Contractor dossier
91 projects on file, including joint ventures this contractor is part of.
Total projects
91
Total budget
₱6.7B
Average progress
93.7%
Completion rate
75.8%
Average risk score
55.9
Medium risk on average, out of 100
Flagged as unusual
2
2.2% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region V | 89 | ₱6.2B | 55.8 | 2 | 94.3% |
| Region IV-B | 2 | ₱461.8M | 63.7 | 0 | 69.6% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 49 | ₱3.4B | 52.1 | 0 | 93.0% |
| Flood Control and Drainage | 20 | ₱2.4B | 63.4 | 1 | 95.6% |
| Buildings and Facilities | 9 | ₱147.4M | 44.4 | 1 | 88.4% |
| OTHER | 7 | ₱374.3M | 76.0 | 0 | 97.6% |
| Bridges | 6 | ₱300.9M | 56.4 | 0 | 96.9% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 19F00094REHABILITATION/RESTORATION OF MATANAG FLOOD CONTROL(UPSTREAM OF SPILLWAY), MATANAG, LEGAZPI CITY, ALBAY, ALBAY 2ND LEGISLATIVE DISTRICT | Region V | Region V | Completed | ₱120.4M | 100% | High risk81 | —-0.014 |
| 17F00014MFO1-IMPROVEMENT/WIDENING OF NATIONAL ROADS-OTHER PRIMARY ROADS: ROLANDO A. ANDAYA HIGHWAY, K0319+938.00-K0324+300.00 WITH EXCEPTIONS, RAGAY & SIPOCOT, CAMARINES SUR PROVINCE | Region V | Region V | Completed | ₱149.1M | 100% | High risk80 | —-0.011 |
| 17FN0012REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED NATIONAL ROADS INCLUDING DRAINAGE, CABUSAO, CAMARINES SUR | Region V | Camarines Sur 1st DEO | Completed | ₱11.3M | 100% | High risk77 | —-0.034 |
| 17FG0042INDV. PROJ. - IMPVT/WIDENING OF NAT'L RD ALONG NABUA-BALATAN ROAD, BALATAN, CAM. SUR K0483+591-K0484+033, K0484+700-K0486+000, K0488+506-K0488+560, K0489+(-)173-K0489+(-)126, K0491+(-)084-K0491+(-)052, K0491+148-K0491+301, K0491+660-K0491+760 | Region V | Camarines Sur 5th DEO | Completed | ₱43.7M | 100% | High risk77 | —-0.036 |
| 19F00113REHABILITATION/IMPROVEMENT OF WARAS RIVER FLOOD CONTROL PROJECT (STA. ELENA-SAN JOSE SECTION) IRIGA CITY, CAMARINES SUR, CAMARINES SUR 5TH LEGISLATIVE DISTRICT | Region V | Region V | Completed | ₱190.1M | 100% | High risk75 | Flagged0.001 |
| 24F00029ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-ROAD WIDENING-PRIMARY ROADS-DAANG MAHARLIKA (LZ)-K0299+000 - K0299+291. K0299+821-K0300+000, LABO, CAMARINES NORTE (1ST LEGISLATIVE DISTRICT) | Region V | Region V | On-Going | ₱45.5M | 87% | High risk75 | —-0.004 |
| 20F00093OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - BRIDGE PROGRAM - WIDENING OF PERMANENT BRIDGES - KILBAY BRIDGE (B00446LZ) ALONG ROLANDO A. ANDAYA HIGHWAY (PHASE II), DEL GALLEGO, CAMARINES SUR 1ST LEGISLATIVE DISTRICT | Region V | Region V | Completed | ₱28.9M | 100% | High risk75 | —-0.034 |
| 23FC0071NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - PRIMARY ROADS - DAANG MAHARLIKA (LZ) - K0261+515 - K0262+183, STA. ELENA, CAMARINES NORTE | Region V | Camarines Norte DEO | Completed | ₱48.7M | 100% | High risk75 | —-0.032 |
