Contractor dossier
150 projects on file, including joint ventures this contractor is part of.
Total projects
150
Total budget
₱5.1B
Average progress
97.1%
Completion rate
88.7%
Average risk score
48.7
Medium risk on average, out of 100
Flagged as unusual
4
2.7% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region IV-A | 117 | ₱3.3B | 49.6 | 2 | 97.1% |
| Region IV-B | 33 | ₱1.8B | 45.3 | 2 | 97.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 62 | ₱2.6B | 49.4 | 0 | 96.8% |
| Buildings and Facilities | 38 | ₱978.7M | 44.4 | 1 | 99.0% |
| Bridges | 19 | ₱313.5M | 50.6 | 0 | 94.8% |
| Flood Control and Drainage | 19 | ₱721.3M | 46.7 | 0 | 100.0% |
| Water Provision and Storage | 6 | ₱148.2M | 40.8 | 0 | 100.0% |
| OTHER | 4 | ₱236.3M | 76.7 | 2 | 84.9% |
| GAA 2025 SSP | 1 | ₱9.8M | 94.5 | 1 | 59.7% |
| Bridges, Roads | 1 | ₱66.6M | 55.0 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25DK0132CSSP - BASIC INFRASTRUCTURE PROGRAM (BIP) - BIP - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF ROAD FROM BRGY ANOS TO BRGY ILAYANG BUKAL, TAYABAS, QUEZON | Region IV-A | Quezon 1st DEO | On-Going | ₱9.8M | 60% | High risk94 | Flagged0.007 |
| 24EA0050CONSTRUCTION OF WATER SUPPLY SYSTEM (LEVEL III), BUENAVISTA, MARINDUQUE | Region IV-B | Marinduque DEO | On-Going | ₱54M | 100% | High risk79 | Flagged0.008 |
| 25EA0035LOCAL PROGRAM - NATIONAL BUILDING PROGRAM, BUILDINGS AND OTHER MULTIPURPOSE/ FACILITIES STRUCTURES, CONSTRUCTION OF DPWH BUILDING, MARINDUQUE DISTRICT ENGINEERING OFFICE, BOAC, MARINDUQUE | Region IV-B | Marinduque DEO | On-Going | ₱53.4M | 40% | High risk79 | Flagged0.012 |
| 17D00028IMPROVEMENT/WIDENING OF NATIONAL ROADS, ALONG N1, DAANG MAHARLIKA (LZ), MSR DIVERSION ROAD, S01994LZ, QUEZON | Region IV-A | Quezon 2nd DEO | Completed | ₱107.8M | 100% | High risk78 | —-0.026 |
| 16DJ0054OFF CARRIAGEWAY IMPROVEMENT INCLUDING DRAINAGE, PRIMARY ROADS, IMPROVEMENT OF INTERSECTION ALONG DAANG MAHARLIKA (LZ) S01985LZ AND LUTUCAN-GUISGUIS PORT ROAD S02003LZ INTERSECTION, K0114+380-K0114+440 SARIAYA, QUEZON | Region IV-A | Quezon 2nd DEO | Completed | ₱21.1M | 100% | High risk72 | —-0.042 |
| 16DK0114NETWORK DEV'T -IMPV'T/WIDENING OF NAT'L ROADS (N1) ALONG DAANG MAHARLIKA (LZ) K0122+098-K0123+000 | Region IV-A | Quezon 1st DEO | Completed | ₱57.9M | 100% | High risk69 | —-0.072 |
| 17DL0098A. MFO-1: NATIONAL ROAD NETWORK SERVICES 1. ASSET PRESERVATION OF NATIONAL ROADS B. REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED NATIONAL ROADS INCLUDING DRAINAGE BASED ON PAVEMENT MANAGEMENT SYSTEM/ HIGHWAY DEVELOPMENT AND MANAGEMENT - 4 | Region IV-A | Quezon 4th DEO | Completed | ₱47.9M | 100% | High risk68 | —-0.071 |
