Opening the dossier…
Opening the dossier…
Contractor dossier
117 projects on file, including joint ventures this contractor is part of.
Total projects
117
Total budget
₱2.9B
Average progress
99.3%
Completion rate
93.2%
Average risk score
34.0
Medium risk on average, out of 100
Flagged as unusual
1
0.9% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region III | 113 | ₱2.6B | 33.1 | 0 | 99.4% |
| Region XI | 3 | ₱240.4M | 66.5 | 1 | 96.8% |
| Region IV-B | 1 | ₱34.4M | 40.5 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 55 | ₱870.2M | 30.3 | 0 | 99.0% |
| Buildings and Facilities | 33 | ₱390.4M | 25.4 | 0 | 100.0% |
| Flood Control and Drainage | 22 | ₱1.4B | 43.5 | 0 | 99.9% |
| GAA 2025 OO-2 | 2 | ₱144.5M | 89.0 | 0 | 94.6% |
| OTHER | 2 | ₱60.5M | 69.0 | 1 | 96.5% |
| GAA 2025 SSP | 1 | ₱5.9M | 93.7 | 0 | 100.0% |
| GAA 2025 OO-1 | 1 | ₱22.3M | 89.4 | 0 | 99.5% |
| Water Provision and Storage | 1 | ₱2.3M | 14.2 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25CE0236CONSTRUCTION OF ROAD, BARANGAY PINAGPANAAN, TALAVERA, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | On-Going | ₱5.9M | 100% | High risk94 | —-0.006 |
| 25CF0057FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG PEÑARANDA RIVER, BARANGAY SAN NICOLAS, GAPAN CITY, NUEVA ECIJA | Region III | Nueva Ecija 2nd DEO | On-Going | ₱96M | 91% | High risk92 | —-0.016 |
| 25CE0234ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS, NUEVA ECIJA-PANGASINAN RD - K0141 + 184 - K0141 + 202, K0141 + 330 - K0141 + 348, K0141 + 600 - K0141 + 962, K0142 + 000 - K0142 + 044, K0142 | Region III | Nueva Ecija 1st DEO | On-Going | ₱22.3M | 100% | High risk89 | —-0.013 |
| 25CE0030CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG RIO CHICO RIVER, BARANGAY MACAMIAS, GUIMBA, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | On-Going | ₱48.5M | 98% | High risk86 | —-0.021 |
| 24LA0049CONSTRUCTION OF MULTI-PURPOSE BUILDING AT TAMBONGON NATIONAL HIGHSCHOOL, PANTUKAN, DAVAO DE ORO | Region XI | Davao de Oro 1st DEO | On-Going | ₱49M | 93% | High risk76 | Flagged0.019 |
| 17CE0316ASSET PRESERVATION - PREVENTIVE MAINTENANCE - SECONDARY ROADS - NUEVA ECIJA - PANGASINAN RD - K0161+000 - K0162+000, K0163+000 - K0163+952, K0170+000 - K0171+000 | Region III | Nueva Ecija 1st DEO | Completed | ₱19.7M | 100% | High risk66 | —-0.066 |
| 17CE0317ASSET PRESERVATION - PREVENTIVE MAINTENANCE - TERTIARY ROADS - TARLAC - GUIMBA RD VIA VICTORIA - K0148+-184 - K0149+300, K0151+000 - K0153+329 | Region III | Nueva Ecija 1st DEO | Completed | ₱25.1M | 100% | High risk65 | —-0.067 |
| 17CF0063ASSET PRESERVATION OF NATIONAL ROADS-REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED NATIONAL ROADS INCLUDING DRAINAGE BASED ON PAVEMENT MANAGEMENT SYSTEM/HIGHWAY DEVELOPMENT AND MANAGEMENT-4 (HDM-4) BANGAD -FORT MAGSAYSAY ROAD,K0132+026.10-K0 1 | Region III | Nueva Ecija 2nd DEO | Completed | ₱42.7M | 100% | High risk65 | —-0.067 |
| 17CE0163CONSTRUCTION OF CONCRETE SLOPE PROTECTION WITH STEEL SHEET PILE ALONG TALAVERA RIVER, BRGY. MATIAS, TALAVERA, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | Completed | ₱27.9M | 100% | High risk64 | —-0.062 |
