Contractor dossier
150 projects on file, including joint ventures this contractor is part of.
Total projects
150
Total budget
₱5.1B
Average progress
97.1%
Completion rate
88.7%
Average risk score
48.7
Medium risk on average, out of 100
Flagged as unusual
4
2.7% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region IV-A | 117 | ₱3.3B | 49.6 | 2 | 97.1% |
| Region IV-B | 33 | ₱1.8B | 45.3 | 2 | 97.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 62 | ₱2.6B | 49.4 | 0 | 96.8% |
| Buildings and Facilities | 38 | ₱978.7M | 44.4 | 1 | 99.0% |
| Bridges | 19 | ₱313.5M | 50.6 | 0 | 94.8% |
| Flood Control and Drainage | 19 | ₱721.3M | 46.7 | 0 | 100.0% |
| Water Provision and Storage | 6 | ₱148.2M | 40.8 | 0 | 100.0% |
| OTHER | 4 | ₱236.3M | 76.7 | 2 | 84.9% |
| GAA 2025 SSP | 1 | ₱9.8M | 94.5 | 1 | 59.7% |
| Bridges, Roads | 1 | ₱66.6M | 55.0 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25DK0132CSSP - BASIC INFRASTRUCTURE PROGRAM (BIP) - BIP - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF ROAD FROM BRGY ANOS TO BRGY ILAYANG BUKAL, TAYABAS, QUEZON | Region IV-A | Quezon 1st DEO | On-Going | ₱9.8M | 60% | High risk94 | Flagged0.007 |
| 24EA0050CONSTRUCTION OF WATER SUPPLY SYSTEM (LEVEL III), BUENAVISTA, MARINDUQUE | Region IV-B | Marinduque DEO | On-Going | ₱54M | 100% | High risk79 | Flagged0.008 |
| 25EA0035LOCAL PROGRAM - NATIONAL BUILDING PROGRAM, BUILDINGS AND OTHER MULTIPURPOSE/ FACILITIES STRUCTURES, CONSTRUCTION OF DPWH BUILDING, MARINDUQUE DISTRICT ENGINEERING OFFICE, BOAC, MARINDUQUE | Region IV-B | Marinduque DEO | On-Going | ₱53.4M | 40% | High risk79 | Flagged0.012 |
| 17D00028IMPROVEMENT/WIDENING OF NATIONAL ROADS, ALONG N1, DAANG MAHARLIKA (LZ), MSR DIVERSION ROAD, S01994LZ, QUEZON | Region IV-A | Quezon 2nd DEO | Completed | ₱107.8M | 100% | High risk78 | —-0.026 |
| 16DJ0054OFF CARRIAGEWAY IMPROVEMENT INCLUDING DRAINAGE, PRIMARY ROADS, IMPROVEMENT OF INTERSECTION ALONG DAANG MAHARLIKA (LZ) S01985LZ AND LUTUCAN-GUISGUIS PORT ROAD S02003LZ INTERSECTION, K0114+380-K0114+440 SARIAYA, QUEZON | Region IV-A | Quezon 2nd DEO | Completed | ₱21.1M | 100% | High risk72 | —-0.042 |
| 16DK0114NETWORK DEV'T -IMPV'T/WIDENING OF NAT'L ROADS (N1) ALONG DAANG MAHARLIKA (LZ) K0122+098-K0123+000 | Region IV-A | Quezon 1st DEO | Completed | ₱57.9M | 100% | High risk69 | —-0.072 |
| 17DL0098A. MFO-1: NATIONAL ROAD NETWORK SERVICES 1. ASSET PRESERVATION OF NATIONAL ROADS B. REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED NATIONAL ROADS INCLUDING DRAINAGE BASED ON PAVEMENT MANAGEMENT SYSTEM/ HIGHWAY DEVELOPMENT AND MANAGEMENT - 4 | Region IV-A | Quezon 4th DEO | Completed | ₱47.9M | 100% | High risk68 | —-0.071 |
