Contractor dossier
936 projects on file, including joint ventures this contractor is part of.
Total projects
936
Total budget
₱59.2B
Average progress
91.5%
Completion rate
75.7%
Average risk score
54.0
Medium risk on average, out of 100
Flagged as unusual
90
9.6% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region II | 698 | ₱36.5B | 52.5 | 74 | 93.2% |
| Region I | 64 | ₱5.9B | 63.9 | 4 | 92.8% |
| Cordillera Administrative Region | 62 | ₱5.4B | 56.9 | 4 | 94.7% |
| Region III | 36 | ₱3.3B | 47.2 | 0 | 96.6% |
| Region IV-B | 30 | ₱3.2B | 55.5 | 3 | 65.7% |
| Region IV-A | 16 | ₱1.7B | 60.4 | 0 | 77.1% |
| National Capital Region | 13 | ₱1B | 65.6 | 2 | 55.7% |
| Region VII | 6 | ₱655.8M | 65.1 | 1 | 86.3% |
| Region V | 5 | ₱765.6M | 64.0 | 1 | 58.5% |
| Region VIII | 3 | ₱633.9M | 65.1 | 0 | 100.0% |
| Negros Island Region | 2 | ₱87.6M | 46.5 | 0 | 100.0% |
| Region XII | 1 | ₱73.8M | 77.1 | 1 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 378 | ₱23.6B | 51.4 | 13 | 91.7% |
| Flood Control and Drainage | 243 | ₱17.1B | 53.8 | 7 | 95.9% |
| Buildings and Facilities | 120 | ₱4.2B | 46.7 | 2 | 96.7% |
| Bridges | 117 | ₱8.7B | 53.7 | 27 | 88.3% |
| OTHER | 25 | ₱2.2B | 79.6 | 13 | 81.6% |
| GAA 2025 SSP | 20 | ₱1.1B | 95.0 | 20 | 57.4% |
| Water Provision and Storage | 17 | ₱586.6M | 54.3 | 0 | 99.0% |
| GAA 2025 OO-1 | 7 | ₱960.1M | 92.9 | 6 | 45.5% |
| GAA 2025 OO-2 | 5 | ₱400.6M | 91.4 | 2 | 74.5% |
| Bridges, Roads | 4 | ₱370.8M | 59.5 | 0 | 52.7% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25BE0021CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR STRATEGIC PUBLIC BUILDINGS/ FACILITIES-REHABILITATION OF POBLACION 1-DIVISORIA | Region II | Isabela 1st DEO | On-Going | ₱112.9M | 71% | High risk97 | Flagged0.030 |
| 25A00519SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), REHABILITATION OF FLOOD CONTROL STRUCTURE, DRAINAGE STRUCTURE AND SMALL WATER IMPOUNDING PROJECT (SWIP), BARANGAY 20, SAN PABLO, SAN NICOLAS, ILOCOS NORTE | Region I | Region I | On-Going | ₱140.4M | 0% | High risk96 | Flagged0.063 |
| 25BE0034CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR / STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF CONCRETE ROAD ALONG L | Region II | Isabela 1st DEO | On-Going | ₱24.5M | 92% | High risk96 | Flagged0.011 |
| 25BE0094CONVERGENCE AND SPECIAL SUPPORT PROGRAM -SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF BRIDGE AT BARANGAY | Region II | Isabela 1st DEO | On-Going | ₱74.8M | 15% | High risk96 | Flagged0.043 |
| 25BE0011CONVERGENCE AND SPECIAL SUPPORT PROGRAM- SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR / STRATEGIC PUBLIC BUILDINGS/ FACILITIES- CONSTRUCTION OF CONCRETE ROAD ALONG MOZZO | Region II | Isabela 1st DEO | On-Going | ₱49M | 81% | High risk96 | Flagged0.014 |
| 25A00300SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - CONSTRUCTION OF DAQUIOAG-TABUCBUC BRIDGE, MARCOS, ILOCOS NORTE | Region I | Region I | On-Going | ₱187.3M | 14% | High risk96 | Flagged0.064 |
| 25BE0071CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUTURE PROGRAM (BIP)-BIP- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG ROAD, BARANGAY | Region II | Isabela 1st DEO | On-Going | ₱4.8M | 99% | High risk96 | Flagged0.004 |
