Contractor dossier
102 projects on file, including joint ventures this contractor is part of.
Total projects
102
Total budget
₱14.1B
Average progress
86.7%
Completion rate
59.8%
Below 70%
Average risk score
61.9
High risk on average, out of 100
Flagged as unusual
17
16.7% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region VIII | 31 | ₱6.2B | 68.2 | 11 | 77.9% |
| Region II | 17 | ₱1.7B | 56.3 | 0 | 100.0% |
| National Capital Region | 12 | ₱1.1B | 69.6 | 2 | 83.7% |
| Region IV-A | 12 | ₱1.3B | 64.5 | 0 | 67.8% |
| Region III | 9 | ₱589.3M | 48.0 | 0 | 91.2% |
| Region IV-B | 8 | ₱506.4M | 45.5 | 0 | 100.0% |
| Region I | 4 | ₱335.1M | 66.6 | 1 | 100.0% |
| Region VI | 4 | ₱443.1M | 54.9 | 2 | 97.1% |
| Central Office | 3 | ₱1.1B | 76.2 | 1 | 99.6% |
| Region V | 1 | ₱482.5M | 68.2 | 0 | 100.0% |
| Region XI | 1 | ₱193M | 57.8 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Flood Control and Drainage | 40 | ₱5.1B | 60.4 | 5 | 91.2% |
| Roads | 33 | ₱3.6B | 55.4 | 0 | 92.6% |
| Buildings and Facilities | 16 | ₱3.2B | 64.0 | 4 | 73.8% |
| OTHER | 10 | ₱2B | 77.6 | 7 | 75.5% |
| GAA 2025 OO-2 | 2 | ₱96.5M | 89.0 | 0 | 60.0% |
| GAA 2025 SSP | 1 | ₱49M | 93.8 | 1 | 82.9% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25OA0049CONSTRUCTION OF FLOOD MITIGATION STRUCTURE IN BARANGAY TANZA (PHASE 3), NAVOTAS CITY | National Capital Region | Malabon-Navotas DEO | On-Going | ₱49M | 83% | High risk94 | Flagged0.008 |
| 25OA0025CONSTRUCTION OF BOX CULVERT, E. RODRIGUEZ ST., BARANGAY TANZA 1, NAVOTAS CITY | National Capital Region | Malabon-Navotas DEO | On-Going | ₱47.5M | 29% | High risk89 | —-0.007 |
| 25OA0001CONSTRUCTION OF RIVERWALLS ALONG TANGOS RIVER, PHASE 4, NAVOTAS CITY | National Capital Region | Malabon-Navotas DEO | On-Going | ₱49M | 91% | High risk89 | —-0.020 |
| 24I00375BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING (SPORTS CENTER), TOLOSA, LEYTE | Region VIII | Region VIII | On-Going | ₱197.9M | 62% | High risk84 | Flagged0.030 |
| 24I00395SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - EVACUATION CENTERS/QUARANTINE FACILITIES/PUBLIC HEALTH FACILITIES - CONSTRUCTION (COMPLETION) OF EASTERN VISAYAS MEDICAL CENTER, CANCER CENTER, TACLOBAN CITY | Region VIII | Region VIII | On-Going | ₱482.2M | 24% | High risk84 | Flagged0.046 |
| 23I00128CLUSTER 5: PROJECT 1. BUILDINGS AND OTHER STRUCTURES - MULTIPURPOSE/FACILITIES - NATIONAL BUILDING PROGRAM - CONSTRUCTION OF THREE-STOREY BUILDING, DPWH REGIONAL OFFICE VIII, EQUIPMENT MANAGEMENT DIVISION, PHASE II, BARANGAY PAWING, PALO, LEYTE; PROJECT 2 | Region VIII | Region VIII | On-Going | ₱277.7M | 81% | High risk84 | Flagged0.044 |
| 24I00141CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - CONSTRUCTION OF MOTHER & CHILD AND OUT-PATIENT BUILDING OF SAMAR ISLAND MEDICAL CENTER, CALBAYOG CITY, SAMAR | Region VIII | Region VIII | On-Going | ₱385.9M | 59% | High risk84 | Flagged0.044 |
| 23I00131CONSTRUCTION OF NEW BILIRAN PROVINCIAL HOSPITAL BARANGAY LARRAZABAL, NAVAL, BILIRAN | Region VIII | Region VIII | On-Going | ₱222.9M | 87% | High risk83 | Flagged0.034 |
| 23IF0127CONSTRUCTION OF MULTI-PURPOSE BUILDING (CULTURAL CENTER), BRGY. JUATON, ORMOC CITY, LEYTE | Region VIII | Leyte 4th DEO | On-Going | ₱148.4M | 100% | High risk83 | Flagged0.022 |
