Contractor dossier
173 projects on file, including joint ventures this contractor is part of.
Total projects
173
Total budget
₱14.7B
Average progress
85.1%
Completion rate
67.6%
Below 70%
Average risk score
57.5
Medium risk on average, out of 100
Flagged as unusual
3
1.7% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| National Capital Region | 121 | ₱7.6B | 54.3 | 3 | 84.3% |
| Central Office | 28 | ₱5.3B | 74.3 | 0 | 100.0% |
| Region IV-A | 24 | ₱1.9B | 54.1 | 0 | 71.7% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Flood Control and Drainage | 133 | ₱12.8B | 57.8 | 2 | 89.9% |
| Roads | 25 | ₱1.1B | 49.4 | 0 | 70.1% |
| Bridges | 6 | ₱271.5M | 51.2 | 0 | 47.6% |
| GAA 2025 OO-2 | 5 | ₱532.3M | 87.1 | 1 | 65.2% |
| GAA 2025 SSP | 2 | ₱40.9M | 91.8 | 0 | 100.0% |
| Buildings and Facilities | 2 | ₱55.1M | 50.5 | 0 | 99.8% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25OC0003PREVENTIVE MAINTENANCE-SECONDARY ROADS ALONG SOUTH SUPER H-WAY - K0007 + 000- K0007 + 305MAKATI CITY, METRO MANILA | National Capital Region | Metro Manila 2nd DEO | On-Going | ₱17.6M | 100% | High risk92 | —-0.003 |
| 25OC0004PREVENTIVE MAINTENANCE - SECONDARY ROADS ALONG SOUTH SUPER H-WAY-K0007 + 401 - K0007 + 712MAKATI CITY, METRO MANILA | National Capital Region | Metro Manila 2nd DEO | On-Going | ₱23.3M | 100% | High risk92 | —-0.001 |
| 25OC0026CONSTRUCTION OF GROUNDSILL / REVETMENT WALL ALONG MAKATI DIVERSION CHANNEL (PHASE 4)MAKATI CITY, METRO MANILA | National Capital Region | Metro Manila 2nd DEO | On-Going | ₱76.4M | 40% | High risk90 | —-0.006 |
| 25OC0002CONSTRUCTION OF GROUNDSILL / REVETMENT WALL ALONG MAKATI DIVERSION CHANNEL (PHASE 3),MAKATI CITY, METRO MANILA | National Capital Region | Metro Manila 2nd DEO | On-Going | ₱76.4M | 59% | High risk90 | —-0.009 |
| 25OI0073CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BALIHATAR-MARULAS CREEK, LAS PINAS CITY | National Capital Region | Las Piñas-Muntinlupa DEO | On-Going | ₱47.3M | 90% | High risk86 | —-0.021 |
| 25O00107REHABILITATION AND IMPROVEMENT OF RETARDING POND AT TAPAYAN PUMPING STATION AND TRIBUTARIES, PASIG CITY | National Capital Region | National Capital Region | On-Going | ₱189.1M | 38% | High risk85 | Flagged0.012 |
| 25OH0051ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM- CONSTRUCTION - MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-REHABILITATION/UPGRADING OF EDSA PUMPING STATION, PASAY CITY | National Capital Region | South Manila DEO | On-Going | ₱143.1M | 99% | High risk85 | —-0.010 |
| 20O00094UPGRADING/REHABILITATION OF NORTH NAVOTAS PUMPING STATION AND REPAIR OF NAVOTAS NAVIGATIONAL GATE (PHASE I) | Central Office | Flood Control Management Cluster | Completed | ₱382.4M | 100% | High risk77 | —-0.035 |
| 22O00062UPGRADING OF MAYPAJO PUMPING STATION, CALOOCAN CITY | Central Office | Flood Control Management Cluster | Completed | ₱241.2M | 100% | High risk77 | —-0.043 |
| 20O00074REPLACEMENT OF TWO (2) BOX CULVERT ALONG LONGOS CREEK LEADING TO LONGOS PUMPING STATION AND REHABILITATION OF BOX CULVERT AT P. AQUINO AVE., BRGY. LONGOS, MALABON CITY | Central Office | Flood Control Management Cluster | Completed | ₱161.1M | 100% | High risk77 | —-0.053 |
| 17Z00011REHABILITATION OF NAPINDAN HYDRAULIC CONTROL STRUCTURES THROUGH DESIGN AND BUILD SCHEME, BRGY. BUTING, PASIG CITY | Central Office | Flood Control Management Cluster | Completed | ₱849.1M | 100% | High risk77 | —-0.006 |
| 19Z00017UPGRADING OF CATMON PUMPING STATION, MALABON CITY | Central Office | Flood Control Management Cluster | Completed | ₱416.4M | 100% | High risk76 | —-0.032 |
| 18Z00031UPGRADING OF SPINE PUMPING STATION, NAVOTAS CITY | Central Office | Flood Control Management Cluster | Completed | ₱385M | 100% | High risk76 | —-0.038 |
