Contractor dossier
474 projects on file, including joint ventures this contractor is part of.
Total projects
474
Total budget
₱11.2B
Average progress
97.4%
Completion rate
83.8%
Average risk score
45.1
Medium risk on average, out of 100
Flagged as unusual
44
9.3% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region II | 474 | ₱11.2B | 45.1 | 44 | 97.4% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 203 | ₱2.7B | 40.3 | 6 | 98.3% |
| Buildings and Facilities | 98 | ₱910.4M | 37.7 | 1 | 99.4% |
| Flood Control and Drainage | 75 | ₱3.7B | 48.4 | 0 | 99.9% |
| Bridges | 33 | ₱581.1M | 42.5 | 1 | 99.7% |
| Water Provision and Storage | 24 | ₱179M | 39.2 | 0 | 100.0% |
| OTHER | 17 | ₱1.2B | 75.3 | 14 | 91.1% |
| GAA 2025 SSP | 15 | ₱250.3M | 95.9 | 15 | 69.7% |
| GAA 2025 OO-2 | 7 | ₱753.1M | 93.0 | 5 | 78.0% |
| GAA 2025 OO-1 | 1 | ₱253.5M | 95.1 | 1 | 46.0% |
| Bridges, Roads | 1 | ₱714M | 63.0 | 1 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25BE0118CONVERGENCE AND SPECIAL SUPPORT PROGRAM- BASIC INFRASTRUTURE PROGRAM (BIP) - BIP - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG CAGAYAN RIVER, PHASE 4, BARANGAY NGAR | Region II | Isabela 1st DEO | On-Going | ₱43.2M | 38% | High risk96 | Flagged0.027 |
| 25BE0040CONVERGENCE AND SPECIAL SUPPORT PROGRAM- BASIC INFRASTRUCTURE PROGRAM (BIP)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-REHABILITATION OF ROAD LEADING TO CABAGAN SCIENCE ELEMENTARY SCHOOL, BA | Region II | Isabela 1st DEO | On-Going | ₱29.7M | 87% | High risk96 | Flagged0.012 |
| 25BE0077CONVERGENCE AND SPECIAL SUPPORT PROGRAM- BASIC INFRASTRUTURE PROGRAM (BIP) - BIP - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - REHABILITATION OF ROAD, BARANGAY PILIG ABAJO, CABAGAN, ISABELA | Region II | Isabela 1st DEO | On-Going | ₱4.8M | 80% | High risk96 | Flagged0.012 |
| 25BE0059CONVERGENCE AND SPECIAL SUPPORT PROGRAM- BASIC INFRASTRUTURE PROGRAM (BIP) - BIP - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, MOZZOZZIN ELEMENTARY SCHOOL, BARANGAY MOZZOZZIN SUR, SANTA MARIA, IS | Region II | Isabela 1st DEO | On-Going | ₱9.6M | 53% | High risk96 | Flagged0.023 |
| 25BE0058CONVERGENCE AND SPECIAL SUPPORT PROGRAM- BASIC INFRASTRUTURE PROGRAM (BIP) - BIP - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, SANTA MARIA CENTRAL ELEMENTARY SCHOOL, BARANGAY POBLACION I, SANTA | Region II | Isabela 1st DEO | On-Going | ₱9.6M | 53% | High risk96 | Flagged0.023 |
| 25BE0073CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUTURE PROGRAM (BIP)-BIP- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF ROAD ALONG BARANGAY BOLINAO-CULALABO (JUNCTION GARDE | Region II | Isabela 1st DEO | On-Going | ₱19.2M | 96% | High risk96 | Flagged0.008 |
| 25BE0057CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUTURE PROGRAM (BIP) - BIP - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING BARANGAY POBLACION, SAN PABLO, ISABELA | Region II | Isabela 1st DEO | On-Going | ₱19.2M | 52% | High risk96 | Flagged0.024 |
| 25BE0068CONVERGENCE AND SPECIAL SUPPORT PROGRAM- BASIC INFRASTRUTURE PROGRAM (BIP) - BIP - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, BARANGAY SIMANU SUR, SAN PABLO, ISABELA | Region II | Isabela 1st DEO | On-Going | ₱9.6M | 100% | High risk96 | Flagged0.004 |
| 25BE0110CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION / REHABILITATION OF WATER SUPPLY / SEPTAGE AND SEWERAGE / RAIN WATER COLLECTORS- WATER SUPPLY SYSTEM - CONSTRUCTION OF WATER SUPPLY SYSTEM AT BARANGAY SAN ROQUE, SANTO TOMAS, ISABELA | Region II | Isabela 1st DEO | On-Going | ₱4.8M | 81% | High risk96 | Flagged0.012 |
