Opening the dossier…
Opening the dossier…
Contractor dossier
37 projects on file, including joint ventures this contractor is part of.
Total projects
37
Total budget
₱480.3M
Average progress
91.3%
Completion rate
70.3%
Average risk score
44.9
Medium risk on average, out of 100
Flagged as unusual
5
13.5% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region IX | 37 | ₱480.3M | 44.9 | 5 | 91.3% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 25 | ₱439.3M | 49.4 | 3 | 98.2% |
| Buildings and Facilities | 8 | ₱23.3M | 26.8 | 1 | 66.6% |
| Water Provision and Storage | 3 | ₱12.7M | 39.4 | 0 | 100.0% |
| GAA 2025 SSP | 1 | ₱4.9M | 94.1 | 1 | 92.6% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25JI0049COMPLETION OF MULTI PURPOSE BUILDING, BALANGAO, DIPLAHAN, ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 1st DEO | On-Going | ₱4.9M | 93% | High risk94 | Flagged0.011 |
| 23JF0043ACCESS ROADS AND/ OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF CONCRETE ROAD ALONG TUNGAWAN (MALUNGON) - SIRAWAI ROAD, ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 2nd DEO | Completed | ₱86.8M | 100% | High risk63 | —-0.073 |
| 24JI0079CONCRETING OF BRGY. GAULAN TO BRGY. GUITOM FMR, BRGY. GAULAN, DIPLAHAN AND BRGY. GUITOM, BUUG, ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 1st DEO | On-Going | ₱29.8M | 85% | High risk60 | Flagged0.035 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24JI0079CONCRETING OF BRGY. GAULAN TO BRGY. GUITOM FMR, BRGY. GAULAN, DIPLAHAN AND BRGY. GUITOM, BUUG, ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 1st DEO | On-Going | ₱29.8M | 85% | High risk60 | Flagged0.035 |
| 24JF0071CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY MINSULAO, SIAY, ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 2nd DEO | On-Going | ₱3.4M | 61% | Low risk14 | Flagged0.020 |
| 25JI0049COMPLETION OF MULTI PURPOSE BUILDING, BALANGAO, DIPLAHAN, ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 1st DEO | On-Going | ₱4.9M | 93% | High risk94 | Flagged0.011 |
| 23JB0097CONCRETING OF BARANGAY ROAD, POBLACION SITIO LUPOC-MINLASAG, BARANGAY MINLASAG,ZN | Region IX | Zamboanga del Norte 1st DEO | On-Going | ₱33.7M | 92% | Medium risk54 | Flagged0.010 |
| 23JB0098CONCRETING OF BARANGAY ROAD, MINLASAG-SIPALOC BARANGAY SIPALOC-ZN | Region IX | Zamboanga del Norte 1st DEO | On-Going | ₱33.7M | 96% | Medium risk54 | Flagged0.010 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25JI0049COMPLETION OF MULTI PURPOSE BUILDING, BALANGAO, DIPLAHAN, ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 1st DEO | On-Going | ₱4.9M | 93% | High risk94 | Flagged0.011 |
| 2 | 23JF0043ACCESS ROADS AND/ OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF CONCRETE ROAD ALONG TUNGAWAN (MALUNGON) - SIRAWAI ROAD, ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 2nd DEO | Completed | ₱86.8M | 100% | High risk63 | —-0.073 |
| 3 | 24JI0079CONCRETING OF BRGY. GAULAN TO BRGY. GUITOM FMR, BRGY. GAULAN, DIPLAHAN AND BRGY. GUITOM, BUUG, ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 1st DEO | On-Going | ₱29.8M | 85% | High risk60 | Flagged0.035 |
| 4 | 25JI0083CONCRETING OF BRGY. LUMBOG FMR, BRGY. LUMBOG, IMELDA, ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 1st DEO | On-Going | ₱14.9M | 86% | Medium risk55 | —-0.001 |
| 5 | 22JI0010CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS - NATIONAL ROAD JUNCTION LEADING TO GUINOMAN CAVE AND WATERFALLS, DIPLAHAN, ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 1st DEO | Completed | ₱29.4M | 100% | Medium risk54 | —-0.085 |
| 6 | 23JB0098CONCRETING OF BARANGAY ROAD, MINLASAG-SIPALOC BARANGAY SIPALOC-ZN | Region IX | Zamboanga del Norte 1st DEO | On-Going | ₱33.7M | 96% | Medium risk54 | Flagged0.010 |
| 7 | 23JB0097CONCRETING OF BARANGAY ROAD, POBLACION SITIO LUPOC-MINLASAG, BARANGAY MINLASAG,ZN | Region IX | Zamboanga del Norte 1st DEO | On-Going | ₱33.7M | 92% | Medium risk54 | Flagged0.010 |
