Contractor dossier
77 projects on file, including joint ventures this contractor is part of.
Total projects
77
Total budget
₱1B
Average progress
99.8%
Completion rate
97.4%
Average risk score
33.2
Medium risk on average, out of 100
Flagged as unusual
1
1.3% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region XI | 71 | ₱940.4M | 34.1 | 1 | 99.8% |
| Region X | 5 | ₱25.6M | 20.2 | 0 | 100.0% |
| Region XIII | 1 | ₱39.2M | 38.0 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 41 | ₱263.6M | 22.4 | 0 | 99.8% |
| Roads | 26 | ₱408M | 41.7 | 0 | 100.0% |
| Bridges | 5 | ₱148M | 44.2 | 0 | 100.0% |
| OTHER | 4 | ₱141.5M | 71.3 | 1 | 98.6% |
| Flood Control and Drainage | 1 | ₱44.1M | 50.1 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25LC0064CONCRETING OF BRGY. KIPALILI FMR, BRGY. KIPALILI, SAN ISIDRO, DAVAO DEL NORTE | Region XI | Davao del Norte DEO | On-Going | ₱14.9M | 94% | High risk86 | Flagged0.053 |
| 18LC0031CONSTRUCTION CONCRETE ROAD JCT. AGUSAN-DAVAO ROAD, BRGY. CANOCOTAN TO JCT. SURIGAO DAVAO COASTAL ROAD LEADING TO BANANA BEACH, LANIKAI BEACH RESORT & HIJO PORT ( BRIDGE REHABILITATION) TAGUM CITY, DAVAO DEL NORTE | Region XI | Davao del Norte DEO | Completed | ₱50.4M | 100% | High risk77 | —-0.024 |
| 18LC0017WIDENING OF STO. NIÑO BRIDGE 2 ( B01120MN ) ALONG KAPALONG- TALAINGOD-VALENCIA ( BUKIDNONO ) ROAD INCL. RROW, DAVAO DEL NORTE | Region XI | Davao del Norte DEO | Completed | ₱37.1M | 100% | High risk72 | —-0.027 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 51 | 17LA0350CONSTRUCTION OF ONE (1) UNIT, TWO (2) STOREY, SIX (6) CLASSROOM BUILDING @ MAWAB CES, MAWAB, COMPOSTELA VALLEY PROVINCE | Region XI | Davao de Oro 1st DEO | Completed | ₱13.8M | 100% | Low risk18 | —-0.013 |
| 52 | 17LA0233CONSTRUCTION OF TWO (2) UNITS, UNIQUE TECHNICAL AND VOCATIONAL FACILITIES/WORKSHOP BUILDING AT:CW1. ANDILI NHS, MAWABCONSTRUCTION OF ONE (1) UNIT, UNIQUE TECHNICAL AND VOCATIONAL FACILITIES/WORKSHOP BUILDING AT:CW2. LORENZO S. SARMIENTO NHS, MAWAB | Region XI | Davao de Oro 1st DEO | Completed | ₱12.1M | 100% | Low risk18 | —-0.014 |
| 53 | 17LA0338CONSTRUCTION OF ONE (1) UNIT, THREE (3) STOREY, TWELVE (12) CLASSROOM BUILDING @ NUEVO ILOCO NHS, MAWAB, COMPOSTELA VALLEY PROVINCE | Region XI | Davao de Oro 1st DEO | Completed | ₱29.1M | 100% | Low risk18 | —-0.002 |
| 54 | 17LA0265CONSTRUCTION OF ONE (1) UNIT, UNIQUE TECHNICAL AND VOCATIONAL FACILITIES/WORKSHOP BUILDING AT:CW1. ELIZALDE NHS, MACO CW2. NEW LEYTE NHS, MACOCOMPOSTELA VALLEY PROVINCE | Region XI | Davao de Oro 1st DEO | Completed | ₱8.5M | 100% | Low risk18 | —-0.013 |
| 55 | 17LC0379CONSTRUCTION OF 3 STY - 6 CL SCHOOL BUILDING AT SUAYBAGUIO RIÑA ES, TAGUM CITY, DAVAO DEL NORTE | Region XI | Davao del Norte DEO | Completed | ₱16.1M | 100% | Low risk18 | —-0.015 |
| 56 | 17LA0212CONSTRUCTION OF ONE (1) UNIT, ONE (1) STOREY, FOUR (4) CLASSROOM BUILDING AT GUISOK PS, MAWAB, COMPOSTELA VALLEY PROVINCE | Region XI | Davao de Oro 1st DEO | Completed | ₱5.5M | 100% | Low risk18 | —-0.014 |
| 57 | 17LC0519CONSTRUCTION OF 2 STY - 4 CL SCHOOL BUILDING (COMPUTER (ICT) LAB) AT SOUTHERN DAVAO NHS, CITY OF PANABO, DAVAO DEL NORTE | Region XI | Davao del Norte DEO | Completed | ₱8.9M | 100% | Low risk18 | —-0.019 |
| 58 | 17LC0520CONSTRUCTION OF 2 STY - 4 CL SCHOOL BUILDING (SCIENCE LABORATORY) AT SOUTHERN DAVAO NHS, CITY OF PANABO, DAVAO DEL NORTE | Region XI | Davao del Norte DEO | Completed | ₱9.4M | 100% | Low risk18 | —-0.019 |
