING SITE | Region XI | Davao Oriental 1st DEO | Completed | ₱9.8M | 100% | Medium risk46 | —-0.077 |
| 14 | 18KB0027REHAB/RECONST OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE ALONG KKK ROAD, K1590+500-K1590+600, KADINGILAN, BUKIDNON | Region X | Bukidnon 2nd DEO | Completed | ₱16.6M | 100% | Medium risk45 | —-0.093 |
| 15 | 18KB0002PAVING OF UNPAVED ROADS ALONG KIBAWE-KADINGILAN-KALILANGAN ROAD, K1590+908-K1591+556, MALINAO, POBLACION, KADINGILAN, BUKIDNON | Region X | Bukidnon 2nd DEO | Completed | ₱17.9M | 100% | Medium risk45 | —-0.093 |
| 16 | 20LC0032NRJ TAGUM-PANABO ROAD PAG-ASA (KAPALONG) ROAD -KIMAMON (STO. TOMAS) - LUNGA-OG ROAD, SALVACION - SAN MIGUEL, STO. TOMAS ROAD CONNECTING PANABO WHARF TO BANANA INDUSTRIES, KAPALONG, DAVAO DEL NORTE | Region XI | Davao del Norte DEO | Completed | ₱9.8M | 100% | Medium risk45 | —-0.089 |
| 17 | 22LB0450CONSTRUCTION OF SENIOR CITIZENS BUILDING AT PAQUIBATO DISTRICT, DAVAO CITY | Region XI | Davao City DEO | Completed | ₱9.7M | 100% | Medium risk45 | —-0.090 |
| 18 | 17LA0006OFF-CARRIAGEWAY IMPROVEMENT INCLUDING DRAINAGE @ DAANG MAHARLIKA (MN) AND MONTEVISTA-DNAS ROAD INTERSECTION, MONTEVISTA, COMPOSTELA VALLEY PROVINCE | Region XI | Davao de Oro 1st DEO | Completed | ₱19.6M | 100% | Medium risk45 | —-0.048 |
| 19 | 23LI0009CONSTRUCTION OF REVETMENT ALONG UPPER AGUSAN RIVER, OSMEÑA SECTION, COMPOSTELA, DAVAO DE ORO | Region XI | Davao de Oro 2nd DEO | Completed | ₱31.1M | 100% | Medium risk44 | —-0.067 |
| 20 | 17KB0020REHAB/RECONST/UPGRADING OF DAMAGED PAVED NATIONAL ROADS INCLUDING DRAINAGE BASED ON PMS/HDM-4, KKK | Region X | Bukidnon 2nd DEO | Completed | ₱13.8M | 100% | Medium risk43 | —-0.066 |
| 21 | 18LB0282REHABILITATION OF ROAD AT JCT. R. CASTILLO STREET (UBALDE SECTION) INCLUDING ROW DAVAO CITY | Region XI | Davao City DEO | Completed | ₱39.8M | 100% | Medium risk43 | —-0.095 |
| 22 | 19KB0143CONSTRUCTION OF ONE UNIT THREE STOREY NINE (9) CLASSROOM SCHOOL BUILDING AT QUEZON CES, QUEZON, BUKIDNON | Region X | Bukidnon 2nd DEO | Completed | ₱31.7M | 100% | Medium risk41 | —-0.038 |
| 23 | 18LA0340CONSTRUCTION OF ONE (1) UNIT, TWO (2) STOREY, TEN (10) CLASSROOMS BUILDING AT DIOSDADO MACAPAGAL NHS, COMPOSTELA, COMPOSTELA VALLEY PROVINCE | Region XI | Davao de Oro 1st DEO | Completed | ₱35.2M | 100% | Medium risk41 | —-0.028 |
| 24 | 18LA0348CONSTRUCTION OF ONE (1) UNIT, THREE (3) STOREY, NINE (9) CLASSROOM BUILDING AT OLAYCON INTEGRATED SCHOOL, MONKAYO, COMPOSTELA VALLEY PROVINCE | Region XI | Davao de Oro 1st DEO | Completed | ₱31.7M | 100% | Medium risk41 | —-0.033 |
| 25 | 17LC0027COMPLETION OF PEOPLE'S CULTURAL CENTER (CONSTRUCTION OF CONCRETE BLEACHER) BRAULIO E. DUJALI, DAVAO DEL NORTE | Region XI | Davao del Norte DEO | Completed | ₱9.9M | 100% | Medium risk40 | —-0.058 |