Contractor dossier
25 projects on file, including joint ventures this contractor is part of.
Total projects
25
Total budget
₱222.6M
Average progress
95.8%
Completion rate
84.0%
Average risk score
35.9
Medium risk on average, out of 100
Flagged as unusual
2
8.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region IV-B | 18 | ₱190.5M | 32.5 | 1 | 99.8% |
| Region IV-A | 5 | ₱22.3M | 34.2 | 1 | 80.0% |
| Region III | 2 | ₱9.8M | 71.6 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 11 | ₱62.7M | 38.4 | 0 | 100.0% |
| Water Provision and Storage | 8 | ₱24.9M | 26.7 | 1 | 87.5% |
| Roads | 5 | ₱63.8M | 33.6 | 0 | 100.0% |
| GAA 2025 SSP | 1 | ₱71.3M | 94.3 | 1 | 96.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25EH0041CONSTRUCTION OF SEAWALL ALONG POBLACION LEADING TO AMBULONG, PHASE 2, MAGDIWANG, ROMBLON | Region IV-B | Romblon DEO | On-Going | ₱71.3M | 96% | High risk94 | Flagged0.012 |
| 24C00138BASIC INFRASTRUCTURE PROGRAM-BIP- MULTI PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING (PHASE II), BARANGAY PULONG BAYABAS, SAN MIGUEL BULACAN | Region III | Region III | Completed | ₱4.9M | 100% | High risk72 | —-0.076 |
| 24C00139BASIC INFRASTRUCTURE PROGRAM-BIP- MULTI PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING (PHASE II), BARANGAY MAGMARALE, SAN MIGUEL, BULACAN | Region III | Region III | Completed | ₱4.9M | 100% | High risk71 | —-0.075 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25EH0041CONSTRUCTION OF SEAWALL ALONG POBLACION LEADING TO AMBULONG, PHASE 2, MAGDIWANG, ROMBLON | Region IV-B | Romblon DEO | On-Going | ₱71.3M | 96% | High risk94 | Flagged0.012 |
| 25DQ0109CAPITAL OUTLAY - CONVERGENCE AND SPECIAL SUPPORT PROGRAM - RAINWATER COLLECTOR SYSTEM - VICENTE P. VILLANUEVA MEMORIAL SCHOOL, DASMARIÑAS CITY, CAVITE; MALINTA ELEMENTARY SCHOOL, BRGY. SAMPALOC II, DASMARIÑAS CITY, CAVITE; CAVITE STATE UNIVERSITY, BRGY. | Region IV-A | Cavite 3rd DEO | On-Going | ₱2.6M | 0% | Medium risk48 | Flagged0.011 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25EH0041CONSTRUCTION OF SEAWALL ALONG POBLACION LEADING TO AMBULONG, PHASE 2, MAGDIWANG, ROMBLON | Region IV-B | Romblon DEO | On-Going | ₱71.3M | 96% | High risk94 | Flagged0.012 |
| 2 | 24C00138BASIC INFRASTRUCTURE PROGRAM-BIP- MULTI PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING (PHASE II), BARANGAY PULONG BAYABAS, SAN MIGUEL BULACAN | Region III | Region III | Completed | ₱4.9M | 100% | High risk72 | —-0.076 |
| 3 | 24C00139BASIC INFRASTRUCTURE PROGRAM-BIP- MULTI PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING (PHASE II), BARANGAY MAGMARALE, SAN MIGUEL, BULACAN | Region III | Region III | Completed | ₱4.9M | 100% | High risk71 | —-0.075 |
| 4 | 22DH0055CONSTRUCTION OF MULTI-PURPOSE BUILDING (MATERIALS RECOVERY FACILITY), MAJAYJAY, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱9.5M | 100% | Medium risk49 | —-0.106 |
| 5 | 25DQ0109CAPITAL OUTLAY - CONVERGENCE AND SPECIAL SUPPORT PROGRAM - RAINWATER COLLECTOR SYSTEM - VICENTE P. VILLANUEVA MEMORIAL SCHOOL, DASMARIÑAS CITY, CAVITE; MALINTA ELEMENTARY SCHOOL, BRGY. SAMPALOC II, DASMARIÑAS CITY, CAVITE; CAVITE STATE UNIVERSITY, BRGY. | Region IV-A | Cavite 3rd DEO | On-Going | ₱2.6M | 0% | Medium risk48 | Flagged0.011 |
| 6 | 25EH0007CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), SAN AGUSTIN ELEMENTARY SCHOOL, BARANGAY POBLACION, SAN AGUSTIN, ROMBLON | Region IV-B | Romblon DEO | On-Going | ₱9.8M | 100% | Medium risk39 | —-0.059 |
| 7 | 23EH0061REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE ALONG TABLAS CIRCUMFERENTIAL RD - K0042+100 - K0042+125, K0042+700 - K0042+718, K0042+750 - K0042+768.30, TABLAS ISLAND, ROMBLON | Region IV-B | Romblon DEO | Completed | ₱14.5M | 100% | Medium risk37 | —-0.091 |
| 8 | 24EH0011REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE ALONG TABLAS CIRCUMFERENTIAL ROAD - K0041+091 - K0041+117.80 (AS PER ACTUAL AND RBIA), TABLAS ISLAND, ROMBLON | Region IV-B | Romblon DEO | Completed | ₱18.1M | 100% | Medium risk36 | —-0.092 |