| 17IK0001CLUSTER I - PREVENTIVE MAINT. WRIGHT OLD ROUTE, KO826+797-KO826+182; SAN JUANICO-BASEY-SOHOTON ROAD, KO896+290-KO900+500 & KO900+850-KO907+450; SAN JUANICO-BASEY-SOHOTON ROAD, KO909+278-KO909+422 | Region VIII | Samar 2nd DEO | Completed | ₱27.9M | 100% | High risk78 | —-0.035 |
| 17O00021CONSTRUCTION OF NAVOTAS COASTAL DIKE, NAVOTAS CITY, STA. 0+000 - STA. 0+(-425) (NAVOTAS TERMINAL) | Central Office | Flood Control Management Cluster | Completed | ₱183.9M | 100% | High risk77 | —-0.049 |
| 17Z00010RAISING OF FOLDER DIKE INCLUDING SLOPE PROTECTION WORKS (PHASE 4: STA 2+030 TO STA. 2+530, PHASE 5: STA. 5+720 TO STA. 5+200, PHASE 6) BRGY. DAMPALIT, MALABON CITY | Central Office | Flood Control Management Cluster | On-Going | ₱284.5M | 99% | High risk77 | Flagged0.014 |
| 25I00193BIP - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (SAMAR ISLAND MEDICAL CENTER BUILDING), CALBAYOG CITY, SAMAR | Region VIII | Region VIII | On-Going | ₱482.2M | 23% | High risk76 | Flagged0.025 |
| 17BD0024MF02: CONSTRUCTION OF FLOOD CONTROL SYSTEM, NAMABBALAN, TUGUEGARAO CITY, CAGAYAN | Region II | Cagayan 3rd DEO | Completed | ₱92M | 100% | High risk76 | —-0.010 |
| 17Z00006REHABILITATION OF DIKE SYSTEM ALONG SOLSONA RIVER (BREACHED AND ERODED DIKE, LEFT AND RIGHT BANK), LAOAG RIVER BASIN FLOOD CONTROL AND SABO PROJECT | Central Office | Flood Control Management Cluster | Completed | ₱669.3M | 100% | High risk75 | —-0.002 |
| 25CC0257CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY SAN MARCOS, CALUMPIT, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱14.5M | 73% | High risk74 | —-0.033 |
| 24CC0223CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY POBLACION, CALUMPIT, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱14.8M | 48% | High risk74 | —-0.017 |
| 16DE0187MFO-2 FLOOD MANAGEMENT SERVICES, CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEM, CONSTRUCTION/IMPROVEMENT OF FLOOD CONTROL STRUCTURE ALONG LOBO RIVERBANKS, POBLACION, LOBO, BATANGAS, 2ND LD | Region IV-A | Batangas 2nd DEO | Completed | ₱77.2M | 100% | High risk73 | —-0.052 |
| 16DE0186MFO-2 FLOOD MANAGEMENT SERVICES, CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEM, CONSTRUCTION/IMPROVEMENT OF FLOOD CONTROL STRUCTURE ALONG LOBO RIVERBANKS, TAYUMAN, LOBO, BATANGAS, 2ND LD | Region IV-A | Batangas 2nd DEO | Completed | ₱77.2M | 100% | High risk73 | —-0.052 |
| 24IL0106FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF SHORELINE PROTECTION STRUCTURE ALONG STO. ROSARIO - BUNGA, PADRE BURGOS, SOUTHERN LEYTE | Region VIII | Southern Leyte 1st DEO | On-Going | ₱125.3M | 31% | High risk72 | Flagged0.045 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24I00395SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - EVACUATION CENTERS/QUARANTINE FACILITIES/PUBLIC HEALTH FACILITIES - CONSTRUCTION (COMPLETION) OF EASTERN VISAYAS MEDICAL CENTER, CANCER CENTER, TACLOBAN CITY | Region VIII | Region VIII | On-Going | ₱482.2M | 24% | High risk84 | Flagged0.046 |
| 24IL0106FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF SHORELINE PROTECTION STRUCTURE ALONG STO. ROSARIO - BUNGA, PADRE BURGOS, SOUTHERN LEYTE | Region VIII | Southern Leyte 1st DEO | On-Going | ₱125.3M | 31% | High risk72 | Flagged0.045 |
