Opening the dossier…
Opening the dossier…
Contractor dossier
67 projects on file, including joint ventures this contractor is part of.
Total projects
67
Total budget
₱1.8B
Average progress
96.1%
Completion rate
83.6%
Average risk score
47.3
Medium risk on average, out of 100
Flagged as unusual
2
3.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| National Capital Region | 50 | ₱1.1B | 46.3 | 1 | 99.3% |
| Region IV-A | 10 | ₱215.3M | 56.0 | 0 | 88.2% |
| Region III | 7 | ₱451.8M | 41.8 | 1 | 83.9% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 33 | ₱926.8M | 46.6 | 1 | 95.9% |
| Flood Control and Drainage | 23 | ₱787.1M | 47.9 | 1 | 94.7% |
| Buildings and Facilities | 8 | ₱52.8M | 43.4 | 0 | 99.5% |
| Bridges | 2 | ₱23.8M | 46.8 | 0 | 100.0% |
| GAA 2025 OO-2 | 1 | ₱18.8M | 87.9 | 0 | 99.1% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25DN0046CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BANGIAD CREEK, TAYTAY, RIZAL (FIRST DISTRICT) | Region IV-A | Rizal 1st DEO | On-Going | ₱18.8M | 99% | High risk88 | —-0.033 |
| 24DN0014FY 2024 DPWH INFRASTRUCTURE PROGRAM - BASIC INFRASTRUCTURE PROGRAM - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), ABA HOMES, BARANGAY DALIG ANTIPOLO CITY, RIZAL (SECOND DISTRICT) | Region IV-A | Rizal 1st DEO | On-Going | ₱5M | 96% | High risk71 | —-0.033 |
| 25DN0039CONSTRUCTION OF BREAKWATER, BARANGAY PIPINDAN, BINANGONAN, RIZAL (FIRST DISTRICT) | Region IV-A | Rizal 1st DEO | On-Going | ₱47M | 13% | High risk71 | —-0.004 |
| 24OF0142PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - CONGRESSIONAL AVE EXT - (S05137LZ) K0015+(-903) - K0016+813, QUEZON CITY | National Capital Region | Quezon City 1st DEO | Completed | ₱96.5M | 100% | High risk60 | —-0.087 |
| 25C00006CONVERGENCE & SPL. SUPP. PROG.-SUSTAINABLE INFRASTRUCTURE PROJS. ALLEVIATING GAPS (SIPAG)-ACCESS RDS. AND/OR BRS. FR. THE NAT'L. ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BLDGS./ FACILITIES-CONST. OF ROAD (PACKAGE 3), BRGY. LIYANG, PILAR BRGY. BILOLO, ORIO | Region III | Region III | On-Going | ₱94.8M | 0% | High risk60 | —-0.034 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24OF0295REHABILITATION / RECONSTRUCTION OF SLOPE PROTECTION STRUCTURE OF TULLAHAN RIVER ALONG BARANGAY NAGKAISANG NAYON, QUEZON CITY | National Capital Region | Quezon City 1st DEO | On-Going | ₱38.2M | 67% | Medium risk53 | Flagged0.014 |
| 24CK0184CONSTRUCTION OF BANGUT RIVER SERVICE ROAD (SEGMENT C), CAPAS, TARLAC | Region III | Tarlac 2nd DEO | On-Going | ₱76.4M | 87% | Medium risk42 | Flagged0.004 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 26 | 22OF0189REHABILITATION/ IMPROVEMENT OF ROAD INCLUDING DRAINAGE AT ORANGE STREET, VIOLET STREET, AND RAINBOW STREET, BARANGAY SAN BARTOLOME, QUEZON CITY | National Capital Region | Quezon City 1st DEO | Completed | ₱38.8M | 100% | Medium risk47 | —-0.096 |
| 27 | 22OF0049REHABILITATION OF ROAD AT BATASAN HILLS, QUEZON CITY | National Capital Region | Quezon City 1st DEO | Completed | ₱43.3M | 100% | Medium risk47 | —-0.096 |
| 28 | 23OF0047CONSTRUCTION OF FLOOD CONTROL STRUCTURES AT PANGILINAN, BRGY. TANDANG SORA, QUEZON CITY | National Capital Region | Quezon City 1st DEO | Completed | ₱28.8M | 100% | Medium risk47 | —-0.097 |
| 29 | 21OF0047REHABILITATION OF ROAD AT CUENCO STREET, QUEZON CITY | National Capital Region | Quezon City 1st DEO | Completed | ₱28.5M | 100% | Medium risk47 | —-0.099 |
| 30 | 17OB0103REHABILITATION OF DRAINAGE SYSTEM INCLUDING CURBS AND GUTTER AND SIDEWALK, AMANG RODRIGUEZ AVENUE, PASIG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱9.2M | 100% | Medium risk47 | —-0.065 |
| 31 | 17OB0173CONSTRUCTION OF MANGGAHAN FLOODWAY DRAINAGE OUTFALL (VIA OCTAGON STREET F. MARIANO STREET), PASIG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱7.2M | 100% | Medium risk47 | —-0.064 |
| 32 | 21OF0099WIDENING OF BRIDGE - PASONG TAMO BR. 2 (SB) (BO2355LZ) ALONG VISAYAS AVE., QUEZON CITY | National Capital Region | Quezon City 1st DEO | Completed | ₱14.3M | 100% | Medium risk47 | —-0.065 |
