Contractor dossier
105 projects on file, including joint ventures this contractor is part of.
Total projects
105
Total budget
₱1.6B
Average progress
99.0%
Completion rate
85.7%
Average risk score
45.8
Medium risk on average, out of 100
Flagged as unusual
0
0.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region VI | 39 | ₱893.5M | 45.4 | 0 | 99.8% |
| Region V | 27 | ₱275.2M | 53.4 | 0 | 96.3% |
| Cordillera Administrative Region | 10 | ₱67.1M | 45.9 | 0 | 100.0% |
| Region IX | 7 | ₱127.9M | 54.5 | 0 | 100.0% |
| Region X | 6 | ₱80.8M | 40.7 | 0 | 100.0% |
| Region IV-B | 6 | ₱59.4M | 27.0 | 0 | 100.0% |
| Region III | 5 | ₱18.6M | 26.6 | 0 | 100.0% |
| Region VIII | 3 | ₱69.8M | 48.2 | 0 | 100.0% |
| Region I | 1 | ₱12.7M | 52.0 | 0 | 100.0% |
| Region VII | 1 | ₱1.6M | 19.0 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Bridges | 103 | ₱1.5B | 45.7 | 0 | 98.9% |
| Buildings and Facilities | 2 | ₱67.5M | 47.3 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
Nothing to report.
No flagged projects here.
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 76 | 18GF0002RETROFITTING OF SIWARAGAN BRIDGE (B00140PN) ALONG ILOILO-ANTIQUE ROAD (K0055+725), SAN JOAQUIN, ILOILO | Region VI | Iloilo 1st DEO | Completed | ₱12.8M | 100% | Medium risk46 | —-0.054 |
| 77 | 18KB0014REHABILITATION/MAJOR REPAIR OF PERMANENT BRIDGES, MANUTO BRIDGE (B01380MN) ALONG BUKIDNON-DAVAO CITY ROAD | Region X | Bukidnon 2nd DEO | Completed | ₱5.1M | 100% | Medium risk46 | —-0.059 |
| 78 | 20GB0015TALISAYAN BR. (B00415PN) ALONG ANINI-Y TOBIAS-FORNIER RD BRGY. TALISAYAN, ANINI-Y, ANTIQUE | Region VI | Antique DEO | Completed | ₱9.6M | 100% | Medium risk46 | —-0.052 |
| 79 | 19GF0014REHABILITATION/MAJOR REPAIR OF PERMANENT BRIDGE-SINUGBUHAN BR. (B00506PN) ALONG TIOLAS-SINUGBUHAN ROAD, SAN JOAQUIN, ILOILO | Region VI | Iloilo 1st DEO | Completed | ₱7M | 100% | Medium risk46 | —-0.053 |
| 80 | 18GI0022REHABILITATION/MAJOR REPAIR OF BRIDGE - AGANAN BR. (NEW) (B00500PN) ALONG SEN. BENIGNO S. AQUINO, JR. AVE | Region VI | Iloilo 4th DEO | Completed | ₱9M | 100% | Medium risk45 | —-0.053 |
| 81 | 18GB0212REHABILITATION OF OLD PROVINCIAL CAPITOL (PHASE 2), SAN JOSE DE BUENAVISTA, ANTIQUE | Region VI | Antique DEO | Completed | ₱28.7M | 100% | Medium risk45 | —-0.029 |
| 82 | 17KB0002RETROFITTING/STRENGTHENING OF PERMANENT BRIDGES (5 CLUSTERED PROJECTS) | Region X | Bukidnon 2nd DEO | Completed | ₱18.2M | 100% | Medium risk41 | —-0.041 |
| 83 | 23EA0018RETROFITTING/STRENGTHENING OF PERMANENT BRIDGES, LIBTANGIN BR. (B00024MQ) ALONG MARINDUQUE CIRCUMFERENTIAL RD | Region IV-B | Marinduque DEO | Completed | ₱39.2M | 100% | Medium risk40 | —-0.056 |
| 84 | 23EA0020RETROFITTING/ STRENGTHENING OF PERMANENT BRIDGES, MATUYATUYA BR. (B00007MQ) ALONG MARINDUQUE CIRCUMFERENTIAL RD | Region IV-B | Marinduque DEO | Completed | ₱9.6M | 100% | Medium risk38 | —-0.054 |
| 85 | 18CN0058RETROFITTING/STRENGTHENING OF PERMANENT BRIDGES, DIABUYO BR. (B02830LZ) ALONG NUEVA ECIJA-AURORA ROAD | Region III | Aurora DEO | Completed | ₱5.6M | 100% | Medium risk38 | —-0.063 |