| 20DK0043CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG DUMACAA RIVER (ALONG PRINCESA BRIDGE) @ BARANGAY IBAS, TAYABAS CITY-QUEZON | Region IV-A | Quezon 1st DEO | Completed | ₱19.6M | 100% | High risk67 | —-0.060 |
| 17DL0031A. MFO -1: NATIONAL ROAD NETWORK SERVICES 2. NETWORK DEVELOPMENT A. IMPROVEMENT / WIDENING OF NATIONAL ROADS 1. PRIMARY ROADS B. OTHER PRIMARY ROADS 1. QUIRINO H-WAY - K0251+ - 511 - K0251+000, K0251+359 - K0251+600, K0251+834 - K0252+192 | Region IV-A | Quezon 4th DEO | Completed | ₱47.2M | 100% | High risk67 | —-0.071 |
| 25DK0026ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS - JCT LUCBAN-LUISIANA RD - K0130+650 - K0131+193 | Region IV-A | Quezon 1st DEO | On-Going | ₱24.2M | 60% | High risk66 | —-0.036 |
| 20DK0005NETWORK DEVELOPMENT ROAD WIDENING SECONDARY ROAD LUCENA-TAYABAS- LUCBAN-SAMPALOC-MAUBAN PORT ROAD, K0134+170-K0134+460 | Region IV-A | Quezon 1st DEO | Completed | ₱12.7M | 100% | High risk65 | —-0.074 |
| 17DM0006REHABILITATION/ RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE ALONG SN FRANCISCO-SN ANDRES-SN NARCISO RD - K0369+200 - K0370+418, K0370+592 - K0371+400 | Region IV-A | Quezon 3rd DEO | Completed | ₱27.4M | 100% | High risk64 | —-0.071 |
| 17EA0079ROAD UPGRADNG (UNPAVED TO PAVED) OF DR. DAMIAN REYES ROAD (BOAC SIDE), K0022+1092.00-K0024+013.00 | Region IV-B | Marinduque DEO | Completed | ₱48.9M | 100% | High risk63 | —-0.037 |
| 21DK0194CONSTRUCTION OF MULTI- PURPOSE BUILDING, BARANGAY LAKAWAN, TAYABAS CITY, QUEZON | Region IV-A | Quezon 1st DEO | Completed | ₱96.5M | 100% | High risk62 | —-0.082 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 22DJ0169PROPOSED CONSTRUCTION OF FOUR (4) STOREY WITH ROOF DECK DEPARTMENT OF JUSTICE BUILDING, LUCENA CITY, QUEZON | Region IV-A | Quezon 2nd DEO | On-Going | ₱57.1M | 75% | Medium risk49 | Flagged0.031 |
| 25EA0035LOCAL PROGRAM - NATIONAL BUILDING PROGRAM, BUILDINGS AND OTHER MULTIPURPOSE/ FACILITIES STRUCTURES, CONSTRUCTION OF DPWH BUILDING, MARINDUQUE DISTRICT ENGINEERING OFFICE, BOAC, MARINDUQUE | Region IV-B | Marinduque DEO | On-Going | ₱53.4M | 40% | High risk79 | Flagged0.012 |
| 24EA0050CONSTRUCTION OF WATER SUPPLY SYSTEM (LEVEL III), BUENAVISTA, MARINDUQUE | Region IV-B | Marinduque DEO | On-Going | ₱54M | 100% | High risk79 | Flagged0.008 |
| 25DK0132CSSP - BASIC INFRASTRUCTURE PROGRAM (BIP) - BIP - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF ROAD FROM BRGY ANOS TO BRGY ILAYANG BUKAL, TAYABAS, QUEZON | Region IV-A | Quezon 1st DEO | On-Going | ₱9.8M | 60% | High risk94 | Flagged0.007 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 51 | 21DL0079LOCAL PROGRAM, NATIONAL BUILDING PROGRAM, BUILDING AND OTHER STRUCTURES, MULTIPURPOSE / FACILTIES, CONSTRUCTION OF THE TECHNOLOGY AND LIVELIHOOD EDUCATION INNOVATION BUILDING - COMPLETION OF PNU SOUTH LUZON, LOPEZ, QUEZON, PHASE IV | Region IV-A | Quezon 4th DEO | Completed | ₱29M | 100% | Medium risk49 | —-0.099 |
