Opening the dossier…
Opening the dossier…
Contractor dossier
20 projects on file, including joint ventures this contractor is part of.
Total projects
20
Total budget
₱267M
Average progress
91.4%
Completion rate
55.0%
Below 70%
Average risk score
58.8
Medium risk on average, out of 100
Flagged as unusual
3
15.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Cordillera Administrative Region | 20 | ₱267M | 58.8 | 3 | 91.4% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 9 | ₱85.8M | 44.1 | 0 | 98.2% |
| OTHER | 5 | ₱103.5M | 77.8 | 2 | 77.8% |
| GAA 2025 OO-1 | 3 | ₱45.4M | 91.3 | 1 | 89.5% |
| Flood Control and Drainage | 2 | ₱29.3M | 45.2 | 0 | 100.0% |
| Buildings and Facilities | 1 | ₱2.9M | 26.6 | 0 | 86.6% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25PI0002CONSTRUCTION OF MISSING LINKS/NEW ROADS - BESAO - TUBO (VIA TAMBOAN) ROAD, MOUNTAIN PROVINCE | Cordillera Administrative Region | Mountain Province 1st DEO | On-Going | ₱21.8M | 81% | High risk92 | Flagged0.002 |
| 25PI0101DANTAY-SAGADA RD - KO392+518 - KO392+574, KO392+100 - KO392+163 | Cordillera Administrative Region | Mountain Province 1st DEO | On-Going | ₱12.1M | 89% | High risk91 | —-0.003 |
| 25PI0031SAGADA-BESAO-QUIRINO RD - (SO3998LZ) CHAINAGE 12122 - CHAINAGE 12145, CHAINAGE 12370 - CHAINAGE 12390, CHAINAGE 14135 - CHAINAGE 14164 | Cordillera Administrative Region | Mountain Province 1st DEO | On-Going | ₱11.4M | 98% | High risk90 | —-0.003 |
| 24P00088LGU HOSPITALS - BESAO DISTRICT HOSPITAL, MOUNTAIN PROVINCE | Cordillera Administrative Region | Cordillera Administrative Region | On-Going | ₱29.9M | 42% | High risk87 | Flagged0.062 |
| 24P00095CONSTRUCTION OF NEW SUPER HEALTH CENTERS/RHU - BESAO SUPER HEALTH CENTER, MOUNTAIN PROVINCE | Cordillera Administrative Region | Cordillera Administrative Region | On-Going | ₱10M | 47% | High risk84 | Flagged0.058 |
| 24PI0023OO1, NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF MISSING LINKS/NEW ROADS - BESAO - TUBO (VIA TAMBOAN) ROAD, MOUNTAIN PROVINCE | Cordillera Administrative Region | Mountain Province 1st DEO | Completed | ₱19.6M | 100% | High risk73 | —-0.025 |
| 22PI0035CONSTRUCTION OF MISSING LINKS/ NEW ROADS, BESAO - TUBO (VIA TAMBOAN) ROAD, MOUNTAIN PROVINCE | Cordillera Administrative Region | Mountain Province 1st DEO | Completed | ₱24.5M | 100% | High risk73 | —-0.025 |
| 21PI0053CONSTRUCTION OF MISSING LINKS/ NEW ROADS, BESAO - TUBO (VIA TAMBOAN) ROAD, MOUNTAIN PROVINCE | Cordillera Administrative Region | Mountain Province 1st DEO | Completed | ₱19.6M | 100% | High risk73 | —-0.025 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24P00088LGU HOSPITALS - BESAO DISTRICT HOSPITAL, MOUNTAIN PROVINCE | Cordillera Administrative Region | Cordillera Administrative Region | On-Going | ₱29.9M | 42% | High risk87 | Flagged0.062 |
| 24P00095CONSTRUCTION OF NEW SUPER HEALTH CENTERS/RHU - BESAO SUPER HEALTH CENTER, MOUNTAIN PROVINCE | Cordillera Administrative Region | Cordillera Administrative Region | On-Going | ₱10M | 47% | High risk84 | Flagged0.058 |
| 25PI0002CONSTRUCTION OF MISSING LINKS/NEW ROADS - BESAO - TUBO (VIA TAMBOAN) ROAD, MOUNTAIN PROVINCE | Cordillera Administrative Region | Mountain Province 1st DEO | On-Going | ₱21.8M | 81% | High risk92 | Flagged0.002 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25PI0002CONSTRUCTION OF MISSING LINKS/NEW ROADS - BESAO - TUBO (VIA TAMBOAN) ROAD, MOUNTAIN PROVINCE | Cordillera Administrative Region | Mountain Province 1st DEO | On-Going | ₱21.8M | 81% | High risk92 | Flagged0.002 |
| 2 | 25PI0101DANTAY-SAGADA RD - KO392+518 - KO392+574, KO392+100 - KO392+163 | Cordillera Administrative Region | Mountain Province 1st DEO | On-Going | ₱12.1M | 89% | High risk91 | —-0.003 |
| 3 | 25PI0031SAGADA-BESAO-QUIRINO RD - (SO3998LZ) CHAINAGE 12122 - CHAINAGE 12145, CHAINAGE 12370 - CHAINAGE 12390, CHAINAGE 14135 - CHAINAGE 14164 | Cordillera Administrative Region | Mountain Province 1st DEO | On-Going | ₱11.4M | 98% | High risk90 | —-0.003 |