| 24I00141CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - CONSTRUCTION OF MOTHER & CHILD AND OUT-PATIENT BUILDING OF SAMAR ISLAND MEDICAL CENTER, CALBAYOG CITY, SAMAR | Region VIII | Region VIII | On-Going | ₱385.9M | 59% | High risk84 | Flagged0.044 |
| 23I00128CLUSTER 5: PROJECT 1. BUILDINGS AND OTHER STRUCTURES - MULTIPURPOSE/FACILITIES - NATIONAL BUILDING PROGRAM - CONSTRUCTION OF THREE-STOREY BUILDING, DPWH REGIONAL OFFICE VIII, EQUIPMENT MANAGEMENT DIVISION, PHASE II, BARANGAY PAWING, PALO, LEYTE; PROJECT 2 | Region VIII | Region VIII | On-Going | ₱277.7M | 81% | High risk84 | Flagged0.044 |
| 24IL0105FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF SHORELINE PROTECTION STRUCTURE ALONG LUNGSODAAN - DINAHUGAN SECTION, PADRE BURGOS, SOUTHERN LEYTE | Region VIII | Southern Leyte 1st DEO | On-Going | ₱120.5M | 46% | High risk72 | Flagged0.042 |
| 23I00131CONSTRUCTION OF NEW BILIRAN PROVINCIAL HOSPITAL BARANGAY LARRAZABAL, NAVAL, BILIRAN | Region VIII | Region VIII | On-Going | ₱222.9M | 87% | High risk83 | Flagged0.034 |
| 24I00375BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING (SPORTS CENTER), TOLOSA, LEYTE | Region VIII | Region VIII | On-Going | ₱197.9M | 62% | High risk84 | Flagged0.030 |
| 25I00193BIP - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (SAMAR ISLAND MEDICAL CENTER BUILDING), CALBAYOG CITY, SAMAR | Region VIII | Region VIII | On-Going | ₱482.2M | 23% | High risk76 | Flagged0.025 |
| 23IF0127CONSTRUCTION OF MULTI-PURPOSE BUILDING (CULTURAL CENTER), BRGY. JUATON, ORMOC CITY, LEYTE | Region VIII | Leyte 4th DEO | On-Going | ₱148.4M | 100% | High risk83 | Flagged0.022 |
| 17AB0239REHABILITATION OF DIKE SYSTEM ALONG MADONGAN RIVER, (BREACHED & ERODED DIKE) RIGHT BANK, BRGY. BARESBES, DINGRAS, ILOCOS NORTE | Region I | Ilocos Norte 2nd DEO | Completed | ₱47.7M | 100% | High risk63 | Flagged0.015 |
| 22I00108CONSTRUCTION OF OFFICE OF CIVIL DEFENSE (OCD) REGIONAL OFFICE 8 BUILDING, GOVERNMENT CENTER, BRGY. CANDAHUG, PALO, LEYTE | Region VIII | Region VIII | On-Going | ₱216.2M | 16% | High risk69 | Flagged0.015 |
| 24OD0028CONSTRUCTION OF REINFORCED CONCRETE BOX CULVERT ALONG A. MABINI ST., CALOOCAN CITY | National Capital Region | Metro Manila 3rd DEO | On-Going | ₱94.3M | 52% | High risk68 | Flagged0.015 |
| 17Z00010RAISING OF FOLDER DIKE INCLUDING SLOPE PROTECTION WORKS (PHASE 4: STA 2+030 TO STA. 2+530, PHASE 5: STA. 5+720 TO STA. 5+200, PHASE 6) BRGY. DAMPALIT, MALABON CITY | Central Office | Flood Control Management Cluster | On-Going | ₱284.5M | 99% | High risk77 | Flagged0.014 |
| 21G00028CONSTRUCTION OF THREE-STOREY DPWH REGIONAL OFFICE VI BUILDING, FORT SAN PEDRO, ILOILO CITY | Region VI | Region VI | On-Going | ₱193M | 89% | High risk62 | Flagged0.014 |
| 25OA0049CONSTRUCTION OF FLOOD MITIGATION STRUCTURE IN BARANGAY TANZA (PHASE 3), NAVOTAS CITY | National Capital Region | Malabon-Navotas DEO | On-Going | ₱49M | 83% | High risk94 | Flagged0.008 |
| 19G00112CONSTRUCTION OF MUSEUM/AUDITORIUM, BACOLOD CITY, NEGROS OCCIDENTAL | Region VI | Region VI | Completed | ₱157.4M | 100% | High risk62 | Flagged0.007 |