| 52 | 21EA0052NETWORK DEVELOPMENT PROGRAM-ROAD WIDENING - SECONDARY ROADS, MARINDUQUE CIRCUMFERENTIAL RD - K0037+000- K0037+640, K0037+687-K0039+000 | Region IV-B | Marinduque DEO | Completed | ₱91.5M | 100% | Medium risk49 | —-0.077 |
| 53 | 20DK0055CONSTRUCTION OF PROTECTION WALL AT BARANGAY SADSARAN, MAUBAN, QUEZON | Region IV-A | Quezon 1st DEO | Completed | ₱49M | 100% | Medium risk49 | —-0.085 |
| 54 | 22DJ0169PROPOSED CONSTRUCTION OF FOUR (4) STOREY WITH ROOF DECK DEPARTMENT OF JUSTICE BUILDING, LUCENA CITY, QUEZON | Region IV-A | Quezon 2nd DEO | On-Going | ₱57.1M | 75% | Medium risk49 | Flagged0.031 |
| 55 | 23DM0086CONSTRUCTION OF MULTI-PURPOSE BUILDINGS, MULANAY, QUEZON | Region IV-A | Quezon 3rd DEO | Completed | ₱43.1M | 100% | Medium risk49 | —-0.096 |
| 56 | 22DL0130LOCAL PROGRAM, NATIONAL BUILDING PROGRAM, BUILDINGS AND OTHER STRUCTURES, MULTIPURPOSE / FACILITIES, CONSTRUCTION OF BUILDING, DOÑA MARTA DISTRICT HOSPITAL, ATIMONAN, QUEZON, PHASE II | Region IV-A | Quezon 4th DEO | Completed | ₱4.8M | 100% | Medium risk49 | —-0.103 |
| 57 | 23DL0077LOCAL PROGRAM, NATIONAL BUILDING PROGRAM, BUILDINGS AND OTHER STRUCTURES, MULTIPURPOSE / FACILITIES 2. CONSTRUCTION OF BUILDING, DOÑA MARTA DISTRICT HOSPITAL, ATIMONAN, QUEZON, PHASE III | Region IV-A | Quezon 4th DEO | Completed | ₱24.5M | 100% | Medium risk49 | —-0.097 |
| 58 | 24DL0158LOCAL PROGRAM, NATIONAL BUILDING PROGRAM, BUILDINGS AND OTHER STRUCTURES, MULTIPURPOSE / FACILITIES 2. CONSTRUCTION OF DOÑA MARTA DISTRICT HOSPITAL, ATIMONAN, QUEZON | Region IV-A | Quezon 4th DEO | On-Going | ₱9.8M | 96% | Medium risk48 | —-0.056 |
| 59 | 20DL0012D. LOCAL PROGRAM 1. NATIONAL BUILDING PROGRAM A. BUILDING AND OTHER STRUCTURES 1. CONSTRUCTION OF ACADEMIC BUILDING LAGUNA STATE POLYTECHNIC UNIVERSITY (LSPU), LOPEZ, QUEZON | Region IV-A | Quezon 4th DEO | Completed | ₱14.5M | 100% | Medium risk48 | —-0.101 |
| 60 | 25D00132WIDENING OF PERMANENT BRIDGES INACLAGAN BR. (B02573LZ) ALONG MAHARLIKA HIGHWAY | Region IV-A | Region IV-A | On-Going | ₱33.9M | 5% | Medium risk48 | —-0.009 |
| 61 | 21DL0078LOCAL PROGRAM, NATIONAL BUILDING PROGRAM, BUILDING AND OTHER STRUCTURES, CONSTRUCTION OF ACADEMIC BUILDING, POLYTECHNIC UNIVERSITY OF THE PHILIPPINES (PUP), LOPEZ, QUEZON, PHASE II | Region IV-A | Quezon 4th DEO | Completed | ₱19.3M | 100% | Medium risk48 | —-0.100 |
| 62 | 19DL0010I. OPERATIONS D. LOCAL PROGRAM 1. NATIONAL BUILDING PROGRAM A. BUILDING AND OTHER STRUCTURES 2. CONSTRUCTION OF ENGINEERING BUILDING POLYTECHNIC UNIVERSITY OF THE PHILIPPINES, LOPEZ, QUEZON | Region IV-A | Quezon 4th DEO | Completed | ₱19.3M | 100% | Medium risk48 | —-0.100 |
