Contractor dossier
84 projects on file, including joint ventures this contractor is part of.
Total projects
84
Total budget
₱5B
Average progress
88.6%
Completion rate
71.4%
Average risk score
52.6
Medium risk on average, out of 100
Flagged as unusual
2
2.4% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region IV-A | 24 | ₱1.6B | 52.7 | 0 | 90.3% |
| National Capital Region | 22 | ₱1B | 50.6 | 1 | 79.4% |
| Region III | 20 | ₱1.4B | 49.9 | 0 | 94.9% |
| Region V | 16 | ₱750.9M | 55.8 | 0 | 90.1% |
| Region VII | 2 | ₱157.7M | 75.1 | 1 | 92.3% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Flood Control and Drainage | 54 | ₱3.7B | 52.7 | 0 | 91.8% |
| Roads | 22 | ₱1B | 51.1 | 0 | 85.0% |
| Buildings and Facilities | 5 | ₱80.9M | 34.6 | 0 | 98.1% |
| GAA 2025 SSP | 2 | ₱162.4M | 94.7 | 2 | 42.9% |
| GAA 2025 OO-1 | 1 | ₱19.2M | 87.9 | 0 | 37.1% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25HO0044CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES, CONSTRUCTION OF REVETMENT WALL AT SITIO NONOK, BARANGAY MONTAÑEZA - SITIO WALO | Region VII | Cebu 7th DEO | On-Going | ₱99.8M | 85% | High risk96 | Flagged0.024 |
| 25OD0176REHABILITATION OF ROAD ALONG MAKABUD ST. AND ANAHAW ST., BARANGAY 179, CALOOCAN CITY | National Capital Region | Metro Manila 3rd DEO | On-Going | ₱62.6M | 1% | High risk94 | Flagged0.031 |
| 25OD0248REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - TERTIARY ROADS CENTRAL LUZON LEPROSARIUM RD - K0031 + (-170) - K0031 + 724 | National Capital Region | Metro Manila 3rd DEO | On-Going | ₱19.2M | 37% | High risk88 | —-0.001 |
| 24CL0137BANK IMPROVEMENT ALONG LAWIS RIVER, CANDELARIA, ZAMBALES (PHASE 2) | Region III | Zambales 1st DEO | On-Going | ₱95.5M | 99% | High risk80 | —-0.013 |
| 24CL0136BANK IMPROVEMENT ALONG LAWIS RIVER, CANDELARIA, ZAMBALES (PHASE 1) | Region III | Zambales 1st DEO | Completed | ₱95.5M | 100% | High risk80 | —-0.042 |
| 24CL0170CONSTRUCTION OF LAUIS RIVER-MASINLOC SIDE FLOOD MITIGATION STRUCTURE INCLUDING ROAD DIKE DOWNSTREAM, MASINLOC, ZAMBALES (PHASE 3) | Region III | Zambales 1st DEO | Completed | ₱95.3M | 100% | High risk80 | —-0.041 |
| 24CC0295BANK IMPROVEMENT AND REHABILITATION OF WATERWAYS, BRGY. MAMBOG, MALOLOS CITY, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱74.2M | 100% | High risk76 | —-0.061 |
| 24FD0091CLUSTER 9: REPAIR/REHABILITATION OF FLOOD CONTROL/DRAINAGE STRUCTURES,RAGAY, CAMARINES SUR | Region V | Camarines Sur 1st DEO | Completed | ₱112.9M | 100% | High risk66 | —-0.073 |
| 22DH0064BANK IMPROVEMENT ALONG PAGSANJAN RIVER, BRGY. MAGDAPIO, PAGSANJAN, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱93.6M | 100% | High risk65 | —-0.075 |
| 24OE0071CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG ESTERO DE MAYPAJO, PACKAGE I, MANILA | National Capital Region | North Manila DEO | Completed | ₱113.1M | 100% | High risk65 | —-0.075 |
| 24DF0220CONVERGENCE AND SPECIAL SUPPORT PROGRAMBASIC INFRASTRUCTURE PROGRAM (BIP)BIP - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIESCONST OF REVETMENT ALONG RIO GRANDE RIVER RIVER, BARANGAY SANTIAGO, GEN. TRIAS, CAVITE | Region IV-A | Cavite 1st DEO | On-Going | ₱99M | 70% | High risk64 | —-0.026 |
| 24D00177CONSTRUCTION OF ROAD DIKE ALONG RIO GRANDE RIVER, BARANGAY SANTIAGO, GEN. TRIAS, CAVITE (PHASE II) | Region IV-A | Region IV-A | On-Going | ₱97M | 70% | High risk64 | —-0.032 |
| 24DF0219CONVERGENCE AND SPECIAL SUPPORT PROBASIC INFRASTRUCTURE PROGRAM (BIP)BIP - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIESCONSTRUCTION OF REVETMENT ALONG YLANG-YLANG, SAN FRANCISCO, GEN. TRIAS, CAVITE (PHASE III) | Region IV-A | Cavite 1st DEO | On-Going | ₱99M | 0% | High risk64 | —-0.006 |