| 33 | 24DN0041FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BANGIAD CREEK (PACKAGE 3) TAYTAY, RIZAL (FIRST DISTRICT) | Region IV-A | Rizal 1st DEO | Completed | ₱29.4M | 100% | Medium risk47 | —-0.085 |
| 34 | 21OF0098WIDENNING OF BRIDGE - CULIAT BR. 3 (SB) (BO2356LZ) ALONG VISAYAS AVE., QUEZON CITY | National Capital Region | Quezon City 1st DEO | Completed | ₱9.5M | 100% | Medium risk47 | —-0.065 |
| 35 | 23DN0076FY 2023 DPWH INFRASTRUCTURE PROGRAM - BASIC INFRASTRUCTURE PROGRAM - FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES - CONSTRUCTION OF BREAKWATER, BARANGAY PIPINDAN BINANGONAN, RIZAL (FIRST DISTRICT) | Region IV-A | Rizal 1st DEO | Completed | ₱9.9M | 100% | Medium risk47 | —-0.091 |
| 36 | 19OF0145IMPROVEMENT OF MAYON STREET, QUEZON CITY | National Capital Region | Quezon City 1st DEO | Completed | ₱28.2M | 100% | Medium risk47 | —-0.097 |
| 37 | 24DN0042ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD ALONG WEST FLOODWAY PUROK 8 BAGONG PAG-ASA, BARANGAY STA. ANA TAYTAY, RIZAL (FIRST DISTRICT) | Region IV-A | Rizal 1st DEO | On-Going | ₱15.6M | 90% | Medium risk47 | —-0.064 |
| 38 | 22DN0137CONSTRUCTION OF ROAD, PUROK 2, BARANGAY SAPANG BINANGONAN, RIZAL (FIRST DISTRICT) | Region IV-A | Rizal 1st DEO | Completed | ₱19.6M | 100% | Medium risk47 | —-0.108 |
| 39 | 23OF0004PREVENTIVE MAINTENANCE OF ROAD: CONCRETE REBLOCKING - EPIFANIO DELOS SANTOS AVE. (EDSA) - K0012 + 786 - K0013 + 632, QUEZON CITY | National Capital Region | Quezon City 1st DEO | Completed | ₱21M | 100% | Medium risk46 | —-0.099 |
| 40 | 22OF0090REHABILITATION OF ROAD, DAPITAN STREET, QUEZON CITY | National Capital Region | Quezon City 1st DEO | Completed | ₱19.3M | 100% | Medium risk46 | —-0.100 |
| 41 | 18OF0070ROAD OMPROVEMENT OF SHORTHORN ST., BRGY. BAHAY TORO, Q.C. | National Capital Region | Quezon City 1st DEO | Completed | ₱14.3M | 100% | Medium risk46 | —-0.095 |
| 42 | 23DN0089ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD WITH DRAINAGE SYSTEM, RAINBOW VILLAGE (PHASE 3), BARANGAY KALAYAAN, ANGONO, RIZAL (FIRST DISTRICT) | Region IV-A | Rizal 1st DEO | Completed | ₱9.9M | 100% | Medium risk46 | —-0.108 |
| 43 | 22OF0024CONSTRUCTION OF FLOOD CONTROL STRUCTURES AND TRIBUTARIES ALONG CULIAT CREEK (LEFT SIDE) BARANGAY VASRA, QUEZON CITY | National Capital Region | Quezon City 1st DEO | Completed | ₱42.8M | 100% | Medium risk46 | —-0.087 |
| 44 | 21OF0055REHABILITATION OF ROAD, ROAD 20 EXTENSION, QUEZON CITY | National Capital Region | Quezon City 1st DEO | Completed | ₱19M | 100% | Medium risk46 | —-0.100 |
| 45 | 20OF0036CONSTRUCTION OF MAUBAN STREET, 000.000 TO 000.7000, QUEZON CITY | National Capital Region | Quezon City 1st DEO | Completed | ₱19M | 100% | Medium risk46 | —-0.100 |
| 46 | 24OF0033PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - STO. DOMINGO - K0007 + 484 - K0008 + 070, QUEZON CITY | National Capital Region | Quezon City 1st DEO | Completed | ₱16.2M | 100% | Medium risk46 | —-0.101 |
| 47 | 20OF0019CONSTRUCTION/ IMPROVEMENT OF FLOOD CONTROL STRUCTURE AT MATALAHIB CREEK, QUEZON CITY | National Capital Region | Quezon City 1st DEO | Completed | ₱30.2M | 100% | Medium risk46 | —-0.088 |
| 48 | 21OF0007PREVENTIVE MAINTENANCE OF ROAD: CONCRETE REBLOCKING - EPIFANIO DELOS SANTOS AVE., (EDSA), K0013+969 - K0014+247, QUEZON CITY | National Capital Region | Quezon City 1st DEO | Completed | ₱4.8M | 100% | Medium risk46 | —-0.098 |
| 49 | 19OF0030CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BRGY. BATASAN HILLS (PHASE 5), Q.C. | National Capital Region | Quezon City 1st DEO | Completed | ₱46.5M | 100% | Medium risk46 | —-0.076 |
| 50 | 24OB0094REHABILITATION OF DRAINAGE SYSTEM AND SITE DEVELOPMENT AT MUNTING BAHAYAN AND VICINITY, BARANGAY PINAGBUHATAN, PASIG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱14.4M | 100% | Medium risk46 | —-0.090 |