| 63 | 24EA0076CONSTRUCTION OF MULTI-PURPOSE BUILDING (AMPHITHEATER -PHASE 2) OF PULANG LUPA, BARANGAY BOLO, TORRIJOS, MARINDUQUE | Region IV-B | Marinduque DEO | On-Going | ₱67.2M | 90% | Medium risk48 | —-0.037 |
| 64 | 25DK0020ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - BRIDGE PROGRAM - RETROFITTING/ STRENGTHENING OF PERMANENT BRIDGES - ALITAO II BR. ALONG TAYABAS BYPASS RD | Region IV-A | Quezon 1st DEO | On-Going | ₱32M | 97% | Medium risk48 | —-0.038 |
| 65 | 23DM0087CONSTRUCTION OF MULTI-PURPOSE BUILDINGS, GENERAL LUNA, QUEZON | Region IV-A | Quezon 3rd DEO | Completed | ₱28.4M | 100% | Medium risk48 | —-0.098 |
| 66 | 20DL0013D. LOCAL PROGRAM 1. NATIONAL BUILDING PROGRAM A. BUILDING AND OTHER STRUCTURES 2. CONSTRUCTION OF ACADEMIC BUILDING TECHNOLOGICAL UNIVERSITY OF THE PHILIPPINES (TUP), LOPEZ, QUEZON | Region IV-A | Quezon 4th DEO | Completed | ₱14.5M | 100% | Medium risk47 | —-0.101 |
| 67 | 22DK0175CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY CALUMPANG, TAYABAS CITY, QUEZON | Region IV-A | Quezon 1st DEO | Completed | ₱4.9M | 100% | Medium risk47 | —-0.105 |
| 68 | 19DJ0055OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, BRIDGE PROGRAM, RETROFITTING/STRENGTHENING OF PERMANENT BRIDGES, LALIG BR. (B04793LZ) ALONG TIAONG BYPASS RD. TIAONG, QUEZON PROVINCE | Region IV-A | Quezon 2nd DEO | Completed | ₱14.8M | 100% | Medium risk47 | —-0.069 |
| 69 | 23DL0018CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES 1. CONSTRUCTION OF ALIJI - MAHINTA BRIDGE | Region IV-A | Quezon 4th DEO | Completed | ₱14.7M | 100% | Medium risk47 | —-0.064 |
| 70 | 23DL0019CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES 2. CONSTRUCTION OF ALIJI BRIDGE AND APPROAC | Region IV-A | Quezon 4th DEO | Completed | ₱14.7M | 100% | Medium risk47 | —-0.064 |
| 71 | 19DK0031CONSTRUCTION OF BYPASS AND DIVERSION ROAD MAUBAN BYPASS PACKAGE B MAUBAN, QUEZON | Region IV-A | Quezon 1st DEO | Completed | ₱42.9M | 100% | Medium risk47 | —-0.105 |
| 72 | 18DK0106CONSTRUCTION OF WATER SYSTEM BARANGAY MALAOA, TAYABAS CITY-QUEZON | Region IV-A | Quezon 1st DEO | Completed | ₱19.8M | 100% | Medium risk47 | —-0.071 |
| 73 | 22DM0132BRIDGE PROGRAM - WIDENING OF PERMANENT BRIDGES - BALSAHAN BR. (B01858LZ) ALONG SN FRANCISCO-SN ANDRES-SN NARCISO RDSAN FRANCISCO, QUEZON | Region IV-A | Quezon 3rd DEO | Completed | ₱14.7M | 100% | Medium risk47 | —-0.064 |
| 74 | 22DK0085ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - PAGBILAO-TAYABAS-LUCBAN, DIVERSION ROAD QUEZON (LUCBAN SIDE) - PACKAGE B | Region IV-A | Quezon 1st DEO | Completed | ₱39.2M | 100% | Medium risk47 | —-0.103 |
| 75 | 23DK0011ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT - ROAD WIDENING - SECONDARY ROADS - LUCENA - TAYABAS - LUCBAN - SAMPALOC - MAUBAN PORT RD - K0129+(-302) - K0129+040 | Region IV-A | Quezon 1st DEO | Completed | ₱29.4M | 100% | Medium risk47 | —-0.109 |