Opening the dossier…
Opening the dossier…
Contractor dossier
75 projects on file, including joint ventures this contractor is part of.
Total projects
75
Total budget
₱513.3M
Average progress
97.2%
Completion rate
93.3%
Average risk score
29.4
Low risk on average, out of 100
Flagged as unusual
0
0.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region III | 54 | ₱203M | 24.1 | 0 | 98.6% |
| National Capital Region | 21 | ₱310.2M | 42.8 | 0 | 93.7% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 31 | ₱158M | 25.3 | 0 | 95.0% |
| Roads | 19 | ₱111.4M | 32.2 | 0 | 99.5% |
| Flood Control and Drainage | 14 | ₱209M | 37.9 | 0 | 96.9% |
| Bridges | 10 | ₱32.9M | 25.2 | 0 | 100.0% |
| OTHER | 1 | ₱1.9M | 25.5 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25CC0183CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY BUNGAHAN, MALOLOS CITY, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱9.7M | 23% | High risk73 | —-0.017 |
| 24CC0435CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING OF VIRGINIA RAMIREZ-CRUZ NATIONAL HIGH SCHOOL, BARANGAY SILING BATA, PANDI, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱4.9M | 100% | High risk72 | —-0.075 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
Nothing to report.
No flagged projects here.
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 26 | 17CD0084CONSTRUCTION/COMPLETION OF MULTI-PURPOSE BUILDING BARANGAY CAMALIG, MEYCAUAYAN CITY, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱2.3M | 100% | Medium risk34 | —-0.073 |
| 27 | 17CD0200CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. LOMA DE GATO, MARILAO, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱2.8M | 100% | Medium risk33 | —-0.074 |
| 28 | 17CD0104IMPROVEMENT / REPAIR / REHABILITATION OF EXISTING MULTI - PURPOSE (PWD HALL), BARANGAY KAYPIAN, SAN JOSE DEL MONTE, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱2.8M | 100% | Medium risk33 | —-0.074 |
| 29 | 19CD0267CONSTRUCTION/IMPROVEMENT/REHABILITATION OF SLOPE PROTECTION LEADING TO RELOCATION SITES, BRGY. BAGONG BUHAY, SAN PEDRO AND CITRUS, SAN JOSE DEL MONTE CITY, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱9.3M | 100% | Medium risk33 | —-0.093 |
| 30 | 18CD0123RETROFITTING/STRENGTHENING OF PERMANENT BRIDGE SAPANG BULAC BR.(B04462LZ) ALONG EASTERN BULACAN ROAD, DOÑA REMEDIOS TRINIDAD,BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱5.1M | 100% | Medium risk32 | —-0.064 |
| 31 | 18CD0122RETROFITTING/STRENGTHENING OF PERMANENT BRIDGE SAN MIGUEL BR. (B01685LZ) ALONG STA. RITA - CAMIAS OLD ROAD, SAN MIGUEL, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱5.1M | 100% | Medium risk31 | —-0.064 |
| 32 | 17CD0071RETROFITTING / STRENGTHENING OF PERMANENT BRIDGES, SALCERO BR. (B03204LZ) ALONG GEN. ALEJO SANTOS HIGHWAY, ANGAT, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱2.2M | 100% | Low risk29 | —-0.038 |
| 33 | 17CD0069RETROFITTING / STRENGTHENING OF PERMANENT BRIDGES, PANGARAYUMAN BR. 1 (B01687LZ) ALONG SIBUL-BIAK-NA-BATO RD., SAN MIGUEL, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱2.5M | 100% | Low risk29 | —-0.038 |
| 34 | 17CD0070RETROFITTING / STRENGTHENING OF PERMANENT BRIDGES, SABANG BR. (B01667LZ) ALONG OLD CAGAYAN VALLEY RD., SAN RAFAEL, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱2.7M | 100% | Low risk29 | —-0.038 |
| 35 | 17CD0068RETROFITTING / STRENGTHENING OF PERMANENT BRIDGES, CAMACHILE BR. 1 (B04460LZ) ALONG EASTERN BULACAN RD., DOÑA REMEDIOS TRINIDAD, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱2.7M | 100% | Low risk28 | —-0.038 |
| 36 | 17CD0067RETROFITTING / STRENGTHENING OF PERMANENT BRIDGES, BALAONG BR. (B01690LZ) ALONG SIBUL-BIAK-NA-BATO RD., SAN MIGUEL, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱2.6M | 100% | Low risk28 | —-0.038 |
| 37 | 17CD0106CONCRETING OF ROAD, BRGY. BINAGBAG, ANGAT, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱1.9M | 100% | Low risk28 | —-0.065 |
| 38 | 17CD0105CONCRETING OF TAIWAN ROAD, BRGY. STA. LUCIA, ANGAT, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱1.9M | 100% | Low risk28 | —-0.066 |
| 39 | 17CD0149CONSTRUCTION OF SLOPE PROTECTION/DRAINAGE, SITIO IBAYO, PULONG BUHANGIN, STA. MARIA, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱1.9M | 100% | Low risk26 | —-0.060 |
| 40 | 17CD0130CONSTRUCTION OF ROAD, ABANGAN NORTE, MARILAO, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱1.9M | 100% | Low risk26 | —-0.038 |
| 41 | 21OA0018REHABILITATION OF ROAD, ROAD II, BRGY. SAN RAFAEL VILL. NAVOTAS CITY | National Capital Region | Malabon-Navotas DEO | Completed | ₱3.9M | 100% | Low risk25 | —-0.099 |
| 42 | 18CD0289REHABILITATION / CONCRETING OF BRGY. PULONG BUHANGIN FMR, BRGY. PULONG BUHANGIN, STA. MARIA, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱4.8M | 100% | Low risk25 | —-0.048 |
| 43 | 20CC0276IMPROVEMENT OF LOCAL ROAD INCLUDING DRAINAGE, POBLACION, BALIUAG, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱4.8M | 100% | Low risk24 | —-0.048 |
| 44 | 22OA0095REHABILITATION (COMPLETION) OF SPINE CANAL, NAVOTAS CITY | National Capital Region | Malabon-Navotas DEO | Completed | ₱2M | 100% | Low risk23 | —-0.088 |
| 45 | 17CD0234REPAIR/REHABILITATION AND CONSTRUCTION OF SITIO BATO GUYONG FMR, BRGY. GUYONG, STA. MARIA, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱1.9M | 100% | Low risk20 | —-0.012 |
| 46 | 19CD0269CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BRGY. PATUBIG, MARILAO, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱4.7M | 100% | Low risk20 | —-0.108 |
| 47 | 21OA0037REHABILITATION OF ROAD, KALAKAL ST. TO FRANCISCO ST., BRGY. SAN RAFAEL VILLAGE, NAVOTAS CITY | National Capital Region | Malabon-Navotas DEO | Completed | ₱1.9M | 100% | Low risk20 | —-0.098 |
| 48 | 17CD0172CONSTRUCTION OF MULTI-PURPOSE BUILDING (DAY CARE/SENIOR CITIZEN CENTER), ABANGAN SUR, MARILAO, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱1.9M | 100% | Low risk20 | —-0.074 |
| 49 | 17CD0063CONSTRUCTION/COMPLETION OF MULTI-PURPOSE BUILDING BRGY. HULO, OBANDO, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱1.9M | 100% | Low risk20 | —-0.074 |
| 50 | 17CD0208REHABILITATION / IMPROVEMENT OF PUROK PALAYAN FMR, BRGY. DONACION, ANGAT, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱1.9M | 100% | Low risk20 | —-0.012 |