| 21O00123UPGRADING OF SAN ANDRES PUMPING STATION, MANILA | Central Office | Flood Control Management Cluster | Completed | ₱186.1M | 100% | High risk76 | —-0.048 |
| 22O00068UPGRADING OF TAPAYAN PUMPING STATION, TAGUIG CITY | Central Office | Flood Control Management Cluster | Completed | ₱389.3M | 100% | High risk76 | —-0.037 |
| 21O00038CONSTRUCTION OF REVETMENT WALL OF BACLARAN CHANNEL (PHASE 5) PARAÑAQUE CITY | Central Office | Flood Control Management Cluster | Completed | ₱188.3M | 100% | High risk76 | —-0.048 |
| 21O00116REVETMENT WORKS ALONG MARULAS TUNGTONG CREEK DIVERSION CHANNEL, LAS PIÑAS CITY | Central Office | Flood Control Management Cluster | Completed | ₱351.8M | 100% | High risk76 | —-0.040 |
| 18O00029UPGRADING OF LONGOS PUMPING STATIONS 1 AND 2 (PHASE 2), MALABON CITY | Central Office | Flood Control Management Cluster | Completed | ₱95.2M | 100% | High risk75 | —-0.071 |
| 21O00125UPGRADING OF ABUCAY PUMPING STATION, MANILA | Central Office | Flood Control Management Cluster | Completed | ₱95.9M | 100% | High risk75 | —-0.069 |
| 17O00020UPGRADING OF LONGOS PUMPING STATIONS 1 & 2, BRGY. LOGOS, MALABON CITY | Central Office | Flood Control Management Cluster | Completed | ₱96.4M | 100% | High risk74 | —-0.071 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25O00107REHABILITATION AND IMPROVEMENT OF RETARDING POND AT TAPAYAN PUMPING STATION AND TRIBUTARIES, PASIG CITY | National Capital Region | National Capital Region | On-Going | ₱189.1M | 38% | High risk85 | Flagged0.012 |
| 25O00113CONSTRUCTION OF SAN ANDRES PUMPING STATION, MANILA (PHASE 2) | National Capital Region | National Capital Region | On-Going | ₱376.8M | 1% | High risk67 | Flagged0.003 |
| 25OH0122CONSTRUCTION OF CUTCUT PUMPING STATION, PASAY CITY (PHASE 1) | National Capital Region | South Manila DEO | On-Going | ₱283.3M | 8% | High risk67 | Flagged0.001 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25OC0003PREVENTIVE MAINTENANCE-SECONDARY ROADS ALONG SOUTH SUPER H-WAY - K0007 + 000- K0007 + 305MAKATI CITY, METRO MANILA | National Capital Region | Metro Manila 2nd DEO | On-Going | ₱17.6M | 100% | High risk92 | —-0.003 |
| 2 | 25OC0004PREVENTIVE MAINTENANCE - SECONDARY ROADS ALONG SOUTH SUPER H-WAY-K0007 + 401 - K0007 + 712MAKATI CITY, METRO MANILA | National Capital Region | Metro Manila 2nd DEO | On-Going | ₱23.3M | 100% | High risk92 | —-0.001 |
| 3 | 25OC0026CONSTRUCTION OF GROUNDSILL / REVETMENT WALL ALONG MAKATI DIVERSION CHANNEL (PHASE 4)MAKATI CITY, METRO MANILA | National Capital Region | Metro Manila 2nd DEO | On-Going | ₱76.4M | 40% | High risk90 | —-0.006 |
| 4 | 25OC0002CONSTRUCTION OF GROUNDSILL / REVETMENT WALL ALONG MAKATI DIVERSION CHANNEL (PHASE 3),MAKATI CITY, METRO MANILA | National Capital Region | Metro Manila 2nd DEO | On-Going | ₱76.4M | 59% | High risk90 | —-0.009 |
| 5 | 25OI0073CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BALIHATAR-MARULAS CREEK, LAS PINAS CITY | National Capital Region | Las Piñas-Muntinlupa DEO | On-Going | ₱47.3M | 90% | High risk86 | —-0.021 |
| 6 | 25O00107REHABILITATION AND IMPROVEMENT OF RETARDING POND AT TAPAYAN PUMPING STATION AND TRIBUTARIES, PASIG CITY | National Capital Region | National Capital Region | On-Going | ₱189.1M | 38% | High risk85 | Flagged0.012 |
| 7 | 25OH0051ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM- CONSTRUCTION - MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-REHABILITATION/UPGRADING OF EDSA PUMPING STATION, PASAY CITY | National Capital Region | South Manila DEO | On-Going | ₱143.1M | 99% | High risk85 | —-0.010 |
| 8 | 20O00094UPGRADING/REHABILITATION OF NORTH NAVOTAS PUMPING STATION AND REPAIR OF NAVOTAS NAVIGATIONAL GATE (PHASE I) | Central Office | Flood Control Management Cluster | Completed | ₱382.4M | 100% | High risk77 | —-0.035 |