| 25BE0096CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUTURE PROGRAM (BIP) - BIP -EVACUATION CENTERS / QUARANTINE FACILITIES / PUBLIC HEALTH FACILITIES - CONSTRUCTION OF MULTI-PURPOSE BUILDING (EVACUATION CENTER), BARANGAY POBLACION, SAN PABLO, ISABELA | Region II | Isabela 1st DEO | On-Going | ₱14.4M | 49% | High risk96 | Flagged0.024 |
| 25BE0099CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUTURE PROGRAM (BIP) - BIP - EVACUATION CENTERS / QUARANTINE FACILITIES/PUBLIC HEALTH FACILITIES - CONSTRUCTION OF MULTI-PURPOSE BUILDING (EVACUATION CENTER), BARANGAY CARALUCUD, SAN PABLO, ISABELA | Region II | Isabela 1st DEO | On-Going | ₱14.4M | 67% | High risk96 | Flagged0.020 |
| 25BE0128CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUTURE PROGRAM (BIP) - BIP - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES -CONSTRUCTION OF SLOPE PROTECTION AND CROSS DRAIN ALONG BAGABAG CREEK, STO. TOMAS, ISABE | Region II | Isabela 1st DEO | On-Going | ₱14.4M | 60% | High risk96 | Flagged0.022 |
| 25BE0091CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUTURE PROGRAM (BIP) - BIP - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG CAGAYAN RIVER, PHASE 5, BARANGAY MALA | Region II | Isabela 1st DEO | On-Going | ₱38.4M | 50% | High risk96 | Flagged0.024 |
| 25BE0069CONVERGENCE AND SPECIAL SUPPORT PROGRAM- SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF CONCRETE ROAD AT SI | Region II | Isabela 1st DEO | On-Going | ₱14.3M | 90% | High risk95 | Flagged0.008 |
| 25B00047OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: BRIDGE PROGRAM - WIDENING OF PERMANENT BRIDGES - MALALAM BR. (B01121LZ) ALONG MAHARLIKA HIGHWAY | Region II | Region II | On-Going | ₱253.5M | 46% | High risk95 | Flagged0.038 |
| 25BE0109CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION / REHABILITATION OF WATER SUPPLY / SEPTAGE AND SEWERAGE / RAIN WATER COLLECTORS - WATER SUPPLY SYSTEM - CONSTRUCTION OF WATER SUPPLY SYSTEM AT BARANGAY BALELLENG, SANTO TOMAS, ISABELA | Region II | Isabela 1st DEO | On-Going | ₱4.8M | 90% | High risk94 | Flagged0.008 |
| 25BE0090ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF SLOPE PROTECTION STRUCTUR | Region II | Isabela 1st DEO | On-Going | ₱93.6M | 42% | High risk93 | Flagged0.011 |
| 25BE0081ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS- FLOOD MANAGEMENT PROGRAM- CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONSTRUCTION OF FLOOD MITIGATION STRUCTURE | Region II | Isabela 1st DEO | On-Going | ₱93.6M | 96% | High risk93 | —-0.000 |
| 25BE0079ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD MITIGATION STRUCTURE AL | Region II | Isabela 1st DEO | On-Going | ₱93.6M | 93% | High risk93 | —-0.000 |
| 25BE0041ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION / REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONSTRUCTION OF FLOOD MITIGATION STRUCTURE AL | Region II | Isabela 1st DEO | On-Going | ₱96.5M | 92% | High risk93 | Flagged0.001 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 20B00028ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT: CONSTRUCTION OF BY-PASS ROAD, PACKAGE 2, ISABELA (GOV. DY BRIDGE) | Region II | Region II | On-Going | ₱579.2M | 84% | High risk83 | Flagged0.062 |