| 23F00300CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) - CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM-TRIP)-DAET-VINZONS LEADING TO MANTIGBI-SULA-SABANG-AGUIT-IT BEACH, QUINAMANUKAN ISLAND, | Region V | Region V | On-Going | ₱47.1M | 96% | High risk74 | —-0.002 |
| 16F00096CONSTRUCTION/REHABILITATION/IMPROVEMENT OF BICOL RIVER FLOOD CONTROL, MABOLO SECTION, BRGY. MABOLO; AND TRIANGULO SECTION, BRGY. TRIANGULO, NAGA CITY, CAMARINES SUR 3RD LD | Region V | Region V | Completed | ₱97.5M | 100% | High risk71 | —-0.047 |
| 24F00282ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF DAET RIVER FLOOD CONTROL STRUCTURE (DOGONGAN SECTION-PACKAGE | Region V | Region V | On-Going | ₱238.7M | 90% | High risk71 | —-0.016 |
| 25F00037ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, DAET RIVER, BARANGAY BIBIRAO, DAE | Region V | Region V | On-Going | ₱235.2M | 95% | High risk71 | —-0.024 |
| 24F00283ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF DAET RIVER FLOOD CONTROL STRUCTURE (DOGONGAN SECTION-PACKAGE | Region V | Region V | Completed | ₱236.4M | 100% | High risk71 | —-0.051 |
| 24F00190ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG | Region V | Region V | On-Going | ₱149M | 78% | High risk71 | —-0.025 |
| 25F00022ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, BARANGAY MAMBALITE, DAET, CAMARIN | Region V | Region V | On-Going | ₱149.8M | 89% | High risk70 | —-0.035 |
| 24F00275CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-SIPAG-FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE (PHASE 1), SITIO LUGI, | Region V | Region V | On-Going | ₱187.2M | 61% | High risk70 | —-0.009 |
| 19F00078OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM, REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS-PRIMARY ROADS, ROLANDO A. ANDAYA HIGHWAY, CAMARINES SUR, K0282+(-186)-K0282+(-181), K0282+160-K0282+245, K0282+3 | Region V | Region V | Completed | ₱240.8M | 100% | High risk70 | —-0.064 |
| 20F00107LOCAL PROGRAM-NATIONAL ROADS AND BRIDGES-NATIONAL ROADS-LOCAL INFRASTRUCTURE PROGRAM-REHABILITATION/RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSED AND LANDSLIDE ANDAYA HIGHWAY, RAGAY, CAMARINES SUR, RAGAY, CAMARINES SUR(1ST LEGISLATIVE DISTR | Region V | Region V | Completed | ₱142.1M | 100% | High risk69 | —-0.075 |
| 18F00038OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT-ROAD WIDENING-PRIMARY ROADS, ROLANDO A. ANDAYA HIGHWAY, K0283+183-K0286+760 (WITH EXCEPTIONS), CAMARINES SUR | Region V | Region V | Completed | ₱141.1M | 100% | High risk69 | —-0.078 |
| 23F00195CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-INTERJURISDICTIONAL ROADS AND/OR BRIDGES (OR,ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS)-CONSTRUCTION OF BALATAS-CARARAYAN-DEL ROSARIO BYPASS ROAD, PA | Region V | Region V | On-Going | ₱144.7M | 90% | High risk69 | —-0.042 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 19F00131CONSTRUCTION OF EVACUATION CENTERS INCLUDING SITE DEVELOPMENT IN REGION V, COMADOG-CADOG, DEL GALLEGO, CAMARINES SUR | Region V | Region V | On-Going | ₱34.6M | 0% | Medium risk55 | Flagged0.047 |