| 17CE0158CONSTRUCTION/REHABILITATION OF FLOOD CONTROL STRUCTURES ALONG TALAVERA RIVER, BRGY. STA. MONICA, ALIAGA, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | Completed | ₱27.9M | 100% | High risk64 | —-0.062 |
| 24L00129CONSTRUCTION OF COASTAL REVETMENT AT KINGKING RIVER MOUTH, PANTUKAN, DAVAO DE ORO | Region XI | Region XI | On-Going | ₱94.9M | 97% | High risk63 | —-0.021 |
| 24CF0039ASSET PRESERVATION PROGRAM - REHABILITATION / RECONSTRUCTION / UPGRADING OF DAMAGED PAVED ROADS - TERTIARY ROADS - CABANATUAN CITY-CARMEN RD - K0127+730-K0127+902, K0128+000-K0128+062 | Region III | Nueva Ecija 2nd DEO | Completed | ₱11.5M | 100% | High risk62 | —-0.042 |
| 24LA0015CONSTRUCTION OF REVETMENT ALONG KINGKING RIVER (KINGKING BRIDGE DOWNSTREAM), BARANGAY KINGKING, PANTUKAN, DAVAO DE ORO | Region XI | Davao de Oro 1st DEO | Completed | ₱96.5M | 100% | High risk61 | —-0.058 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 26 | 24CF0078SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES / FACILITIES - CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY DALAMPANG, CABANATUAN CITY, NUEVA ECIJA | Region III | Nueva Ecija 2nd DEO | Completed | ₱71.1M | 100% | Medium risk36 | —-0.085 |
| 27 | 23CE0062CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - TERTIARY ROADS, GUIMBA-TALUGTUG-UMINGAN RD-(S04415LZ) CHAINAGE 4597 - CHAINAGE 5279, CHAINAGE 7259 - CHAINAGE 7562 | Region III | Nueva Ecija 1st DEO | Completed | ₱48.9M | 100% | Medium risk36 | —-0.101 |
| 28 | 23CE0019CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG TALAVERA RIVER, BARANGAY SAN NICOLAS, LLANERA, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | Completed | ₱49M | 100% | Medium risk35 | —-0.088 |
| 29 | 22CF0076CONSTRUCTION OF ENLISTED PERSONNEL BARRACKS, FORT RAMON MAGSAYSAY, PALAYAN CITY, NUEVA ECIJA | Region III | Nueva Ecija 2nd DEO | Completed | ₱24M | 100% | Medium risk35 | —-0.100 |
| 30 | 23CF0015CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY PINAMALISAN, GABALDON, NUEVA ECIJA | Region III | Nueva Ecija 2nd DEO | Completed | ₱4.9M | 100% | Medium risk35 | —-0.106 |
| 31 | 18CF0149CONSTRUCTION OF MULTI PURPOSE BUILDING, FORT MAGSAYSAY, SANTA ROSA, NUEVA ECIJA | Region III | Nueva Ecija 2nd DEO | Completed | ₱9.7M | 100% | Medium risk34 | —-0.105 |
| 32 | 21CE0115CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG RIO CHICO RIVER, STA. 48+168 - STA. 48+483, BRGY. PASONG INCHIC, GUIMBA, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | Completed | ₱66.2M | 100% | Medium risk34 | —-0.087 |
| 33 | 22CE0074CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG LABONG RIVER, BRGY. MANACSAC, GUIMBA, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | Completed | ₱67.6M | 100% | Medium risk34 | —-0.088 |
| 34 | 23CF0014CONSTRUCTION OF MULTI-PURPOSE BUILDING, (COVERED COURT), BARANGAY TALABUTAB SUR, GENERAL MAMERTO NATIVIDAD, NUEVA ECIJA | Region III | Nueva Ecija 2nd DEO | Completed | ₱4.9M | 100% | Medium risk34 | —-0.102 |
| 35 | 22CF0102CONSTRUCTION OF METAL CASTING CENTER, NUEVA ECIJA UNIVERSITY OF SCIENCE AND TECHNOLOGY NEUST SUMACAB CAMPUS, CABANATUAN CITY, NUEVA ECIJA | Region III | Nueva Ecija 2nd DEO | Completed | ₱14.7M | 100% | Medium risk33 | —-0.104 |
| 36 | 25CF0089NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - SECONDARY ROADS - NUEVA ECIJA - AURORA RD - K0138+121.40-K0138+144, K0138+460-K0139+945 | Region III | Nueva Ecija 2nd DEO | On-Going | ₱33.7M | 65% | Medium risk33 | —-0.063 |