| 25BG0165CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF RIVER FLOOD CONTROL STRUCTURE, CAGAYAN, PACKAGE 4, BARANGAY DAMMAO, GAMU, | Region II | Isabela 3rd DEO | On-Going | ₱89M | 0% | High risk95 | Flagged0.048 |
| 25BE0050CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/ FACILITIES- CONSTRUCTION OF SAN LORENZO BRIDGE (PHASE I) | Region II | Isabela 1st DEO | On-Going | ₱48M | 89% | High risk95 | Flagged0.011 |
| 25BE0070CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-SIPAG-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF CONCRETE ROAD WITH SLOPE | Region II | Isabela 1st DEO | On-Going | ₱14.2M | 65% | High risk95 | Flagged0.019 |
| 25B00063OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - CABAGAN-STA. MARIA BYPASS ROAD, PACKAGE 2, ISABELA | Region II | Region II | On-Going | ₱95M | 22% | High risk95 | Flagged0.024 |
| 25BE0032CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR / STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF CONCRETE ROAD WITH SL | Region II | Isabela 1st DEO | On-Going | ₱14.7M | 97% | High risk95 | Flagged0.007 |
| 25B00047OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: BRIDGE PROGRAM - WIDENING OF PERMANENT BRIDGES - MALALAM BR. (B01121LZ) ALONG MAHARLIKA HIGHWAY | Region II | Region II | On-Going | ₱253.5M | 46% | High risk95 | Flagged0.038 |
| 25B00038OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - ALICIA-ANGADANAN-SAN GUILLERMO-CAUAYAN CITY-NAGUILIAN ALTERNATE ROUTE, SAN GUILLERMO, PACKAGE 1, ISABELA | Region II | Region II | On-Going | ₱115.5M | 60% | High risk95 | Flagged0.015 |
| 25B00028OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: BRIDGE PROGRAM - REPLACEMENT OF PERMANENT WEAK BRIDGE - MINANGA BR. (B01129LZ) ALONG MAHARLIKA HIGHWAY | Region II | Region II | On-Going | ₱241.2M | 11% | High risk95 | Flagged0.047 |
| 25BE0033CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - REHABILITATION OF ROAD, BARANGAY CONCEPCION, DELFIN ALBANO, ISABEL | Region II | Isabela 1st DEO | On-Going | ₱24.7M | 96% | High risk95 | Flagged0.010 |
| 25B00001OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - CABAGAN-STA. MARIA BYPASS ROAD | Region II | Region II | On-Going | ₱106.1M | 43% | High risk95 | Flagged0.020 |
| 25OC0129CONSTRUCTION OF REVETMENT ALONG PARAÑAQUE RIVER MOUTH (NORTH SIDE), PHASE 2,PARAÑAQUE CITY, METRO MANILA | National Capital Region | Metro Manila 2nd DEO | On-Going | ₱94.6M | 18% | High risk95 | Flagged0.036 |
| 25EH0041CONSTRUCTION OF SEAWALL ALONG POBLACION LEADING TO AMBULONG, PHASE 2, MAGDIWANG, ROMBLON | Region IV-B | Romblon DEO | On-Going | ₱71.3M | 96% | High risk94 | Flagged0.012 |
| 25BE0017ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM- CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE | Region II | Isabela 1st DEO | On-Going | ₱96.5M | 72% | High risk94 | Flagged0.005 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24P00083COMPLETION OF FOUR-STOREY LIBRARY BUILDING, BULANAO CAMPUS - PHASE 2 - KALINGA STATE UNIVERSITY, BULANAO, TABUK CITY, KALINGA | Cordillera Administrative Region | Cordillera Administrative Region | On-Going | ₱124.3M | 38% | High risk90 | Flagged0.081 |