| 20DK0043CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG DUMACAA RIVER (ALONG PRINCESA BRIDGE) @ BARANGAY IBAS, TAYABAS CITY-QUEZON | Region IV-A | Quezon 1st DEO | Completed | ₱19.6M | 100% | High risk67 | —-0.060 |
| 17DL0031A. MFO -1: NATIONAL ROAD NETWORK SERVICES 2. NETWORK DEVELOPMENT A. IMPROVEMENT / WIDENING OF NATIONAL ROADS 1. PRIMARY ROADS B. OTHER PRIMARY ROADS 1. QUIRINO H-WAY - K0251+ - 511 - K0251+000, K0251+359 - K0251+600, K0251+834 - K0252+192 | Region IV-A | Quezon 4th DEO | Completed | ₱47.2M | 100% | High risk67 | —-0.071 |
| 25DK0026ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS - JCT LUCBAN-LUISIANA RD - K0130+650 - K0131+193 | Region IV-A | Quezon 1st DEO | On-Going | ₱24.2M | 60% | High risk66 | —-0.036 |
| 20DK0005NETWORK DEVELOPMENT ROAD WIDENING SECONDARY ROAD LUCENA-TAYABAS- LUCBAN-SAMPALOC-MAUBAN PORT ROAD, K0134+170-K0134+460 | Region IV-A | Quezon 1st DEO | Completed | ₱12.7M | 100% | High risk65 | —-0.074 |
| 17DM0006REHABILITATION/ RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE ALONG SN FRANCISCO-SN ANDRES-SN NARCISO RD - K0369+200 - K0370+418, K0370+592 - K0371+400 | Region IV-A | Quezon 3rd DEO | Completed | ₱27.4M | 100% | High risk64 | —-0.071 |
| 17EA0079ROAD UPGRADNG (UNPAVED TO PAVED) OF DR. DAMIAN REYES ROAD (BOAC SIDE), K0022+1092.00-K0024+013.00 | Region IV-B | Marinduque DEO | Completed | ₱48.9M | 100% | High risk63 | —-0.037 |
| 21DK0194CONSTRUCTION OF MULTI- PURPOSE BUILDING, BARANGAY LAKAWAN, TAYABAS CITY, QUEZON | Region IV-A | Quezon 1st DEO | Completed | ₱96.5M | 100% | High risk62 | —-0.082 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 22DJ0169PROPOSED CONSTRUCTION OF FOUR (4) STOREY WITH ROOF DECK DEPARTMENT OF JUSTICE BUILDING, LUCENA CITY, QUEZON | Region IV-A | Quezon 2nd DEO | On-Going | ₱57.1M | 75% | Medium risk49 | Flagged0.031 |
| 25EA0035LOCAL PROGRAM - NATIONAL BUILDING PROGRAM, BUILDINGS AND OTHER MULTIPURPOSE/ FACILITIES STRUCTURES, CONSTRUCTION OF DPWH BUILDING, MARINDUQUE DISTRICT ENGINEERING OFFICE, BOAC, MARINDUQUE | Region IV-B | Marinduque DEO | On-Going | ₱53.4M | 40% | High risk79 | Flagged0.012 |
| 24EA0050CONSTRUCTION OF WATER SUPPLY SYSTEM (LEVEL III), BUENAVISTA, MARINDUQUE | Region IV-B | Marinduque DEO | On-Going | ₱54M | 100% | High risk79 | Flagged0.008 |
| 25DK0132CSSP - BASIC INFRASTRUCTURE PROGRAM (BIP) - BIP - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF ROAD FROM BRGY ANOS TO BRGY ILAYANG BUKAL, TAYABAS, QUEZON | Region IV-A | Quezon 1st DEO | On-Going | ₱9.8M | 60% | High risk94 | Flagged0.007 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 76 | 20DL0014D. LOCAL PROGRAM 1. NATIONAL BUILDING PROGRAM A. BUILDING AND OTHER STRUCTURES 3. CONSTRUCTION OF ACADEMIC BUILDING SOUTHERN LUZON STATE UNIVERSITY (SLSU), CALAUAG, QUEZON | Region IV-A | Quezon 4th DEO | Completed | ₱14.5M | 100% | Medium risk47 | —-0.101 |