| 24I00058REHABILITATION OF FLOOD CONTROL, PAGSANGA-AN RIVER, ORMOC CITY | Region VIII | Region VIII | On-Going | ₱274.3M | 65% | High risk67 | Flagged0.005 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 76 | 23OD0087CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG JACINTO CREEK AND ROBES CREEK, BARANGAY 175, CALOOCAN CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱85.3M | 100% | Medium risk53 | —-0.081 |
| 77 | 18EA0064REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE OF TIGWI-DAMPULAN-L | Region IV-B | Marinduque DEO | Completed | ₱92.7M | 100% | Medium risk52 | —-0.074 |
| 78 | 18C00026NETWORK DEVELOPMENT-CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, SAN ILDEFONSO-SAN RAFAEL BYPASS ROAD, INCLUDING ROW, BULACAN 3RD LEGISLATIVE DISTRICT, PROVINCE OF BULACAN | Region III | Region III | Completed | ₱126M | 100% | Medium risk50 | —-0.063 |
| 79 | 25OA0002CONSTRUCTION OF RIVERWALLS ALONG TANGOS RIVER, PHASE 5, NAVOTAS CITY | National Capital Region | Malabon-Navotas DEO | On-Going | ₱47.5M | 89% | Medium risk49 | —-0.051 |
| 80 | 18BB0017REHABILITATION/IMPROVEMENTS OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, IMPROVEMENTS OF FLOOD CONTROL SYSTEM, CAGAYAN RIVER BASIN, CHAINAGE 1114.80 - CHAINAGE 1493.20, BRGY. CASICALLAN NORTE, GATTARAN, CAGAYAN | Region II | Cagayan 1st DEO | Completed | ₱74.6M | 100% | Medium risk49 | —-0.032 |
| 81 | 18BB0016REHABILITATION/IMPROVEMENTS OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, IMPROVEMENTS OF FLOOD CONTROL SYSTEM, CAGAYAN RIVER BASIN, CHAINAGE 724.80 - CHAINAGE 1114.80, BRGY. CASICALLAN SUR, GATTARAN, CAGAYAN | Region II | Cagayan 1st DEO | Completed | ₱74.8M | 100% | Medium risk49 | —-0.032 |
| 82 | 18BB0015REHABILITATION/IMPROVEMENTS OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, IMPROVEMENTS OF FLOOD CONTROL SYSTEM, CAGAYAN RIVER BASIN, CHAINAGE 361.20 - CHAINAGE 724.80, BRGYS. CASICALLAN SUR, GATTARAN, CAGAYAN | Region II | Cagayan 1st DEO | Completed | ₱74.9M | 100% | Medium risk49 | —-0.043 |
| 83 | 18BB0014REHABILITATION/IMPROVEMENTS OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, IMPROVEMENTS OF FLOOD CONTROL SYSTEM,CAGAYAN RIVER BASIN,CHAINAGE 0 - CHAINAGE 361.20, BRGYS. L. ADVIENTO AND CASILLAN SUR, GATTARAN | Region II | Cagayan 1st DEO | Completed | ₱74.6M | 100% | Medium risk49 | —-0.044 |
| 84 | 18BB0019REHABILITATION/IMPROVEMENTS OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, IMPROVEMENTS OF FLOOD CONTROL SYSTEM, CAGAYAN RIVER BASIN, CHAINAGE 1827.20 - CHAINAGE 2209.60, BRGY. CASICALLAN NORTE, GATTARAN, CAGAYAN | Region II | Cagayan 1st DEO | Completed | ₱70.3M | 100% | Medium risk49 | —-0.032 |
| 85 | 18BB0018REHABILITATION/IMPROVEMENTS OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, IMPROVEMENTS OF FLOOD CONTROL SYSTEM, CAGAYAN RIVER BASIN, CHAINAGE 1493.20 - CHAINAGE 1827.20, BRGY. CASICALLAN NORTE, GATTARAN, CAGAYAN | Region II | Cagayan 1st DEO | Completed | ₱70M | 100% | Medium risk49 | —-0.032 |
| 86 | 18E00064CONSTRUCTION OF WHITE BEACH PORT, BRGY. POCTOY, STA. 0+072.00 TO STA. 0+195.00, TORRIJOS, MARINDUQUE | Region IV-B | Region IV-B | Completed | ₱28.5M | 100% | Medium risk49 | —-0.007 |
| 87 | 21GB0005CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG SIBALOM RIVER, BRGY. SAN PEDRO, SAN JOSE, ANTIQUE | Region VI | Antique DEO | Completed | ₱47.2M | 100% | Medium risk49 | —-0.069 |
