Contractor dossier
55 projects on file, including joint ventures this contractor is part of.
Total projects
55
Total budget
₱329.2M
Average progress
94.1%
Completion rate
81.8%
Average risk score
41.5
Medium risk on average, out of 100
Flagged as unusual
1
1.8% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region IV-A | 54 | ₱309.5M | 41.3 | 0 | 95.8% |
| Region III | 1 | ₱19.7M | 53.3 | 1 | 2.2% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 37 | ₱199.3M | 35.3 | 1 | 96.1% |
| Roads | 12 | ₱94.3M | 40.4 | 0 | 85.7% |
| GAA 2025 SSP | 5 | ₱32.2M | 93.4 | 0 | 97.6% |
| Water Provision and Storage | 1 | ₱3.4M | 25.2 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25DH0044CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY MUNTING KAWAYAN, MAJAYJAY, LAGUNA | Region IV-A | Laguna 1st DEO | On-Going | ₱4.8M | 88% | High risk95 | —-0.003 |
| 25DH0041CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY PAAGAHAN, MABITAC, LAGUNA | Region IV-A | Laguna 1st DEO | On-Going | ₱4.8M | 100% | High risk94 | —-0.009 |
| 25DH0032CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY SABANG, PAGSANJAN, LAGUNA | Region IV-A | Laguna 1st DEO | On-Going | ₱4.8M | 100% | High risk94 | —-0.009 |
| 25DH0022CONSTRUCTION OF ROAD, BARANGAY SANTO ANGEL NORTE, SANTA CRUZ, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱4.8M | 100% | High risk93 | —-0.033 |
| 25DH0046CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY KAYHACAT, SANTA MARIA, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱13M | 100% | High risk92 | —-0.034 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24C00614STATE UNIVERSITIES AND COLLEGES (SUCS)-THREE STOREY HIGHER EDUCATION BUILDING (PHASE 3), PAMPANGA STATE AGRICULTURAL UNIVERSITY, PROVINCE OF PAMPANGA | Region III | Region III | On-Going | ₱19.7M | 2% | Medium risk53 | Flagged0.034 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25DH0044CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY MUNTING KAWAYAN, MAJAYJAY, LAGUNA | Region IV-A | Laguna 1st DEO | On-Going | ₱4.8M | 88% | High risk95 | —-0.003 |
| 2 | 25DH0041CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY PAAGAHAN, MABITAC, LAGUNA | Region IV-A | Laguna 1st DEO | On-Going | ₱4.8M | 100% | High risk94 | —-0.009 |
| 3 | 25DH0032CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY SABANG, PAGSANJAN, LAGUNA | Region IV-A | Laguna 1st DEO | On-Going | ₱4.8M | 100% | High risk94 | —-0.009 |
| 4 | 25DH0022CONSTRUCTION OF ROAD, BARANGAY SANTO ANGEL NORTE, SANTA CRUZ, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱4.8M | 100% | High risk93 | —-0.033 |
| 5 | 25DH0046CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY KAYHACAT, SANTA MARIA, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱13M | 100% | High risk92 | —-0.034 |
| 6 | 24C00614STATE UNIVERSITIES AND COLLEGES (SUCS)-THREE STOREY HIGHER EDUCATION BUILDING (PHASE 3), PAMPANGA STATE AGRICULTURAL UNIVERSITY, PROVINCE OF PAMPANGA | Region III | Region III | On-Going | ₱19.7M | 2% | Medium risk53 | Flagged0.034 |
| 7 | 23DH0053CONSTRUCTION OF MULTI PURPOSE FACILITY (COVERED COURT), BRGY. KATAYPUANAN, FAMY, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱4.8M | 100% | Medium risk50 | —-0.105 |