| 19F00113REHABILITATION/IMPROVEMENT OF WARAS RIVER FLOOD CONTROL PROJECT (STA. ELENA-SAN JOSE SECTION) IRIGA CITY, CAMARINES SUR, CAMARINES SUR 5TH LEGISLATIVE DISTRICT | Region V | Region V | Completed | ₱190.1M | 100% | High risk75 | Flagged0.001 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 51 | 18FN0076CONSTRUCTION OF TWO (2) UNITS, THREE (3) STOREY, ONE (1) REGULAR, ONE (1) SCIENCE LAB., & ONE (1) ICT BUILDING AT SIPOCOT NATIONAL HIGH SCHOOL, SIPOCOT, CAMARINES SUR | Region V | Camarines Sur 1st DEO | Completed | ₱48.2M | 100% | Medium risk57 | —-0.044 |
| 52 | 24F00030ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-ROAD WIDENING-PRIMARY ROADS-DAANG MAHARLIKA (LZ)-K0305+406-K0305+880, LABO, CAMARINES NORTE (1ST LEGISLATIVE DISTRICT | Region V | Region V | On-Going | ₱36.5M | 76% | Medium risk56 | —-0.062 |
| 53 | 19F00131CONSTRUCTION OF EVACUATION CENTERS INCLUDING SITE DEVELOPMENT IN REGION V, COMADOG-CADOG, DEL GALLEGO, CAMARINES SUR | Region V | Region V | On-Going | ₱34.6M | 0% | Medium risk55 | Flagged0.047 |
| 54 | 22FG0047CONSTRUCTION OF SAN ISIDRO NORTE-AGOSAIS ROAD LEADING TO PILGRIMAGE SITE AND BOLAN-OGAN FALLS, SECTION 1 : STA.0+000.00-STA.0+056.50 TO SECTION 6 : STA.4+189.40 -STA.5+865.00 LAGONOY, CAMARINES SUR | Region V | Camarines Sur 4th DEO | Completed | ₱49M | 100% | Medium risk55 | —-0.090 |
| 55 | 22F00143OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION/IMPROVEMENT OF KILBAY RIVER FLOOD MITIGATION STRUCTURE, DEL GALLEGO, CAMARINES SUR | Region V | Region V | Completed | ₱89.3M | 100% | Medium risk55 | —-0.076 |
| 56 | 19FN0051REHABILITATION/RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - PRIMARY ROADS | Region V | Camarines Sur 1st DEO | Completed | ₱29.8M | 100% | Medium risk55 | —-0.099 |
| 57 | 22FD0005ROAD WIDENING - TERTIARY ROADS, SIPOCOT-CABUSAO RD - K0400 + 000 - K0401 + 000 | Region V | Camarines Sur 1st DEO | Completed | ₱46.4M | 100% | Medium risk54 | —-0.098 |
| 58 | 24F00031ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-ROAD WIDENING-PRIMARY ROADS-DAANG MAHARLIKA (LZ)-K0311+260-K0311+591, LABO, CAMARINES NORTE (1ST LEGISLATIVE DISTRICT) | Region V | Region V | On-Going | ₱22.9M | 88% | Medium risk54 | —-0.063 |
| 59 | 24F00028ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-ROAD WIDENING-PRIMARY ROADS-DAANG MAHARLIKA (LZ)-K0302+103-K0302+280, LABO, CAMARINES NORTE (1ST LEGISLATIVE DISTRICT | Region V | Region V | On-Going | ₱18.4M | 70% | Medium risk53 | —-0.060 |
| 60 | 21FD0005WIDENING OF PERMANENT BRIDGE, AGA BR. (B00376LZ) ALONG DAANG MAHARLIKA (LZ) | Region V | Camarines Sur 1st DEO | Completed | ₱30.3M | 100% | Medium risk53 | —-0.062 |
| 61 | 21FD0007WIDENING OF PERMANENT BRIDGE, CALAGBANGAN BR. (B00375LZ) ALONG ROLANDO A. ANDAYA HIGHWAY (LZ) | Region V | Camarines Sur 1st DEO | Completed | ₱32.3M | 100% | Medium risk53 | —-0.062 |