| 37 | 24CE0259CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG DIBABUYAN RIVER, BARANGAY MABINI, SANTO DOMINGO, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | Completed | ₱47.8M | 100% | Medium risk33 | —-0.090 |
| 38 | 20CE0080CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG TALAVERA RIVER, BRGY. PUNCAN, CARRANGLAN, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | Completed | ₱33.6M | 100% | Medium risk33 | —-0.087 |
| 39 | 25CF0072SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - REHABILITATION OF ROAD, GABALDON, NUEVA ECIJA | Region III | Nueva Ecija 2nd DEO | Completed | ₱19.3M | 100% | Medium risk32 | —-0.105 |
| 40 | 24CE0100CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG LABONG RIVER, BARANGAY CAINGIN TABING ILOG, GUIMBA, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | Completed | ₱47.8M | 100% | Medium risk32 | —-0.090 |
| 41 | 25CE0025NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, GUIMBA-PURA ROAD, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | On-Going | ₱38.8M | 80% | Medium risk32 | —-0.064 |
| 42 | 24CF0047BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING AT VALDEFUENTE ELEMENTARY SCHOOL, BRGY. VALDEFUENTE, CABANATUAN CITY, NUEVA ECIJA | Region III | Nueva Ecija 2nd DEO | Completed | ₱4.9M | 100% | Medium risk32 | —-0.106 |
| 43 | 22CF0044ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - TERTIARY ROADS - GAPAN - FORT MAGSAYSAY RD - K0094+460.30 - K0095+000, K0096+000 - K0096+604, K0111+614.90 - K0112+910.80 | Region III | Nueva Ecija 2nd DEO | Completed | ₱21.4M | 100% | Medium risk32 | —-0.105 |
| 44 | 24CF0053BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING (DAY CARE CENTER), CALAGUNDIAN, BRGY. ADUAS NORTE, CABANATUAN CITY, NUEVA ECIJA | Region III | Nueva Ecija 2nd DEO | Completed | ₱4.9M | 100% | Medium risk32 | —-0.107 |
| 45 | 23CE0030CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG LABONG RIVER, BARANGAY POBLACION SUR, LICAB, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | Completed | ₱49M | 100% | Medium risk32 | —-0.090 |
| 46 | 24CE0281ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS, NUEVA ECIJA - PANGASINAN RD - K0152+000 - K0153+000 | Region III | Nueva Ecija 1st DEO | Completed | ₱33.3M | 100% | Medium risk32 | —-0.102 |
| 47 | 24CF0044BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF COVERED COURT, BARANGAY SAN ROQUE SUR, CABANATUAN CITY, NUEVA ECIJA | Region III | Nueva Ecija 2nd DEO | Completed | ₱5.9M | 100% | Medium risk32 | —-0.105 |
| 48 | 21CF0087PREVENTIVE MAINTENANCE - PRIMARY ROADS, STA. ROSA - TARLAC RD. K0 109+000 - K0 109+726, K0110+1260 - K0 111+117.15 | Region III | Nueva Ecija 2nd DEO | Completed | ₱20.6M | 100% | Medium risk32 | —-0.103 |
| 49 | 22CE0179CONCRETING OF BARANGAY LENNEC FMR, BARANGAY LENNEC, GUIMBA, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | Completed | ₱19.9M | 100% | Medium risk32 | —-0.038 |
| 50 | 23CE0015ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - TERTIARY ROADS, CABANATUAN CITY - CARMEN RD K0129+(-1003) - K0129+000 | Region III | Nueva Ecija 1st DEO | Completed | ₱27.4M | 100% | Medium risk32 | —-0.104 |