30 projects on file, including joint ventures this contractor is part of.
Total projects
30
Total budget
₱112.8M
Average progress
98.5%
Completion rate
93.3%
Average risk score
28.1
Low risk on average, out of 100
Flagged as unusual
2
6.7% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region VII | 25 | ₱97.4M | 29.7 | 2 | 98.2% |
| Negros Island Region | 5 | ₱15.4M | 20.4 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 22 | ₱78.1M | 23.7 | 0 | 98.4% |
| Roads | 6 | ₱23.2M | 26.9 | 0 | 100.0% |
| GAA 2025 SSP | 1 | ₱6.9M | 93.5 | 1 | 90.5% |
| OTHER | 1 | ₱4.7M | 67.3 | 1 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25HA0078COMPLETION OF MULTI-PURPOSE BUILDINGS (CANTAM-IS BAGO, MOTO SUR, CANSAGUIT), LOON, BOHOL | Region VII | Bohol 1st DEO | On-Going | ₱6.9M | 90% | High risk94 | Flagged0.009 |
| 24HN0230CSSP: SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF ROAD WITH DRAINAGE FACILITY, PUROK CALACHUCHI, BARANGAY CASILI, CONSOLACION, CEBU | Region VII | Cebu 6th DEO | Completed | ₱4.7M | 100% | High risk67 | Flagged0.009 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25HA0078COMPLETION OF MULTI-PURPOSE BUILDINGS (CANTAM-IS BAGO, MOTO SUR, CANSAGUIT), LOON, BOHOL | Region VII | Bohol 1st DEO | On-Going | ₱6.9M | 90% | High risk94 | Flagged0.009 |
| 24HN0230CSSP: SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF ROAD WITH DRAINAGE FACILITY, PUROK CALACHUCHI, BARANGAY CASILI, CONSOLACION, CEBU | Region VII | Cebu 6th DEO | Completed | ₱4.7M | 100% | High risk67 | Flagged0.009 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 26 | 24HA0173CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY CANSUAGUIT, LOON, BOHOL | Region VII | Bohol 1st DEO | Completed | ₱2M | 100% | Low risk15 | —-0.052 |
| 27 | 24HA0177CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, LOON TOWN SQUARE, LOON, BOHOL | Region VII | Bohol 1st DEO | On-Going | ₱3.9M | 64% | Low risk15 | —-0.002 |
| 28 | 21HA0132CONSTRUCTION/IMPROVEMENT OF MULTI-PURPOSE BUILDING, BARANGAY UBOJAN, LOON, BOHOL | Region VII | Bohol 1st DEO | Completed | ₱1.9M | 100% | Low risk13 | —-0.094 |
| 29 | 18HA0077CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BRGY. CANLAAS, ANTEQUERA, BOHOL | Region VII | Bohol 1st DEO | Completed | ₱498.7K | 100% | Low risk12 | —-0.089 |
| 30 | 21HA0160CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING IN BARANGAY DANICOP, ANTEQUERA, BOHOL | Region VII | Bohol 1st DEO | Completed | ₱493.2K | 100% | Low risk12 | —-0.089 |