| 23DH0041REHABILITATION OF BANK ALONG INAWASAN RIVER, FAMY, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱98M | 100% | High risk64 | —-0.074 |
| 17FB0037LOCAL INFRASTRUCTURE PROGRAM - CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY BANQUEROHAN, LEGAZPI CITY, ALBAY 2ND LD | Region V | Albay 2nd DEO | Completed | ₱4.8M | 100% | High risk64 | —-0.065 |
| 23CL0085CONSTRUCTION OF SLOPE PROTECTION AT LAWIS RIVER, UPSTREAM, CANDELARIA, ZAMBALES (PHASE 5) | Region III | Zambales 1st DEO | On-Going | ₱98M | 100% | High risk63 | —-0.030 |
| 23CL0070CONSTRUCTION OF SLOPE PROTECTION AT PINAGREALAN, UPSTREAM, CANDELARIA, ZAMBALES (PHASE 1) | Region III | Zambales 1st DEO | Completed | ₱98M | 100% | High risk63 | —-0.071 |
| 23CL0086CONSTRUCTION OF SLOPE PROTECTION AT LAWIS RIVER, UPSTREAM, CANDELARIA, ZAMBALES (PHASE 6) | Region III | Zambales 1st DEO | On-Going | ₱98M | 100% | High risk62 | —-0.030 |
| 23CL0071CONSTRUCTION OF SLOPE PROTECTION AT PINAGREALAN, UPSTREAM, CANDELARIA, ZAMBALES (PHASE 2) | Region III | Zambales 1st DEO | Completed | ₱99M | 100% | High risk62 | —-0.069 |
| 23FD0037CONSTRUCTION OF MULTI-PURPOSE BUILDING, SIPOCOT, CAMARINES SUR | Region V | Camarines Sur 1st DEO | On-Going | ₱69.3M | 91% | High risk62 | —-0.041 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25OD0176REHABILITATION OF ROAD ALONG MAKABUD ST. AND ANAHAW ST., BARANGAY 179, CALOOCAN CITY | National Capital Region | Metro Manila 3rd DEO | On-Going | ₱62.6M | 1% | High risk94 | Flagged0.031 |
| 25HO0044CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES, CONSTRUCTION OF REVETMENT WALL AT SITIO NONOK, BARANGAY MONTAÑEZA - SITIO WALO | Region VII | Cebu 7th DEO | On-Going | ₱99.8M | 85% | High risk96 | Flagged0.024 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 76 | 22CC0249BANK IMPROVEMENT ALONG ANGAT RIVER, STA. 0+290 TO STA. 0+530, SABANG SECTION, BALIUAG, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱65.3M | 100% | Medium risk35 | —-0.089 |
| 77 | 22CC0250BANK IMPROVEMENT STA. 0+525 TO STA. 0+895, BRGY. SULIVAN, BALIUAG, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱67.6M | 100% | Medium risk34 | —-0.083 |
| 78 | 24CC0258ASSET PRESERVATION PROGRAM - CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - TERIARY ROADS - BALIWAG-CANDABA RD - K0052+(-218) - K0054+100, BALIUAG, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱39.2M | 100% | Medium risk34 | —-0.068 |
| 79 | 18CC0242CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG ANGAT RIVER DAMPOL, PLARIDEL, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱9.9M | 100% | Low risk30 | —-0.092 |
| 80 | 23CC0059CONSTRUCTION OF CONCRETE SLOPE PROTECTION AT BARANGAY PAGALA, K002+360 - K002+660, BALIUAG, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱38.6M | 100% | Low risk29 | —-0.093 |
| 81 | 23CC0060CONSTRUCTION OF CONCRETE SLOPE PROTECTION AT BARANGAY TANGOS, K002+360 - K002+960, BALIUAG, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱28.9M | 100% | Low risk29 | —-0.093 |
| 82 | 18DH0006CONSTRUCTION OF MULTI PURPOSE BUILDING, BRGY. BIÑAN, PAGSANJAN, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱2.1M | 100% | Low risk24 | —-0.105 |
| 83 | 17OA0102REPAIR/REHABILITATION OF BAGONG LIPUNAN HEALTH CENTER, NAVOTAS CITY | National Capital Region | Malabon-Navotas DEO | Completed | ₱2.3M | 100% | Low risk12 | —-0.029 |
| 84 | 17OA0093EXPANSION/REPAIR/REHABILITATION OF NORTH BAY BLVD. NORTH HC, NAV. CITY | National Capital Region | Malabon-Navotas DEO | Completed | ₱2.3M | 100% | Low risk11 | —-0.030 |