42 projects on file, including joint ventures this contractor is part of.
Total projects
42
Total budget
₱727.7M
Average progress
97.2%
Completion rate
92.9%
Average risk score
37.3
Medium risk on average, out of 100
Flagged as unusual
1
2.4% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region IV-B | 42 | ₱727.7M | 37.3 | 1 | 97.2% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 14 | ₱180.1M | 37.4 | 0 | 100.0% |
| Flood Control and Drainage | 13 | ₱394.5M | 41.8 | 0 | 95.2% |
| Buildings and Facilities | 9 | ₱81.1M | 24.6 | 0 | 99.4% |
| Bridges | 4 | ₱63.1M | 41.3 | 0 | 100.0% |
| GAA 2025 SSP | 1 | ₱4.9M | 93.3 | 1 | 52.1% |
| Water Provision and Storage | 1 | ₱4M | 21.5 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25ED0176CONSTRUCTION OF MULTI - PURPOSE BUILDING, BARANGAY SAN CARLOS, NAUJAN,ORIENTAL MINDORO | Region IV-B | Mindoro Oriental DEO | On-Going | ₱4.9M | 52% | High risk93 | Flagged0.021 |
| 20EI0049CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF PANLUAN RIVER CONTROL, BONGABONG, ORIENTAL MINDORO | Region IV-B | Southern Mindoro DEO | Completed | ₱19.6M | 100% | High risk64 | —-0.045 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25ED0176CONSTRUCTION OF MULTI - PURPOSE BUILDING, BARANGAY SAN CARLOS, NAUJAN,ORIENTAL MINDORO | Region IV-B | Mindoro Oriental DEO | On-Going | ₱4.9M | 52% | High risk93 | Flagged0.021 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 26 | 22EI0019CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS - INTERNAL ACCESS ROAD TO SITIO PALAMANG, MANIHALA LEADING TO MANIHALA WATERFALLS II, BANSUD, ORIENTAL MINDORO | Region IV-B | Southern Mindoro DEO | Completed | ₱14.7M | 100% | Medium risk37 | —-0.093 |
| 27 | 24EI0029CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM - TRIP) - BRGY. MALUBAY TO BRGY. BUONG LUPA TO WALANG LANGIT FALLS, GLORIA, ORIENTAL MINDORO | Region IV-B | Southern Mindoro DEO | Completed | ₱14.7M | 100% | Medium risk37 | —-0.093 |
| 28 | 21EI0167CONCRETING OF ROAD, SITIO LAWAY, BRGY. SALCEDO - SITIO ILAYA - BRGY. TIGUISAN, BANSUD, ORIENTAL MINDORO | Region IV-B | Southern Mindoro DEO | Completed | ₱19.6M | 100% | Medium risk36 | —-0.094 |
| 29 | 23EI0035CONSTRUCTION OF ROAD AT BARANGAY MALO, BANSUD, ORIENTAL MINDORO | Region IV-B | Southern Mindoro DEO | Completed | ₱4.9M | 100% | Medium risk36 | —-0.092 |
| 30 | 21EI0101CONCRETING OF SAN ROQUE - SAN JUAN - TAFARMA ROAD LEADING TO SUGUICAY ISLAND AND VARIOUS BEACHES, PHASE II, BULALACAO, ORIENTAL MINDORO | Region IV-B | Southern Mindoro DEO | Completed | ₱4.9M | 100% | Medium risk36 | —-0.092 |
| 31 | 24EI0025CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM - TRIP) SAN ROQUE - SAN JUAN - TAFARMA ROAD, BRGY. SAN JUAN, BULALACAO, ORIENTAL MINDORO | Region IV-B | Southern Mindoro DEO | Completed | ₱9.8M | 100% | Medium risk36 | —-0.092 |
| 32 | 21EI0121CONCRETING OF BRGY. ANILAO ROAD, BONGABONG, ORIENTAL MINDORO | Region IV-B | Southern Mindoro DEO | Completed | ₱10.4M | 100% | Medium risk36 | —-0.093 |
| 33 | 24EI0118CONSTRUCTION OF 1-STOREY 2-CLASSROOM SCHOOL BUILDING IN BALATASAN NATIONAL HIGH SCHOOL, BARANGAY BALATASAN, BULALACAO, ORIENTAL MINDORO | Region IV-B | Southern Mindoro DEO | Completed | ₱6M | 100% | Medium risk36 | —-0.046 |
| 34 | 23EI0091CONSTRUCTION OF 1 STY 3 CL SCHOOL BUILDING AT FORMON NHS, BONGABONG, ORIENTAL MINDORO | Region IV-B | Southern Mindoro DEO | Completed | ₱9M | 100% | Medium risk35 | —-0.048 |
| 35 | 19EI0145CONSTRUCTION/REHABILITATION OF MALAMIG - SALCEDO ROAD, BRGY. SALCEDO, BANSUD, ORIENTAL MINDORO | Region IV-B | Southern Mindoro DEO | Completed | ₱2.9M | 100% | Low risk22 | —-0.090 |
| 36 | 20EI0178CONSTRUCTION/REHABILITATION OF WATER SUPPLY/SEPTAGE AND SEWERAGE/RAINWATER COLLECTORS, PINAMALAYAN - BULALACAO, ORIENTAL MINDORO | Region IV-B | Southern Mindoro DEO | Completed | ₱4M | 100% | Low risk21 | —-0.050 |
| 37 | 21EI0093CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY SAN FRANCISCO, BULALACAO, ORIENTAL MINDORO | Region IV-B | Southern Mindoro DEO | Completed | ₱4M | 100% | Low risk21 | —-0.086 |
| 38 | 21ED0025CONSTRUCTION OF MULTI - PURPOSE BUILDING (COVERED COURT), BARANGAY BONDOC, CALAPAN CITY, ORIENTAL MINDORO | Region IV-B | Mindoro Oriental DEO | Completed | ₱3M | 100% | Low risk21 | —-0.086 |
| 39 | 25EI0104CONSTRUCTION(COMPLETION) OF MULTI-PURPOSE BUILDING AT BARANGAY BONBON, MANSALAY, ORIENTAL MINDORO, PHASE II | Region IV-B | Southern Mindoro DEO | On-Going | ₱2.9M | 95% | Low risk21 | —-0.053 |
| 40 | 22ED0035REHABILITATION (COMPLETION) OF EVACUATION CENTER (REHABILITATION AND RECOVERY PLAN (RBP) FOR COVID-19), BRGY. ZONE I, SOCORRO, ORIENTAL MINDORO | Region IV-B | Mindoro Oriental DEO | Completed | ₱2M | 100% | Low risk19 | —-0.086 |
| 41 | 23EI0114CONSTRUCTION/COMPLETION OF MULTI-PURPOSE BUILDING AT BARANGAY MALIWANAG, MANSALAY, ORIENTAL MINDORO | Region IV-B | Southern Mindoro DEO | Completed | ₱2.9M | 100% | Low risk14 | —-0.045 |
| 42 | 20ED0045CONSTRUCTION OF MULTI - PURPOSE BUILDING PHASE 2, BRGY. TABON-TABON, BACO, ORIENTAL MINDORO | Region IV-B | Mindoro Oriental DEO | Completed | ₱1.9M | 100% | Low risk12 | —-0.085 |