| 25BE0130CONCRETING OF RODEO ARENA POBLACION-SITIO ANTAGAN FMR, BRGY. POBLACION AND BRGY. DALENA, SAN PABLO, ISABELA | Region II | Isabela 1st DEO | On-Going | ₱14.5M | 53% | High risk87 | Flagged0.060 |
| 25BE0101CONCRETING OF BRGY. CALANIGAN NORTE FMR, BRGY. CALANIGAN NORTE, STO. TOMAS, ISABELA | Region II | Isabela 1st DEO | On-Going | ₱14.5M | 75% | High risk87 | Flagged0.052 |
| 25BE0100CONCRETING OF SITIO VILLA-SITIO COLUNGUAN FMR, BRGY. BARUMBONG, STO. TOMAS, ISABELA | Region II | Isabela 1st DEO | On-Going | ₱14.5M | 81% | High risk87 | Flagged0.050 |
| 25BE0085CONCRETING OF BRGY. PILIG ALTO FMR, BRGY. PILIG ALTO, CABAGAN, ISABELA | Region II | Isabela 1st DEO | On-Going | ₱19.3M | 89% | High risk87 | Flagged0.048 |
| 25BE0082CONCRETING OF MALASI-SAN ANTONIO FMR, BRGY. SITIO MALASI, BRGY. SAN ANTONIO, CABAGAN, ISABELA | Region II | Isabela 1st DEO | On-Going | ₱14.5M | 85% | High risk88 | Flagged0.047 |
| 25BE0103CONSTRUCTION OF SCHOOL BUILDING, MANGCURAM ELEMENTARY SCHOOL, ILAGAN CITY, ISABELA | Region II | Isabela 1st DEO | On-Going | ₱9.7M | 91% | High risk87 | Flagged0.046 |
| 25BE0083CONCRETING OF BRGY. TALLAG PROPER-SITIO PUNTA FMR, BRGY. TALLAG, CABAGAN, ISABELA | Region II | Isabela 1st DEO | On-Going | ₱29M | 50% | High risk61 | Flagged0.039 |
| 25B00047OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: BRIDGE PROGRAM - WIDENING OF PERMANENT BRIDGES - MALALAM BR. (B01121LZ) ALONG MAHARLIKA HIGHWAY | Region II | Region II | On-Going | ₱253.5M | 46% | High risk95 | Flagged0.038 |
| 24B00100CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ILAGAN-DIVILACAN ROAD, IL | Region II | Region II | On-Going | ₱192.8M | 92% | High risk83 | Flagged0.030 |
| 25BE0118CONVERGENCE AND SPECIAL SUPPORT PROGRAM- BASIC INFRASTRUTURE PROGRAM (BIP) - BIP - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG CAGAYAN RIVER, PHASE 4, BARANGAY NGAR | Region II | Isabela 1st DEO | On-Going | ₱43.2M | 38% | High risk96 | Flagged0.027 |
| 25BE0091CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUTURE PROGRAM (BIP) - BIP - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG CAGAYAN RIVER, PHASE 5, BARANGAY MALA | Region II | Isabela 1st DEO | On-Going | ₱38.4M | 50% | High risk96 | Flagged0.024 |
| 25BE0057CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUTURE PROGRAM (BIP) - BIP - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING BARANGAY POBLACION, SAN PABLO, ISABELA | Region II | Isabela 1st DEO | On-Going | ₱19.2M | 52% | High risk96 | Flagged0.024 |
| 25BE0096CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUTURE PROGRAM (BIP) - BIP -EVACUATION CENTERS / QUARANTINE FACILITIES / PUBLIC HEALTH FACILITIES - CONSTRUCTION OF MULTI-PURPOSE BUILDING (EVACUATION CENTER), BARANGAY POBLACION, SAN PABLO, ISABELA | Region II | Isabela 1st DEO | On-Going | ₱14.4M | 49% | High risk96 | Flagged0.024 |
| 25BE0059CONVERGENCE AND SPECIAL SUPPORT PROGRAM- BASIC INFRASTRUTURE PROGRAM (BIP) - BIP - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, MOZZOZZIN ELEMENTARY SCHOOL, BARANGAY MOZZOZZIN SUR, SANTA MARIA, IS | Region II | Isabela 1st DEO | On-Going | ₱9.6M | 53% | High risk96 | Flagged0.023 |
| 25BE0058CONVERGENCE AND SPECIAL SUPPORT PROGRAM- BASIC INFRASTRUTURE PROGRAM (BIP) - BIP - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, SANTA MARIA CENTRAL ELEMENTARY SCHOOL, BARANGAY POBLACION I, SANTA | Region II | Isabela 1st DEO | On-Going | ₱9.6M | 53% | High risk96 | Flagged0.023 |