| 62 | 21FD0002ROAD WIDENING - PRIMARY ROADS, DAANG MAHARLIKA (LZ) - K0384+772 - K0384+874, K0384+905 - K0384+1222 | Region V | Camarines Sur 1st DEO | Completed | ₱16.2M | 100% | Medium risk53 | —-0.101 |
| 63 | 21FD0004ROAD WIDENING - PRIMARY ROADS, ROLANDO A. ANDAYA HIGHWAY - K0326+000 - K0326+330 | Region V | Camarines Sur 1st DEO | Completed | ₱14.7M | 100% | Medium risk52 | —-0.101 |
| 64 | 21F00072OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-ROAD WIDENING-PRIMARY ROADS-ROLANDO A. ANDAYA HIGHWAY, K0301+395.00-K0301+628.60, CAMARINES SUR 1ST LEGISLATIVE DISTRICT | Region V | Region V | Completed | ₱19.3M | 100% | Medium risk52 | —-0.099 |
| 65 | 20FD0057CONCRETING OF BARANGAY ROAD, BAGANGAN JR. TO BAGANGAN SR., LUPI, CAMARINES SUR | Region V | Camarines Sur 1st DEO | Completed | ₱14.1M | 100% | Medium risk52 | —-0.101 |
| 66 | 22F00082OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-BRIDGE PROGRAM-WIDENING OF PERMANENT BRIDGES- PANAYTAYAN BRIDGE (B00438LZ) ALONG ROLANDO A. ANDAYA HIGHWAY, CAMARINES SUR 1ST LEGISLATIVE DISTRICT | Region V | Region V | On-Going | ₱27M | 100% | Medium risk52 | —-0.017 |
| 67 | 18FN0011PREVENTIVE MAINTENANCE - PRIMARY ROADS, ROLANDO ANDAYA HIGHWAY, K0318+000 - K0318+525 | Region V | Camarines Sur 1st DEO | Completed | ₱10M | 100% | Medium risk52 | —-0.098 |
| 68 | 19FN0157REHABILITATION OF BRIDGE, BRGY. BUCAL, DEL GALLEGO, CAMARINES SUR | Region V | Camarines Sur 1st DEO | Completed | ₱4.8M | 100% | Medium risk52 | —-0.063 |
| 69 | 19FN0104CONCRETING OF BARANGAY ROAD, BRGY. BINAHIAN, SIPOCOT, CAMARINES SUR | Region V | Camarines Sur 1st DEO | Completed | ₱11.3M | 100% | Medium risk51 | —-0.101 |
| 70 | 21F00032OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION/IMPROVEMENT OF RAGAY RIVER FLOOD MITIGATION STRUCTURES | Region V | Region V | Completed | ₱54.3M | 100% | Medium risk51 | —-0.084 |
| 71 | 20FD0021CONSTRUCTION OF MULTI-PURPOSE BUILDING, SOUTH VILLAZAR, SIPOCOT, CAMARINES SUR | Region V | Camarines Sur 1st DEO | Completed | ₱4.8M | 100% | Medium risk50 | —-0.098 |
| 72 | 22FD0026CONSTRUCTION OF MULTI-PURPOSE BUILDING, RAGAY MUNICIPAL QUADRANGLE, BARANGAY POBLACION IRAYA, RAGAY, CAMARINES SUR | Region V | Camarines Sur 1st DEO | Completed | ₱7.7M | 100% | Medium risk50 | —-0.097 |
| 73 | 19FN0094CONSTRUCTION OF MULTI-PURPOSE BUILDING, MUNICIPAL HALL COMPOUND, BRGY. ILAOD, RAGAY, CAMARINES SUR | Region V | Camarines Sur 1st DEO | Completed | ₱9.6M | 100% | Medium risk48 | —-0.098 |
| 74 | 22FG0039CONSTRUCTION OF FLOOD MITIGATION STRUCTURE (SEAWALL) ALONG LAMIT BAY, STA.0+190.50 - STA.0+480.50, STA.0+051.00 - STA.0+475.00BARANGAY BALATON, LAGONOY, CAMARINES SUR | Region V | Camarines Sur 4th DEO | Completed | ₱49M | 100% | Medium risk47 | —-0.075 |
| 75 | 22FG0041CONSTRUCTION OF FLOOD MITIGATION STRUCTURE (SEAWALL) ALONG LAMIT BAYSECTION 1: STA.0+000.00 - STA.0+180.00SECTION 2: STA.0+569.70 - STA.0+900.00MANGGOGON, LAGONOY, CAMARINES SUR | Region V | Camarines Sur 4th DEO | Completed | ₱49M | 100% | Medium risk47 | —-0.081 |