| 77 | 23EA0024ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS, MARINDUQUE CIRCUMFERENTIAL RD-K0024+000 - K0026+000 | Region IV-B | Marinduque DEO | Completed | ₱67.2M | 100% | Medium risk47 | —-0.085 |
| 78 | 22DM0069BRIDGE: RETROFITTING/ STRENGTHENING OF PERMANENT BRIDGES - TAYUMAN BRIDGE (B02973LZ), ALONG MULANAY - SAN FRANCISCO ROAD, SAN FRANCISCO, QUEZON | Region IV-A | Quezon 3rd DEO | Completed | ₱9.8M | 100% | Medium risk47 | —-0.063 |
| 79 | 23DM0101CONSTRUCTION OF PUBLIC WATER SUPPLY SYSTEM LEVEL III, (POBLACION), SAN NARCISO, QUEZON | Region IV-A | Quezon 3rd DEO | Completed | ₱19.6M | 100% | Medium risk47 | —-0.061 |
| 80 | 23DM0110CONSTRUCTION OF PUBLIC WATER SUPPLY SYSTEM LEVEL III, BARANGAY POBLACION, SAN ANDRES, QUEZON | Region IV-A | Quezon 3rd DEO | Completed | ₱19.6M | 100% | Medium risk47 | —-0.067 |
| 81 | 24D00127CONSTRUCTION OF BY-PASS AND DIVERSION ROADS PAGBILAO - TAYABAS - LUCBAN DIVERSION ROAD (PAGBILAO SIDE), QUEZON | Region IV-A | Region IV-A | On-Going | ₱42.6M | 64% | Medium risk47 | —-0.058 |
| 82 | 23DK0002OO1-ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-ROAD WIDENING-SECONDARY ROADS-TAYABAS-MAINIT-MAUBAN RD-K0141+500-K0142+586,K0145+506-K0146+000 | Region IV-A | Quezon 1st DEO | Completed | ₱29.4M | 100% | Medium risk47 | —-0.097 |
| 83 | 23DM0014ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS - PADRE BURGOS - POTOTANIN JCT. ROAD - K0188+094 - K0190+794, UNISAN, QUEZON | Region IV-A | Quezon 3rd DEO | Completed | ₱35.7M | 100% | Medium risk47 | —-0.102 |
| 84 | 23DM0072CONSTRUCTION OF MULTI-PURPOSE BUILDING (PUBLIC MARKET) PHASE 2, GENERAL LUNA, QUEZON | Region IV-A | Quezon 3rd DEO | Completed | ₱19.6M | 100% | Medium risk47 | —-0.100 |
| 85 | 25EA0007NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - SECONDARY ROADS, MARINDUQUE CIRCUMFERENTIAL ROAD-K0074+000-K0075+130, K0075+320 - K0076+000 | Region IV-B | Marinduque DEO | On-Going | ₱87.6M | 85% | Medium risk47 | —-0.059 |
| 86 | 22EA0234CONSTRUCTION OF LAPU-LAPU BUYABOD COASTAL ROAD LEADING TO BALUARTE WATCHTOWER, STA. CRUZ, MARINDUQUE | Region IV-B | Marinduque DEO | Completed | ₱65.6M | 100% | Medium risk47 | —-0.087 |
| 87 | 18DK0024CONSTRUCTION AND MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINGAE SYSTEM-CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG ILOG RIVER, LUCBAN, QUEZON | Region IV-A | Quezon 1st DEO | Completed | ₱39.2M | 100% | Medium risk47 | —-0.088 |
| 88 | 24D00066CONSTRUCTION OF MISSING LINKS/ NEW ROADS MAUBAN-TIGNOAN ROAD (MAUBAN SIDE), QUEZON | Region IV-A | Region IV-A | On-Going | ₱28.4M | 71% | Medium risk47 | —-0.060 |