| 8 | 25DH0045CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY POBLACION, CAVINTI, LAGUNA | Region IV-A | Laguna 1st DEO | On-Going | ₱4.8M | 54% | Medium risk50 | —-0.052 |
| 9 | 25DH0028CONSTRUCTION OF MULTI PURPOSE BUILDING (COVERED COURT),BARANGAY SAN MIGUEL, PILA, LAGUNA | Region IV-A | Laguna 1st DEO | On-Going | ₱14.4M | 100% | Medium risk50 | —-0.071 |
| 10 | 24DH0052CONSTRUCTION OF MULTI PURPOSE BUILDING (KESONG PUTI TRADE CENTER), BARANGAY POBLACION, STA. CRUZ, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱5.8M | 100% | Medium risk50 | —-0.106 |
| 11 | 24DH0046CONSTRUCTION OF MULTI PURPOSE BUILDING, BRGY. SAN BUENAVENTURA, LUISIANA, LAGUNA | Region IV-A | Laguna 1st DEO | On-Going | ₱4.8M | 100% | Medium risk50 | —-0.064 |
| 12 | 23DH0068CONSTRUCTION OF MULTI-PURPOSE BUILDING BARANGAY, E. JACINTO ST. POBLACION, MAGDALENA, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱4.9M | 100% | Medium risk50 | —-0.106 |
| 13 | 21DH0055CONSTRUCTION OF MULTI PURPOSE BUILDING (COVERED COURT) BRGY. BUENAVISTA, MAGDALENA, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱4.9M | 100% | Medium risk49 | —-0.105 |
| 14 | 20DH0025CONSTRUCTION OF MULTI PURPOSE BUILDING, BRGY. KANLURAN TALAONGAN, CAVINTI, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱7.4M | 100% | Medium risk49 | —-0.104 |
| 15 | 23DH0038CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY SANTISIMA CRUZ, STA. CRUZ, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱5.5M | 100% | Medium risk49 | —-0.105 |
| 16 | 24DH0038CONSTRUCTION OF MULTI PURPOSE BUILDING, BARANGAY NANGUMA, MABITAC, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱4.9M | 100% | Medium risk49 | —-0.104 |
| 17 | 23DH0031CONSTRUCTION OF MULTI PURPOSE BUILDING (COVERED COURT) AT BARANGAY OLLA, MAJAYJAY, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱11.6M | 100% | Medium risk49 | —-0.105 |
| 18 | 25DH0042CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY LLAVAC, SINILOAN, LAGUNA | Region IV-A | Laguna 1st DEO | On-Going | ₱13M | 100% | Medium risk49 | —-0.072 |
| 19 | 23DH0025CONSTRUCTION OF MULTI PURPOSE BUILDING (COVERED COURT) AT BARANGAY BULAJO, CAVINTI, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱11M | 100% | Medium risk49 | —-0.103 |
| 20 | 22DH0060CONSTRUCTION OF MULTI PURPOSE FACILITY, BRGY. ISLA, PANGIL, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱9.9M | 100% | Medium risk49 | —-0.105 |
| 21 | 22DH0034CONSTRUCTION OF MULTI-PURPOSE COVERED COURT AT BARANGAY BANGCO, CAVINTI, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱8.8M | 100% | Medium risk49 | —-0.106 |
| 22 | 23DH0044CONSTRUCTION OF MULTI PURPOSE BUILDING BARANGAY, KAPATALAN, SINILOAN, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱4.9M | 100% | Medium risk48 | —-0.104 |
| 23 | 24DH0058CONCRETING OF BRGY. BALUBAD FMR, BRGY. BALUBAD, LUMBAN, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱14.9M | 100% | Medium risk48 | —-0.055 |
| 24 | 23DH0060CONSTRUCTION/REHABILITATION/IMPROVEMENT OF POBLACION-PAOWIN ROAD BRGY. POBLACION, BRGY. SISILMIN, BRGY. BUKAL, BRGY. CANSUO AND BRGY. PAOWIN CAVINTI, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱4.8M | 100% | Medium risk46 | —-0.107 |
| 25 | 20DH0081REHABILITATION/IMPROVEMENT OF ROAD PROJECT, BRGY. POBLACION, CAVINTI, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱4.8M | 100% | Medium risk46 | —-0.108 |