| 86 | 25FF0004001;ENSURE SAFE & RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-BRIDGE PROG.-RETROFITTING/STRENGHTENING OF PERMANENT BRIDGES-BAYAWASON BR.(B00428LZ)ALONG NAGA CITY BOUNDARY-CALABANGA BALONGAY RD,CALABANGA CAM. SUR | Region V | Camarines Sur 3rd DEO | On-Going | ₱4.5M | 0% | Medium risk36 | —-0.014 |
| 87 | 19CN0015RETROFITTING/STRENGTHENING OF DIMANI BR. (B02824LZ) ALONG NUEVA ECIJA-AURORA RD | Region III | Aurora DEO | Completed | ₱5.9M | 100% | Medium risk34 | —-0.065 |
| 88 | 17FI0016CONSTRUCTION AND MAINTENANCE OF BRIDGES ALONG NATIONAL ROADS RETROFITTING/STRENGTHENING OF PERMANENT | Region V | Masbate 2nd DEO | Completed | ₱4.2M | 100% | Medium risk33 | —-0.031 |
| 89 | 17GG0046CONSTRUCTION / MAINTENANCE OF BRIDGE ALONG NATIONAL ROADS, RETROFITTING / STRENGTHENING OF PERMANENT BRIDGES - ABANGAY BRIDGE (B00065PN) ALONG ILOILO - CAPIZ ROAD (OLD ROUTE), JANIUAY, ILOILO | Region VI | Iloilo 2nd DEO | Completed | ₱2.2M | 100% | Medium risk32 | —-0.028 |
| 90 | 21PC0002BRIDGE PROGRAM-RETROFITTING/STRENGTHENING OF PERMANENT BRIDGES CARMELA BRIDGE (B01051LZ) ALONG CLAVERIA-CALANASAN-KABUGAO ROAD CALANASAN, APAYAO | Cordillera Administrative Region | Apayao 2nd DEO | Completed | ₱4.3M | 100% | Medium risk32 | —-0.039 |
| 91 | 23PK0042ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: BRIDGE PROGRAM - RETROFITTING/STRENGTHENING OF PERMANENT BRIDGES: GADAY BRIDGE (B04381LZ) ALONG KALINGA-ABRA ROAD. PASIL, KALINGA | Cordillera Administrative Region | Upper Kalinga DEO | Completed | ₱3.9M | 100% | Medium risk32 | —-0.043 |
| 92 | 16GB0166CONSTRUCTION AND MAINTENANCE OF BRIDGES ALONG NATIONAL ROADS: REHABILITATION/MAJOR REPAIR OF PERMANE | Region VI | Antique DEO | Completed | ₱2.8M | 100% | Medium risk31 | —-0.027 |
| 93 | 20GB0014IRRIGATION BR. (B00460PN) ALONG ALANGAN-CUBAY-SIBALOM RD. DISTRICT I, SIBALOM, ANTIQUE | Region VI | Antique DEO | Completed | ₱2.9M | 100% | Low risk25 | —-0.052 |
| 94 | 21EB0040RETROFITTING/STRENGTHENING OF BRIDGE - MONTECLARO BR. (B00143MR) ALONG JCT MWCR (LABANGAN)-MURTHA-JCT IRIRON | Region IV-B | Mindoro Occidental DEO | Completed | ₱3.9M | 100% | Low risk23 | —-0.050 |
| 95 | 16GB0163CONSTRUCTION AND MAINTENANCE OF BRIDGES ALONG NATIONAL ROAD: REHABILITATION/MAJOR REPAIR OF PERMANEN | Region VI | Antique DEO | Completed | ₱1.4M | 100% | Low risk23 | —-0.027 |
| 96 | 19CN0016RETROFITTING/STRENGTHENING OF DIPAWAN BRIDGE (B02825LZ) ALONG NUEVA ECIJA-AURORA RD | Region III | Aurora DEO | Completed | ₱2.9M | 100% | Low risk22 | —-0.065 |
| 97 | 20EG0011RETROFITTING/ STRENGTHENING OF PERMANENT BRIDGES - BINDUYAN BR. (B00104PW) ALONG PUERTO PRINCESA NORTH ROAD, PUERTO PRINCESA CITY, PALAWAN | Region IV-B | Palawan 3rd DEO | Completed | ₱2.4M | 100% | Low risk21 | —-0.037 |
| 98 | 20EG0012RETROFITTING/ STRENGTHENING OF PERMANENT BRIDGES - CONCEPCION BR. (B00101PW) ALONG PUERTO PRINCESA NORTH ROAD, PUERTO PRINCESA CITY | Region IV-B | Palawan 3rd DEO | Completed | ₱2.4M | 100% | Low risk21 | —-0.037 |
| 99 | 17CH0008REHABILITATION/MAJOR REPAIR OF PERMANENT BRIDGE SAN JUAN BR. #1 (B01519LZ) ALONG SAN FERNANDO-LUBAO | Region III | Pampanga 2nd DEO | Completed | ₱1.9M | 100% | Low risk21 | —-0.036 |
| 100 | 20GB0012BARANGBANG BR. (B00393PN) ALONG ODIONG-SIBALOM SAN REMIGIO-LEON RD. BRGY. BARANGBANG, SAN REMIGIO, A | Region VI | Antique DEO | Completed | ₱1.2M | 100% | Low risk20 | —-0.051 |