| 89 | 20DK0023CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG AGOS RIVER CONTROL, INFANTA, QUEZON (PACKAGE B) | Region IV-A | Quezon 1st DEO | Completed | ₱38.6M | 100% | Medium risk46 | —-0.086 |
| 90 | 20DK0117CONSTRUCTION OF MAAPON RIVER FLOOD CONTROL, SAMPALOC, QUEZON | Region IV-A | Quezon 1st DEO | Completed | ₱40.2M | 100% | Medium risk46 | —-0.087 |
| 91 | 25DK0028CSSP - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - SIPAG - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF SEAWALL AT BARANGAY POBLACION, REAL, QUEZON | Region IV-A | Quezon 1st DEO | On-Going | ₱9.7M | 100% | Medium risk46 | —-0.057 |
| 92 | 18DK0026CONSTRUCTION AND MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG CAMATIAN RIVER, LUCBAN, QUEZON | Region IV-A | Quezon 1st DEO | Completed | ₱24.5M | 100% | Medium risk46 | —-0.089 |
| 93 | 21DK0083CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG DUMACAA RIVER (NEAR MALAGONLONG BRIDGE) BARANGAY LAKAWAN, TAYABAS CITY-QUEZON | Region IV-A | Quezon 1st DEO | Completed | ₱19.6M | 100% | Medium risk46 | —-0.089 |
| 94 | 21DL0054ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF BREAKWATER, TAGKAWAYAN, QUEZON | Region IV-A | Quezon 4th DEO | Completed | ₱37.8M | 100% | Medium risk46 | —-0.085 |
| 95 | 24EA0078CONSTRUCTION OF MULTI-PURPOSE BUILDING (AMPHITHEATER), BRGY. BOLO, TORRIJOS, MARINDUQUE (PHASE II) | Region IV-B | Marinduque DEO | Completed | ₱58.2M | 100% | Medium risk46 | —-0.077 |
| 96 | 18DK0049NETWORK DEVELOPMENT -ROAD WIDENING PRIMARY ROADS (P00201249LZ) DAANG K0123+862-K0124+652, TAYABAS CITY-QUEZON | Region IV-A | Quezon 1st DEO | Completed | ₱24.5M | 100% | Medium risk46 | —-0.109 |
| 97 | 23DK0015ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT - OFF-CARRIAGEWAY IMPROVEMENT - SECONDARY ROADS - JCT LUCBAN-LUISIANA RD - K0132+358 - K0132+748 | Region IV-A | Quezon 1st DEO | Completed | ₱16.3M | 100% | Medium risk46 | —-0.102 |
| 98 | 20DK0002CONSRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL PRIMARY ROADS MSR DIVERSION ROAD, K0125+440-K0126+000 | Region IV-A | Quezon 1st DEO | Completed | ₱14.7M | 100% | Medium risk46 | —-0.109 |
| 99 | 22DK0058ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM ASSET PRESERVATION PROGRAM REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - SECONDARY ROADS JCT LUCBAN-LUISIANA RD - K0133 + 307 - K0133 + 567.80 | Region IV-A | Quezon 1st DEO | Completed | ₱14.7M | 100% | Medium risk46 | —-0.110 |
| 100 | 21DK0053CONSTRUCTION OF BYPASS AND DIVERSION ROADS MAUBAN BYPASS ROAD, PACKAGE D, QUEZON, MAUBAN, QUEZON | Region IV-A | Quezon 1st DEO | Completed | ₱22.1M | 100% | Medium risk46 | —-0.108 |