| 25BE0128CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUTURE PROGRAM (BIP) - BIP - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES -CONSTRUCTION OF SLOPE PROTECTION AND CROSS DRAIN ALONG BAGABAG CREEK, STO. TOMAS, ISABE | Region II | Isabela 1st DEO | On-Going | ₱14.4M | 60% | High risk96 | Flagged0.022 |
| 25BE0099CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUTURE PROGRAM (BIP) - BIP - EVACUATION CENTERS / QUARANTINE FACILITIES/PUBLIC HEALTH FACILITIES - CONSTRUCTION OF MULTI-PURPOSE BUILDING (EVACUATION CENTER), BARANGAY CARALUCUD, SAN PABLO, ISABELA | Region II | Isabela 1st DEO | On-Going | ₱14.4M | 67% | High risk96 | Flagged0.020 |
| 19BE0149REPAIR AND MAINTENANCE OF CONCRETE PAVEMENT ALONG ILAGAN-BIGAO-PALANAN ROAD KO420+400-KO420+500 VILLA IMELDA, CITY OF ILAGAN, ISABELA | Region II | Isabela 1st DEO | Completed | ₱18.3M | 100% | High risk82 | Flagged0.020 |
| 19BE0154REPAIR AND MAINTENANCE OF NAGAPPAGAN BRIDGE APPROACH SLOPE PROTECTION CITY OF ILAGAN, ISABELA | Region II | Isabela 1st DEO | Completed | ₱9M | 100% | High risk86 | Flagged0.018 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 51 | 20B00010OO 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS-RIVER BANK PROTECTION FOR LOWER CAGAYAN RIVER, TUMAUINI, ISABELA (UPSTREAM) | Region II | Region II | Completed | ₱100.9M | 100% | High risk62 | —-0.046 |
| 52 | 23BE0052ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOOD-FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD MITIGATION STRUCTURE AL | Region II | Isabela 1st DEO | On-Going | ₱96.2M | 99% | High risk62 | —-0.012 |
| 53 | 23BE0075ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOOD-FLOOD MANAGEMENT PROGRAM- CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD MITIGATION STRUCTURE AL | Region II | Isabela 1st DEO | On-Going | ₱96.2M | 99% | High risk62 | —-0.013 |
| 54 | 23BE0049ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOOD-FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD MITIGATION STRUCTURE AL | Region II | Isabela 1st DEO | Completed | ₱96.2M | 100% | High risk62 | —-0.053 |
| 55 | 23BE0062ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOOD-FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD MITIGATION STRUCTURE AL | Region II | Isabela 1st DEO | Completed | ₱96.2M | 100% | High risk62 | —-0.053 |
| 56 | 23BE0050ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOOD-FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD MITIGATION STRUCTURE AL | Region II | Isabela 1st DEO | Completed | ₱96.2M | 100% | High risk62 | —-0.052 |
| 57 | 25BE0023ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS- FLOOD MANAGEMENT PROGRAM- CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONSTRUCTION OF FLOOD MITIGATION STRUCTURE | Region II | Isabela 1st DEO | Completed | ₱96.5M | 100% | High risk62 | —-0.053 |
| 58 | 24BE0097ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION / REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD MITIGATION STRUCTU | Region II | Isabela 1st DEO | Completed | ₱96.5M | 100% | High risk62 | —-0.054 |
| 59 | 25BE0025CONVERGENCE AND SPECIAL SUPPORT PROGRAM- SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES- CONSTRUCTION OF ILAGAN-DIVILACAN ROAD, P | Region II | Isabela 1st DEO | On-Going | ₱144.7M | 84% | High risk62 | —-0.033 |
| 60 | 25BE0026CONVERGENCE AND SPECIAL SUPPORT PROGRAM -SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES -CONSTRUCTION OF ILAGAN-DIVILACAN ROAD, P | Region II | Isabela 1st DEO | On-Going | ₱144.7M | 84% | High risk61 | —-0.033 |