| 88 | 18BB0034CONST./IMPROV'T OF ACCESS RDS LEADING TO TRADES, INDUSTRIES & ECONOMIC ZONES - DIORA-ZINUNGAN BRGY. RD LEADING TO DUGU SAN VICENTE ROAD IN SUPPORT OF AGRIBUSINESS (PINEAPPLE GROWERS), BRGY. ZINUNGAN, SANTA ANA, CAGAYAN | Region II | Cagayan 1st DEO | Completed | ₱91.7M | 100% | Medium risk48 | —-0.058 |
| 89 | 19EA0001ASSET PRESERVATION-PREVETIVE MAINTENANCE-SECONDARY ROADS, MARINDUQUE CIRCUMFERENTIAL ROAD (ASPHALT OVERLAY)-K0003+264-K0004+000, K0012+305-K0014+825, K0021+205-K0022+783 | Region IV-B | Marinduque DEO | Completed | ₱88.4M | 100% | Medium risk47 | —-0.082 |
| 90 | 18EA0068REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE OF MARINDUQUE CIRCUM | Region IV-B | Marinduque DEO | Completed | ₱70.7M | 100% | Medium risk47 | —-0.083 |
| 91 | 21DQ0063LOCAL PROGRAM - CONSTRUCTION / REPAIR / REHABILITATION / IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS - LOCAL ROADS AND BRIDGES - LOCAL ROADS - CONSTRUCTION OF ROAD CONNECTING BARANGAY LUMIL AND BARANGAY CABANGAAN, SILANG, CAVITE | Region IV-A | Cavite 3rd DEO | Terminated | ₱18.1M | 100% | Medium risk47 | —-0.080 |
| 92 | 19GB0019CONSTRUCTION OF REVETMENT - CONSTRUCTION OF REVETMENT ALONG SIBALOM RIVER BANTAYAN-SAN PEDRO-CUBAY ROAD, SAN JOSE, ANTIQUE | Region VI | Antique DEO | Completed | ₱45.5M | 100% | Medium risk46 | —-0.068 |
| 93 | 18BB0001ASSET PRESERVATION PROGRAM-PREVENTIVE MAINTENANCE-PRIMARY ROAD CAGAYAN VALLEY ROAD K0541+000 - K0542+009, K0543+531 - K0543+731, K0547+750 - K0548+616, BRGYS. DUMMUN AND L. ADVIENTO, GATTARAN, CAGAYAN (S00887LZ) | Region II | Cagayan 1st DEO | Completed | ₱18.7M | 100% | Medium risk44 | —-0.067 |
| 94 | 18BB0002ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROAD CAGAYAN VALLEY ROAD K0570+745 K0575+584.10, DACALLA FUGU CATOTORAN, CAMALANIUGAN, CAGAYAN (S00662LZ) | Region II | Cagayan 1st DEO | Completed | ₱37.6M | 100% | Medium risk43 | —-0.063 |
| 95 | 19CD0016CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG BULO RIVER PHASE XIX, SAN MIGUEL, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱91.5M | 100% | Medium risk42 | —-0.080 |
| 96 | 20EA0017CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF BAMBAN FLOOD CONTROL BOAC, MARINDUQUE | Region IV-B | Marinduque DEO | Completed | ₱48.6M | 100% | Medium risk40 | —-0.066 |
| 97 | 20EA0008ASSET PRESERVATION - PREVENTIVE MAINTENANCE - SECONDARY ROADS, MARINDUQUE CIRCUMFERENTIAL RD - K0077+000 - K0078+511, TORRIJOS, MARINDUQUE | Region IV-B | Marinduque DEO | Completed | ₱30.4M | 100% | Medium risk38 | —-0.094 |
| 98 | 20EA0030CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURE AND DRAINAGE SYSTEMS, CONSTRUCTION OF NANGKA II FLOOD CONTROL MOGPOG, MARINDUQUE | Region IV-B | Marinduque DEO | Completed | ₱38M | 100% | Medium risk37 | —-0.069 |
| 99 | 18C00005NETWORK DEVELOPMENT PROGRAM-ROAD WIDENING-PRIMARY ROADS, DAANG MAHARLIKA (LZ) INCLUDING ROW, BULACAN 2ND LEGISLATIVE DISTRICT, PROVINCE OF BULACAN | Region III | Region III | Terminated | ₱49.1M | 100% | Medium risk37 | —-0.059 |
| 100 | 18C00004NETWORK DEVELOPMENT PROGRAM-ROAD WIDENING-PRIMARY ROADS, DAANG MAHARLIKA (LZ) INCLUDING ROW, BULACAN 2ND LEGISLATIVE DISTRICT, PROVINCE OF BULACAN | Region III | Region III | Terminated | ₱41.4M | 100% | Medium risk34 | —-0.060 |