| 25BE0132CONCRETING OF BRGY. BUBUG FMR (PHASE II), BRGY. BUBUG, STO. TOMAS, ISABELA | Region II | Isabela 1st DEO | On-Going | ₱19.3M | 9% | High risk87 | Flagged0.073 |
| 24BE0173ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE A | Region II | Isabela 1st DEO | On-Going | ₱101.3M | 85% | High risk90 | Flagged0.065 |
| 25A00300SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - CONSTRUCTION OF DAQUIOAG-TABUCBUC BRIDGE, MARCOS, ILOCOS NORTE | Region I | Region I | On-Going | ₱187.3M | 14% | High risk96 | Flagged0.064 |
| 25A00519SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), REHABILITATION OF FLOOD CONTROL STRUCTURE, DRAINAGE STRUCTURE AND SMALL WATER IMPOUNDING PROJECT (SWIP), BARANGAY 20, SAN PABLO, SAN NICOLAS, ILOCOS NORTE | Region I | Region I | On-Going | ₱140.4M | 0% | High risk96 | Flagged0.063 |
| 25BE0136CONCRETING OF BRGY. MALASIN-BRGY. FELY FMR, BRGY. MALASIN AND BRGY. FELY, MACONACON, ISABELA | Region II | Isabela 1st DEO | On-Going | ₱14.5M | 34% | High risk87 | Flagged0.062 |
| 25BE0084CONCRETING OF BUBUG FMR (PHASE I), BRGY. BUBUG, STO. TOMAS, ISABELA | Region II | Isabela 1st DEO | On-Going | ₱14.5M | 49% | High risk87 | Flagged0.058 |
| 24A00041CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, BAUANG - SAN FERNANDO - SAN JUAN BY-PASS ROAD (BAUANG SECTION), PACKAGE 3, LA UNION | Region I | Region I | On-Going | ₱270.2M | 36% | High risk80 | Flagged0.054 |
| 25BG0165CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF RIVER FLOOD CONTROL STRUCTURE, CAGAYAN, PACKAGE 4, BARANGAY DAMMAO, GAMU, | Region II | Isabela 3rd DEO | On-Going | ₱89M | 0% | High risk95 | Flagged0.048 |
| 25BE0134CONCRETING OF BRGY. BARUMBONG FMR, BRGY. BARUMBONG, STO. TOMAS, ISABELA | Region II | Isabela 1st DEO | On-Going | ₱14.5M | 6% | High risk62 | Flagged0.047 |
| 25B00028OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: BRIDGE PROGRAM - REPLACEMENT OF PERMANENT WEAK BRIDGE - MINANGA BR. (B01129LZ) ALONG MAHARLIKA HIGHWAY | Region II | Region II | On-Going | ₱241.2M | 11% | High risk95 | Flagged0.047 |
| 22B00006OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT PROGRAM: CONSTRUCTION OF MISSING LINKS/NEW ROADS: NAGUILIAN-BENITO SOLIVEN-SAN MARIANO-DIVILACAN-MACONACON-PALANAN ROAD (DISABUNGAN BR.), ISABELA | Region II | Region II | On-Going | ₱101M | 47% | High risk68 | Flagged0.046 |
| 25BE0094CONVERGENCE AND SPECIAL SUPPORT PROGRAM -SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF BRIDGE AT BARANGAY | Region II | Isabela 1st DEO | On-Going | ₱74.8M | 15% | High risk96 | Flagged0.043 |
| 25B00047OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: BRIDGE PROGRAM - WIDENING OF PERMANENT BRIDGES - MALALAM BR. (B01121LZ) ALONG MAHARLIKA HIGHWAY | Region II | Region II | On-Going | ₱253.5M | 46% | High risk95 | Flagged0.038 |
| 24BE0175ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD MITIGATION STRUCTUR | Region II | Isabela 1st DEO | On-Going | ₱101.3M | 73% | High risk70 | Flagged0.037 |