| 61 | 25BE0083CONCRETING OF BRGY. TALLAG PROPER-SITIO PUNTA FMR, BRGY. TALLAG, CABAGAN, ISABELA | Region II | Isabela 1st DEO | On-Going | ₱29M | 50% | High risk61 | Flagged0.039 |
| 62 | 21B00063LOCAL PROGRAM-LOCAL ROADS AND BRIDGES - LOCAL ROADS-CONSTRUCTION/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS: CONSTRUCTION OF CONCRETE ROAD INCLUDING SLOPE PROTECTION ILAGAN-DIVILACAN-PALANAN-SAN MARIANO DINAPIGUR ROAD | Region II | Region II | Completed | ₱96.2M | 100% | Medium risk58 | —-0.062 |
| 63 | 25B00027OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - ILAGAN CITY BYPASS ROAD, ISABELA | Region II | Region II | On-Going | ₱115.2M | 50% | Medium risk58 | —-0.031 |
| 64 | 24B00026OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - ILAGAN CITY BYPASS ROAD, ISABELA | Region II | Region II | Completed | ₱101.2M | 100% | Medium risk57 | —-0.066 |
| 65 | 20BG0131LOCAL INFRASTRUCTURE PROGRAM - BUILDING AND OTHER STRUCTURE - MULTIPURPOSE/FACILITIES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY NAPACCU PEQUENO, REINA MERCEDES, ISABELA | Region II | Isabela 3rd DEO | Completed | ₱68.5M | 100% | Medium risk56 | —-0.059 |
| 66 | 24B00034OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT - CONSTRUCTION OF MISSING LINKS/ NEW ROADS - JCT. DELFIN ALBANO ROAD INCLUDING BRIDGE (CANSAN - BAGUTARI BRIDGE) | Region II | Region II | On-Going | ₱90.4M | 98% | Medium risk55 | —-0.039 |
| 67 | 19BE0151REPAIR AND MAINTENANCE OF SLOPE PROTECTION ALONG ILAGAN-BIGAO-PALANAN ROAD, KO415+000-KO415+020 CITY OF ILAGAN, ISABELA | Region II | Isabela 1st DEO | Completed | ₱2.7M | 100% | Medium risk54 | Flagged0.017 |
| 68 | 22BE0043CONSTRUCTION OF BRIDGE APPROACHES WITH CHANNELIZATION OF WATERWAY AT PACULAGU BRIDGE, BARANGAY NAGANACAN, STA. MARIA, ISABELA | Region II | Isabela 1st DEO | Completed | ₱49.5M | 100% | Medium risk54 | —-0.048 |
| 69 | 24BE0162REHABILITATION OF MUNICIPAL HALL AT BARANGAY CENTRO, CABAGAN, ISABELA | Region II | Isabela 1st DEO | On-Going | ₱39.6M | 88% | Medium risk54 | —-0.039 |
| 70 | 24BE0095CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY NAGANACAN, SANTA MARIA, ISABELA | Region II | Isabela 1st DEO | Completed | ₱4.8M | 100% | Medium risk53 | —-0.086 |
| 71 | 17BE0079CONSTRUCTION OF MULTI-PURPOSE BUILDING (GYMNASIUM) CABAGAN, ISABELA | Region II | Isabela 1st DEO | Completed | ₱4.7M | 100% | Medium risk53 | —-0.058 |
| 72 | 17BE0044MFO-1 NATIONAL ROAD NETWORK SERVICES CONSTRUCTION AND MAINTENANCE OF BRIDGES ALONG NATIONAL ROADS - WIDENING OF PERMANENT BRIDGES, INCLUDING ROW - TO MORE THAN 2 LANES MARANA BR. 2 (B01123LZ) ALONG DAANG MAHARLIKA (LZ) WIDENING OF BRIDGE CITY OF ILAGAN, | Region II | Isabela 1st DEO | Completed | ₱18.8M | 100% | Medium risk53 | —-0.022 |
| 73 | 25BE0003CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP)-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES CONSTRUCTION (COMPLETION) OF BRIDGE, | Region II | Isabela 1st DEO | Completed | ₱11.8M | 100% | Medium risk52 | —-0.025 |
| 74 | 24BE0107CONSTRUCTION OF MUNICIPAL SATELLITE BUILDING AT SAN JUAN, CABAGAN, ISABELA | Region II | Isabela 1st DEO | Completed | ₱9.9M | 100% | Medium risk52 | —-0.083 |
| 75 | 24BE0145CONSTRUCTION OF MULTI-PURPOSE BUILDING (COMPLETION), SANTA MARIA, ISABELA | Region II | Isabela 1st DEO | Completed | ₱9.9M | 100% | Medium risk52 | —-0.083 |