| 4 | 24P00088LGU HOSPITALS - BESAO DISTRICT HOSPITAL, MOUNTAIN PROVINCE | Cordillera Administrative Region | Cordillera Administrative Region | On-Going | ₱29.9M | 42% | High risk87 | Flagged0.062 |
| 5 | 24P00095CONSTRUCTION OF NEW SUPER HEALTH CENTERS/RHU - BESAO SUPER HEALTH CENTER, MOUNTAIN PROVINCE | Cordillera Administrative Region | Cordillera Administrative Region | On-Going | ₱10M | 47% | High risk84 | Flagged0.058 |
| 6 | 24PI0023OO1, NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF MISSING LINKS/NEW ROADS - BESAO - TUBO (VIA TAMBOAN) ROAD, MOUNTAIN PROVINCE | Cordillera Administrative Region | Mountain Province 1st DEO | Completed | ₱19.6M | 100% | High risk73 | —-0.025 |
| 7 | 22PI0035CONSTRUCTION OF MISSING LINKS/ NEW ROADS, BESAO - TUBO (VIA TAMBOAN) ROAD, MOUNTAIN PROVINCE | Cordillera Administrative Region | Mountain Province 1st DEO | Completed | ₱24.5M | 100% | High risk73 | —-0.025 |
| 8 | 21PI0053CONSTRUCTION OF MISSING LINKS/ NEW ROADS, BESAO - TUBO (VIA TAMBOAN) ROAD, MOUNTAIN PROVINCE | Cordillera Administrative Region | Mountain Province 1st DEO | Completed | ₱19.6M | 100% | High risk73 | —-0.025 |
| 9 | 24PI0070FARM-TO-MARKET ROAD (FMR) PROJECTS - CONCRETING OF BRGY. AGAWA TO BALAAN TO BRGY. AMBAGIW FMR, BRGY. AGAWA, BESAO, MOUNTAIN PROVINCE | Cordillera Administrative Region | Mountain Province 1st DEO | Completed | ₱14.9M | 100% | Medium risk46 | —-0.036 |
| 10 | 25PI0034CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BAYUDAN-CHICO RIVER, NACAGANG-KABAYBAYAN-TAMBINGAN, STA 47+017 - STA 47+057 (RS), STA. 47+112 - STA 47+140 (LS), SABANGAN, MOUNTAIN PROVINCE | Cordillera Administrative Region | Mountain Province 1st DEO | On-Going | ₱9.7M | 100% | Medium risk45 | —-0.037 |
| 11 | 22PI0032BONTOC RD - K0344+450 - K0344+480, K0373+801 - K0373+903, K0374+024 - K0374+044, K0387+970 - K0388+000 | Cordillera Administrative Region | Mountain Province 1st DEO | Completed | ₱14.7M | 100% | Medium risk45 | —-0.082 |
| 12 | 24PI0026CONSTRUCTION OF SUPANG FLOOD CONTROL, BISIBISAN SECTION ALONG BAYUDAN-CHICO RIVER, SABANGAN, MOUNTAIN PROVINCE | Cordillera Administrative Region | Mountain Province 1st DEO | Completed | ₱19.6M | 100% | Medium risk45 | —-0.069 |
| 13 | 22PI0029IMPROVEMENT OF LOCAL ROAD, BARANGAY DATA, SABANGAN, MOUNTAIN PROVINCE | Cordillera Administrative Region | Mountain Province 1st DEO | Completed | ₱5M | 100% | Medium risk44 | —-0.081 |
| 14 | 23PI0023CONSTRUCTION OF MISSING LINKS/ NEW ROADS - BESAO-TUBO (VIA TAMBOAN), MOUNTAIN PROVINCE | Cordillera Administrative Region | Mountain Province 1st DEO | Completed | ₱19.6M | 100% | Medium risk44 | —-0.084 |
| 15 | 24PI0067BIP- ACCESS ROADS AND/ OR BRIDGES FROM THE NATIONAL ROADS CONNECTING TO INDIGENOUS PEOPLE (IP) COMMUNITIES - CONSTRUCTION OF LOCAL ROAD, BARANGAY DATA, SABANGAN, MOUNTAIN PROVINCE | Cordillera Administrative Region | Mountain Province 1st DEO | On-Going | ₱4.9M | 94% | Medium risk44 | —-0.045 |
| 16 | 24PI0137BIP, IMPROVEMENT OF AGAWA-AMBAGIW ROAD, LOCATED AT BRGY. KIN-IWAY, BESAO, MOUNTAIN PROVINCE | Cordillera Administrative Region | Mountain Province 1st DEO | On-Going | ₱4.9M | 89% | Medium risk44 | —-0.045 |
| 17 | 24PI0062BIP-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS CONNECTING TO INDIGENOUS PEOPLE (IP) COMMUNITIES, CONSTRUCTION OF ROAD, BARANGAY LAYLAYA, BESAO, MOUNTAIN PROVINCE | Cordillera Administrative Region | Mountain Province 1st DEO | Completed | ₱5M | 100% | Medium risk44 | —-0.078 |
| 18 | 24PI0071BIP, IMPROVEMENT OF SITIO MALITEN ROAD, BRGY. LAYLAYA, BESAO, MOUNTAIN PROVINCE | Cordillera Administrative Region | Mountain Province 1st DEO | Completed | ₱5M | 100% | Medium risk44 | —-0.080 |
| 19 | 23PI0085FARM-TO-MARKET ROAD (FMR) PROJECTS - CONCRETING OF BRGY. AGAWA-MASAMEYEO-GUEDAY FMR, BRGY. GUEDAY, BESAO, MOUNTAIN PROVINCE | Cordillera Administrative Region | Mountain Province 1st DEO | Completed | ₱11.9M | 100% | Medium risk40 | —-0.037 |
| 20 | 25PI0049BIP, CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY TAMBINGAN, SABANGAN, MOUNTAIN PROVINCE | Cordillera Administrative Region | Mountain Province 1st DEO | On-Going | ₱2.9M | 87% | Low risk27 | —-0.042 |