| 9 | 24EH0027CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG TABLAS CIRCUMFERENTIAL ROAD, K0056+000 - K0057+103 AS PER ACTUAL, K0056+000 - K0057+096 AS PER RBIA, TABLAS ISLAND, ROMBLON | Region IV-B | Romblon DEO | Completed | ₱15.3M | 100% | Medium risk36 | —-0.091 |
| 10 | 23EH0025CONSTRUCTION OF MULTI-PURPOSE BUILDING, SITIO TIPOLO, BARANGAY POBLACION, STA. FE, ROMBLON | Region IV-B | Romblon DEO | Completed | ₱5M | 100% | Medium risk36 | —-0.088 |
| 11 | 23EH0087REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE ALONG TABLAS CIRCUMFERENTIAL ROAD, K0043+120 - K0043+132.56, K0043+250 - K0043+284.37, K0043+320 - K0043+334, K0043+400 - K0043+418, TABLAS ISLAND, ROMBLON | Region IV-B | Romblon DEO | Completed | ₱11.8M | 100% | Medium risk36 | —-0.091 |
| 12 | 25EH0052CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HALL), BARANGAY CANDUYONG, ODIONGAN, ROMBLON | Region IV-B | Romblon DEO | Completed | ₱6.8M | 100% | Medium risk35 | —-0.088 |
| 13 | 23EH0013CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY SAN ISIDRO STA. MARIA, ROMBLON | Region IV-B | Romblon DEO | Completed | ₱4.9M | 100% | Medium risk35 | —-0.087 |
| 14 | 24EH0140CONSTRUCTION OF 1-STOREY 2-CLASSROOM SCHOOL BUILDING AT LONOS ELEMENTARY SCHOOL, BARANGAY LONOS, ROMBLON, ROMBLON | Region IV-B | Romblon DEO | Completed | ₱5M | 100% | Medium risk34 | —-0.047 |
| 15 | 25EH0167CONSTRUCTION OF 7 RAINWATER COLLECTION SYSTEM (RWCS), TABLAS ISLAND, ROMBLON | Region IV-B | Romblon DEO | On-Going | ₱2.6M | 100% | Low risk26 | —-0.028 |
| 16 | 22DQ0103CONSTRUCTION/ REHABILITATION OF WATER SUPPLY/ SEPTAGE AND SEWERAGE/ RAINWATER COLLECTOR SYSTEM - RAINWATER COLLECTOR IN PUBLIC FACILITIES, BARANGAY BANABA, SILANG, CAVITE; BARANGAY ACACIA, SILANG, CAVITE; BARANGAY NARRA I, SILANG, CAVITE; BARANGAY NARRA I | Region IV-A | Cavite 3rd DEO | Completed | ₱3.4M | 100% | Low risk25 | —-0.067 |
| 17 | 21DQ0129CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/ REHABILITATION OF WATER SUPPLY/ SEPTAGE AND SEWERAGE/ RAINWATER COLLECTOR SYSTEM - RAINWATER COLLECTOR SYSTEM, PHILIPPINE NATIONAL POLICE, BRGY. LALAAN I, SILANG, CAVITE; RAINWATER COLLECTOR SYSTEM, | Region IV-A | Cavite 3rd DEO | Completed | ₱4.4M | 100% | Low risk25 | —-0.068 |
| 18 | 23DQ0111CONSTRUCTION/ REHABILITATION OF WATER SUPPLY/ SEPTAGE AND SEWERAGE/ RAINWATER COLLECTOR SYSTEM, TIBIG ELEMENTARY SCHOOL, BARANGAY TIBIG, SILANG, CAVITE; POOC ELEMENTARY SCHOOL, BARANGAY POOC, SILANG, CAVITE; BALITE I ELEMENTARY SCHOOL, BARANGAY BALITE I, | Region IV-A | Cavite 3rd DEO | Completed | ₱2.4M | 100% | Low risk24 | —-0.068 |
| 19 | 24EH0147CONSTRUCTION OF 7 RAINWATER COLLECTION SYSTEM (RWCS), TABLAS ISLAND, ROMBLON | Region IV-B | Romblon DEO | Completed | ₱2.9M | 100% | Low risk23 | —-0.048 |
| 20 | 23EH0024REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE ALONG TABLAS CIRCUMFERENTIAL ROAD, K0069+202 - K0069+238.20, K0069+246.60 - K0069+262, TABLAS ISLAND, ROMBLON | Region IV-B | Romblon DEO | Completed | ₱4.2M | 100% | Low risk23 | —-0.089 |
| 21 | 21EH0122CONSTRUCTION OF 12 RAINWATER COLLECTOR SYSTEM (RWCS), SIBUYAN ISLAND, ROMBLON | Region IV-B | Romblon DEO | Completed | ₱4.4M | 100% | Low risk22 | —-0.046 |
| 22 | 24EH0083CONSTRUCTION OF QUALITY ASSURANCE LABORATORY BUILDING, DPWH ROMBLON DEO, ODIONGAN, ROMBLON | Region IV-B | Romblon DEO | Completed | ₱3.6M | 100% | Low risk22 | —-0.088 |
| 23 | 23EH0109CONSTRUCTION OF 6 RAINWATER COLLECTOR SYSTEM (RWCS), TABLAS ISLAND, ROMBLON | Region IV-B | Romblon DEO | Completed | ₱2.3M | 100% | Low risk20 | —-0.048 |
| 24 | 23EH0157CONSTRUCTION OF 1STY2CL, VICTORIO SIXON BALOGO NATIONAL HIGH SCHOOL, CALATRAVA, ROMBLON | Region IV-B | Romblon DEO | Completed | ₱4.1M | 100% | Low risk14 | —-0.046 |
| 25 | 23EH0158CONSTRUCTION OF 1STY2CL, EDUARDO M. MORENO NATIONAL HIGH SCHOOL, SAN AGUSTIN, ROMBLON | Region IV-B | Romblon DEO | Completed | ₱4.1M | 100% | Low risk14 | —-0.046 |