| 9 | 22O00062UPGRADING OF MAYPAJO PUMPING STATION, CALOOCAN CITY | Central Office | Flood Control Management Cluster | Completed | ₱241.2M | 100% | High risk77 | —-0.043 |
| 10 | 20O00074REPLACEMENT OF TWO (2) BOX CULVERT ALONG LONGOS CREEK LEADING TO LONGOS PUMPING STATION AND REHABILITATION OF BOX CULVERT AT P. AQUINO AVE., BRGY. LONGOS, MALABON CITY | Central Office | Flood Control Management Cluster | Completed | ₱161.1M | 100% | High risk77 | —-0.053 |
| 11 | 17Z00011REHABILITATION OF NAPINDAN HYDRAULIC CONTROL STRUCTURES THROUGH DESIGN AND BUILD SCHEME, BRGY. BUTING, PASIG CITY | Central Office | Flood Control Management Cluster | Completed | ₱849.1M | 100% | High risk77 | —-0.006 |
| 12 | 19Z00017UPGRADING OF CATMON PUMPING STATION, MALABON CITY | Central Office | Flood Control Management Cluster | Completed | ₱416.4M | 100% | High risk76 | —-0.032 |
| 13 | 18Z00031UPGRADING OF SPINE PUMPING STATION, NAVOTAS CITY | Central Office | Flood Control Management Cluster | Completed | ₱385M | 100% | High risk76 | —-0.038 |
| 14 | 21O00123UPGRADING OF SAN ANDRES PUMPING STATION, MANILA | Central Office | Flood Control Management Cluster | Completed | ₱186.1M | 100% | High risk76 | —-0.048 |
| 15 | 22O00068UPGRADING OF TAPAYAN PUMPING STATION, TAGUIG CITY | Central Office | Flood Control Management Cluster | Completed | ₱389.3M | 100% | High risk76 | —-0.037 |
| 16 | 21O00038CONSTRUCTION OF REVETMENT WALL OF BACLARAN CHANNEL (PHASE 5) PARAÑAQUE CITY | Central Office | Flood Control Management Cluster | Completed | ₱188.3M | 100% | High risk76 | —-0.048 |
| 17 | 21O00116REVETMENT WORKS ALONG MARULAS TUNGTONG CREEK DIVERSION CHANNEL, LAS PIÑAS CITY | Central Office | Flood Control Management Cluster | Completed | ₱351.8M | 100% | High risk76 | —-0.040 |
| 18 | 18O00029UPGRADING OF LONGOS PUMPING STATIONS 1 AND 2 (PHASE 2), MALABON CITY | Central Office | Flood Control Management Cluster | Completed | ₱95.2M | 100% | High risk75 | —-0.071 |
| 19 | 21O00125UPGRADING OF ABUCAY PUMPING STATION, MANILA | Central Office | Flood Control Management Cluster | Completed | ₱95.9M | 100% | High risk75 | —-0.069 |
| 20 | 17O00020UPGRADING OF LONGOS PUMPING STATIONS 1 & 2, BRGY. LOGOS, MALABON CITY | Central Office | Flood Control Management Cluster | Completed | ₱96.4M | 100% | High risk74 | —-0.071 |
| 21 | 16O00047FLOOD CONTROL PROJECTS BAS3ED ON FLOOD MASTER PLAN FOR METRO MANILA AND SURROUNDING AREAS, LAS PINAS RIVER IMPROVEMENT INCLUDING ROW (REVETMENT WORKS ALONG MARULAS-TUNGTONG CREEK DIVERSION CHANNEL (DPWH: KAYBUBOY CREEK TRIBUTARY)STA. 1+100 TO STA. 1+400, | Central Office | Flood Control Management Cluster | Completed | ₱114.9M | 100% | High risk74 | —-0.065 |
| 22 | 19O00050PROPOSED CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG ALABANG RIVER AND LAGUNA DE BAY, STA. 0+000 TO STA. 0+195 AND STA. 0+080-B, BRGY. ALABANG AND BRGY. CUPANG, MUNTINLUPA CITY | Central Office | Flood Control Management Cluster | Completed | ₱112.8M | 100% | High risk74 | —-0.068 |
| 23 | 22Z00025UPGRADING OF TAPAYAN PUMPING STATION, (UPGRADING OF POWER SUPPLY SYSTEM AND OTHER RELATED STRUCTURES), TAGUIG CITY | Central Office | Flood Control Management Cluster | Completed | ₱102.3M | 100% | High risk74 | —-0.068 |
| 24 | 20O00070CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG LAGUNA DE BAY, STA. 0+000 TO STA. 0+179.00 AND STA. 0+000-B TO STA. 0+239.80-B TUNASAN AND BRGY. POBLACION, MUNTINLUPA CITY | Central Office | Flood Control Management Cluster | Completed | ₱139.6M | 100% | High risk74 | —-0.059 |
| 25 | 20O00071CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG LAGUNA DE BAY, STA. 0+000 TO STA. 0+339.80 AND STA. 0+000-B - STA. 0+331.80-B ALABANG AND BRGY. CUPANG, MUNTINLUPA CITY | Central Office | Flood Control Management Cluster | Completed | ₱139.4M | 100% | High risk74 | —-0.059 |