| 25OC0129CONSTRUCTION OF REVETMENT ALONG PARAÑAQUE RIVER MOUTH (NORTH SIDE), PHASE 2,PARAÑAQUE CITY, METRO MANILA | National Capital Region | Metro Manila 2nd DEO | On-Going | ₱94.6M | 18% | High risk95 | Flagged0.036 |
| 22B00009OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: BRIDGE PROGRAM - WIDENING OF PERMANENT BRIDGES - SN. PABLO BRIDGE (B01137LZ) ALONG DAANG MAHARLIKA (LZ) | Region II | Region II | On-Going | ₱181.4M | 50% | High risk68 | Flagged0.035 |
| 24PL0069ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - TERTIARY ROADS - NAMBARAN-ISABELA RD - K0509 + (-903) - K0520 + 865 | Cordillera Administrative Region | Lower Kalinga DEO | On-Going | ₱193M | 88% | High risk80 | Flagged0.033 |
| 24B00100CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ILAGAN-DIVILACAN ROAD, IL | Region II | Region II | On-Going | ₱192.8M | 92% | High risk83 | Flagged0.030 |
| 25BE0021CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR STRATEGIC PUBLIC BUILDINGS/ FACILITIES-REHABILITATION OF POBLACION 1-DIVISORIA | Region II | Isabela 1st DEO | On-Going | ₱112.9M | 71% | High risk97 | Flagged0.030 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 726 | 25BE0009ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - TERTIARY ROADS - JCT. NATIONAL-STA. VICTORIA RD - K0410+(-1894)-K0410+(-1089), CITY OF ILAGAN, ISABELA | Region II | Isabela 1st DEO | Completed | ₱33M | 100% | Medium risk45 | —-0.076 |
| 727 | 19BE0142REPAIR AND MAINTENANCE OF PARAGU FLOOD CONTROL STRUCTURE PARAGU, TUMAUINI, ISABELA | Region II | Isabela 1st DEO | Completed | ₱18.3M | 100% | Medium risk45 | —-0.017 |
| 728 | 23BH0183BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ECHAGUE - DINAPIGUE ALTERNATE ROUTE, PACKAGE 1, ECHAGUE, ISABELA | Region II | Isabela 4th DEO | On-Going | ₱40.7M | 100% | Medium risk45 | —-0.042 |
| 729 | 18BG0066NETWORK DEVELOPMENT - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - CONSTRUCTION OF CONCRETE ROAD - ALICIA - ANGADANAN - SAN GUILLERMO - CAUAYAN CITY - NAGUILIAN ALTERNATE ROUTE, INC. ROW, ISABELA, ALICIA-ANGADANAN, ISABELA | Region II | Isabela 3rd DEO | Completed | ₱41.9M | 100% | Medium risk45 | —-0.082 |
| 730 | 19BG0009NETWORK DEVELOPMENT - CONSTRUCTION OF BYPASS AND DIVERSION ROADS - ALICIA-ANGADANAN-SAN GUILLERMO-CAUAYAN CITY-NAGUILIAN ALTERNATE ROUTE, ANGADANAN, ISABELA | Region II | Isabela 3rd DEO | Completed | ₱41.2M | 100% | Medium risk45 | —-0.082 |
| 731 | 18BG0002ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS - DAANG MAHARLIKA (LZ) K0345 + 055 - K0346 + 283, K0350 + 238 - K0350 + 717, ALICIA, ISABELA | Region II | Isabela 3rd DEO | Completed | ₱28.6M | 100% | Medium risk45 | —-0.084 |
| 732 | 23BH0257REHABILITATION/ REPAIR/ MAINTENANCE OF DAMAGED APPROACH AND ABUTMENT PROTECTION OF TAGARAN BRIDGE, TAGARAN, CAUAYAN CITY, ISABELA | Region II | Isabela 4th DEO | On-Going | ₱29.5M | 28% | Medium risk45 | —-0.023 |
| 733 | 22BH0051SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROAD AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDING/ FACILITIES - REHABILITATION OF ROAD, SAN MIGUEL, ECHAGUE, ISABELA | Region II | Isabela 4th DEO | Completed | ₱39.1M | 100% | Medium risk45 | —-0.080 |