| 8 | 18JI0052ROAD WIDENING ALONG JCT IMELDA-ALICIA RD -K1752+200 - K1753 + 047 | Region IX | Zamboanga Sibugay 1st DEO | Completed | ₱26.1M | 100% | Medium risk54 | —-0.077 |
| 9 | 20JI0040PREVENTIVE MAINTENANCE - PRIMARY ROADS ALONG LANAO-PAGADIAN-ZAMBOANGA CITY RD K1738 + 041 - K1738 + 316, K1738 + 321 - K1738 + 362 , K1739 + 250 - K1739 + 289, K1739 + 362 | Region IX | Zamboanga Sibugay 1st DEO | Completed | ₱16.5M | 100% | Medium risk53 | —-0.086 |
| 10 | 23JI0008ROAD WIDENING - TERTIARY ROADS ALONG IMELDA-BAYOG-KUMALARANG-LAPUYAN-MARGOSATUBIG RD - K1751+(-594.60) - K1751 + (-080.00) | Region IX | Zamboanga Sibugay 1st DEO | On-Going | ₱17.5M | 100% | Medium risk53 | —-0.043 |
| 11 | 18JI0036REHABILITATION OF PAVED ROAD ALONG LANAO-PAGADIAN-ZAMBOANGA CITY ROAD, K1743+510 - K1743+906 | Region IX | Zamboanga Sibugay 1st DEO | Completed | ₱12.7M | 100% | Medium risk52 | —-0.086 |
| 12 | 24JI0075CONSTRUCTION OF ROAD, BARANGAY GUINOMAN-SITIO MALAGAK, DIPLAHAN, ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 1st DEO | On-Going | ₱9.9M | 96% | Medium risk51 | —-0.048 |
| 13 | 23JG0014CONSTRUCTION OF BY-PASS AND DIVERSION ROADS ALONG SAN ISIDRO-PANGI DIVERSION ROAD, SAN ISIDRO, BAYOG, ZAMBOANGA DEL SUR | Region IX | Zamboanga del Sur 2nd DEO | Completed | ₱7.3M | 100% | Medium risk51 | —-0.086 |
| 14 | 24JG0019ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS CONNECTING TO INDIGENOUS PEOPLE (IP) COMMUNITIES - CONSTRUCTION OF ROAD, PUROK 7, BARANGAY KAHAYAGAN, MUNICIPALITY OF BAYOG, ZAMBOANGA DEL SUR | Region IX | Zamboanga del Sur 2nd DEO | Completed | ₱9.9M | 100% | Medium risk51 | —-0.086 |
| 15 | 21JI0011CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM TRIP) NATIONAL ROAD JUNCTION LEADING TO GUINOMAN CAVE AND WATERFALLS, DIPLAHAN, ZAMBO. SIBUGAY | Region IX | Zamboanga Sibugay 1st DEO | Completed | ₱7.3M | 100% | Medium risk51 | —-0.086 |
| 16 | 23JF0017CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM - TRIP) - NRJ LEADING TO TIPAN CAVE AND WALO-BALUT CAVE BRGY. TIPAN, NAGA, ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 2nd DEO | Completed | ₱14.8M | 100% | Medium risk51 | —-0.086 |
| 17 | 21JI0096CONCRETING OF BRGY. GUINOMAN FMR, BRGY. GUINOMAN, DIPLAHAN, ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 1st DEO | Completed | ₱19.8M | 100% | Medium risk51 | —-0.035 |
| 18 | 23JG0013CONSTRUCTION OF BY-PASS AND DIVERSION ROADS ALONG POBLACION BAYOG-SALAWAGAN-DEPORE DIVERSION ROAD, BAYOG, ZAMBOANGA DEL SUR | Region IX | Zamboanga del Sur 2nd DEO | Completed | ₱4.9M | 100% | Medium risk51 | —-0.086 |
| 19 | 23JI0066CONCRETING OF BRGY. NATAN FMR, BRGY. NATAN, DIPLAHAN, ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 1st DEO | Completed | ₱14.9M | 100% | Medium risk51 | —-0.038 |
| 20 | 25JF0044CONSTRUCTION OF MULTI-PURPOSE BUILDING (SK BUILDING), BARANGAY POBLACION, NAGA, ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 2nd DEO | On-Going | ₱4.9M | 16% | Medium risk50 | —-0.024 |
| 21 | 21JF0010CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES - ROAD CONNECTING JUNCTION NATIONAL HIGHWAY AT BRGY. MIRANGAN TO BRGY. BALUCANAN IN SUPPORT OF CALAMANSI PROCESSING SIAY, ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 2nd DEO | Completed | ₱7.1M | 100% | Medium risk50 | —-0.085 |
| 22 | 21JF0104CONSTRUCTION OF LOCAL ROAD, BRGY. VETERANS, IPIL, ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 2nd DEO | Completed | ₱9.8M | 100% | Medium risk50 | —-0.086 |
| 23 | 23JI0037CONSTRUCTION OF WATER SYSTEM, BARANGAY GUINOMAN, DIPLAHAN, ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 1st DEO | Completed | ₱4.9M | 100% | Medium risk47 | —-0.045 |
| 24 | 23JI0034CONSTRUCTION OF WATER SYSTEM, BARANGAY DITAY, DIPLAHAN, ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 1st DEO | Completed | ₱4.9M | 100% | Medium risk46 | —-0.048 |
| 25 | 23JF0076CONCRETING OF BRGY. TIGPALAY FMR, BRGY. TIGPALAY, TUNGAWAN, ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 2nd DEO | Completed | ₱11.9M | 100% | Medium risk45 | —-0.032 |