| 59 | 17LA0244CONSTRUCTION OF ONE (1) UNIT, ONE (1) STOREY, TWO (2) CLASSROOM BUILDING AT:CW1. NUEVO ILOCO ES, MAWABCW2. SALVACION ES, MAWABCOMPOSTELA VALLEY PROVINCE | Region XI | Davao de Oro 1st DEO | Completed | ₱6.2M | 100% | Low risk18 | —-0.014 |
| 60 | 17LA0215CONSTRUCTION OF ONE (1) UNIT, ONE (1) STOREY, TWO (2) CLASSROOM BUILDING AT:CW1.TABONTABON ES, MAWABCW2. TUBORAN ES, MAWABCOMPOSTELA VALLEY PROVINCE | Region XI | Davao de Oro 1st DEO | Completed | ₱6.1M | 100% | Low risk18 | —-0.013 |
| 61 | 18LA0287CONSTRUCTION OF A MULTI-PURPOSE BUILDING, NABUNTURAN NATIONAL COMPREHENSIVE HIGH SCHOOL, NABUNTURAN, COMPOSTELA VALLEY PROVINCE | Region XI | Davao de Oro 1st DEO | Completed | ₱4M | 100% | Low risk16 | —-0.086 |
| 62 | 19LA0496CONSTRUCTION OF MPB 721B TUBURAN, MAWAB, COMPOSTELA VALLEY PROVINCE | Region XI | Davao de Oro 1st DEO | Completed | ₱2.9M | 100% | Low risk16 | —-0.086 |
| 63 | 20LA0300IMPROVEMENT OF MPB (GYM) LINDA, NABUNTURAN COMPOSTELA VALLEY | Region XI | Davao de Oro 1st DEO | Completed | ₱2.9M | 100% | Low risk15 | —-0.088 |
| 64 | 18LA0187CONSTRUCTION OF GYM WITH BLEACHER, LORENZO NHS, MAWAB, COMPOSTELA VALLEY PROVINCE | Region XI | Davao de Oro 1st DEO | Completed | ₱2.9M | 100% | Low risk15 | —-0.088 |
| 65 | 21LC0151CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY DEL MONTE, IGACOS, DAVAO DEL NORTE | Region XI | Davao del Norte DEO | Completed | ₱2M | 100% | Low risk13 | —-0.087 |
| 66 | 19KB0099CONSTRUCTION OF MULTI-PURPOSE BUILDING (SOLAR DRIER WITH WAREHOUSE), BRGY LUMINTAO, QUEZON, BUKIDNON | Region X | Bukidnon 2nd DEO | Completed | ₱2M | 100% | Low risk11 | —-0.094 |
| 67 | 19KB0040CONSTRUCTION OF MULTI-PURPOSE BUILDING (SOLAR DRIER WITH WAREHOUSE), BARANGAY LABUAGON, KIBAWE, BUKIDNON | Region X | Bukidnon 2nd DEO | Completed | ₱2M | 100% | Low risk11 | —-0.094 |
| 68 | 19LA0264CONSTRUCTION OF MULTI-PURPOSE BUILDING (BLEACHER) AT BARANGAY CONCEPCION, MONTEVISTA, COMPOSTELA VALLEY PROVINCE | Region XI | Davao de Oro 1st DEO | Completed | ₱1.8M | 100% | Low risk10 | —-0.087 |
| 69 | 18LC0102CONSTRUCTION OF MPB ( DAY CARE CENTER ) BRGY. BINANCIAN, ASUNCION, DAVAO DEL NORTE | Region XI | Davao del Norte DEO | Completed | ₱1.5M | 100% | Low risk10 | —-0.085 |
| 70 | 18LC0131CONSTRUCTION OF MULTI-PURPOSE BUILDING ( GYM STAGE ),BUSAON ELEMENTARY SCHOOL,BRGY.BUSAON,TAGUM CITY,DAVAO DEL NORTE | Region XI | Davao del Norte DEO | Completed | ₱1.5M | 100% | Low risk10 | —-0.091 |
| 71 | 17LA0147CONSTRUCTION BRGY. HALL IN BRGY. LEBANON, MUNICIPALITY OF MONTEVISTACOMPOSTELA VALLEY PROVINCE | Region XI | Davao de Oro 1st DEO | Completed | ₱1.7M | 100% | Low risk8 | —-0.055 |
| 72 | 17LA0054CONSTRUCTION OF ONE (1) UNIT, ONE (1) STOREY, TWO (2) CLASSROOM BUILDING @ PANTUKAN ES, PANTUKAN, COMPOSTELA VALLEY PROVINCE | Region XI | Davao de Oro 1st DEO | Completed | ₱1.6M | 100% | Low risk8 | —-0.056 |
| 73 | 17LA0057CONSTRUCTION OF ONE (1) UNIT, ONE (1) STOREY, TWO (2) CLASSROOM BUILDING @ TIBAGON ES, PANTUKAN, COMPOSTELA VALLEY PROVINCE | Region XI | Davao de Oro 1st DEO | Completed | ₱1.6M | 100% | Low risk8 | —-0.059 |
| 74 | 17LA0088CONSTRUCTION OF MPB, MUSLIM ELDERS BLDG. MATIAO, PANTUKAN, COMPOSTELA VALLEY PROVINCE | Region XI | Davao de Oro 1st DEO | Completed | ₱1.5M | 100% | Low risk8 | —-0.055 |
| 75 | 17LC0313CONSTRUCTION OF 1 STY-2 CL SCHOOL BLDG. AT CABIDIANAN ES, NEW CORELLA, DAVAO DEL NORTE | Region XI | Davao del Norte DEO | Completed | ₱2.8M | 100% | Low risk4 | —-0.014 |