| 734 | 21B00021ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT PROGRAM: CONSTRUCTION OF BY-PASS AND DIVERSION ROADS-ILAGAN CITY BYPASS ROAD; STA. 3+322.50-STA. 004+530.00 | Region II | Region II | On-Going | ₱33.5M | 65% | Medium risk45 | —-0.014 |
| 735 | 21BE0061CONSTRUCTION OF ILAGAN-DIVILACAN ROAD, ISABELA, ILAGAN-DIVILACAN, ISABELA | Region II | Isabela 1st DEO | Completed | ₱46.5M | 100% | Medium risk45 | —-0.080 |
| 736 | 20BE0017NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - PRIMARY ROADS: DAANG MAHARLIKA (LZ) CITY OF ILAGAN AND TUMAUINI, ISABELA KO394+(-580) - KO394+(-357), KO394+880 - KO395+931, KO398+383.20 - KO398+582, KO401+485 - KO401+820, KO425+249.60-KO425+294 | Region II | Isabela 1st DEO | Completed | ₱29.9M | 100% | Medium risk45 | —-0.082 |
| 737 | 20BD0080LOCAL PROGRAM -LOCAL INFRASTRUCTURE PROGRAM, LOCAL ROADS AND BRIDGES, LOCAL ROADS, CONCRETING OF ALABUG-ALABIAO LOCAL ROAD, TUAO, CAGAYAN | Region II | Cagayan 3rd DEO | Completed | ₱19.2M | 100% | Medium risk45 | —-0.081 |
| 738 | 21BG0025OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF BANK PROTECTION ALONG PINACANAUAN RIVER, BRGY. CASALA, SAN MARIANO, ISABELA | Region II | Isabela 3rd DEO | Completed | ₱46.6M | 100% | Medium risk45 | —-0.067 |
| 739 | 21BE0059CONCRETING OF ROAD, BRGY. CALAOCAN DELFIN ALBANO, ISABELA | Region II | Isabela 1st DEO | Completed | ₱14.3M | 100% | Medium risk45 | —-0.083 |
| 740 | 19BF0094OPENING OF ROAD, BRGY. UEG-PANNINAN TO BRGY. LIBERTAD, SAN MARIANO, ISABELA | Region II | Isabela 2nd DEO | Completed | ₱28.8M | 100% | Medium risk44 | —-0.077 |
| 741 | 20BH0102CONCRETING OF SAN JUAN DALENAT-GASUK ROAD | Region II | Isabela 4th DEO | Completed | ₱34.5M | 100% | Medium risk44 | —-0.085 |
| 742 | 18PD0056FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS: CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES/DRAINAGE SYSTEM ALONG BGH FLYOVER TO ATHLETIC BOWL TO ROSE GARDEN, BURNHAM PARK, BAGUIO CITY | Cordillera Administrative Region | Baguio City DEO | Completed | ₱38.3M | 100% | Medium risk44 | —-0.065 |
| 743 | 23BE0083REHABILITATION OF ROAD ALONG BRGY. VILLALUS - BRGY. ANDARAYAN, DELFIN ALBANO, ISABELA | Region II | Isabela 1st DEO | Completed | ₱24.5M | 100% | Medium risk44 | —-0.083 |
| 744 | 23BE0093CONSTRUCTION OF ROAD AT BARANGAY APLAYA, MACONACON, ISABELA | Region II | Isabela 1st DEO | Completed | ₱9.9M | 100% | Medium risk44 | —-0.083 |
| 745 | 20BD0038CONVERGENCE AND SPECIAL SUPPORT PROGRAM-CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURIST DESTINATIONS - NRJ LEADING TO HISTORICAL SITE (FIRST CHURCH CORNERSTONE) TUAO, CAGAYAN | Region II | Cagayan 3rd DEO | Completed | ₱14.3M | 100% | Medium risk44 | —-0.082 |
| 746 | 24B00156DEPARTMENT OF HEALTH - FY 2024 HEALTH FACILITIES ENHANCEMENT PROGRAM (HFEP): RURAL HEALTH UNITS (RURAL HEALTH UNIT) - CONSTRUCTION OF NEW SUPER HEALTH CENTER/RURAL HEALTH UNIT - DIVILACAN SUPER HEALTH CENTER | Region II | Region II | On-Going | ₱11.9M | 53% | Medium risk44 | Flagged0.008 |
| 747 | 24BE0079CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONSTRUCTION OF SAN JUAN-RAGAN SUR ROAD, | Region II | Isabela 1st DEO | On-Going | ₱14.7M | 100% | Medium risk44 | —-0.053 |
| 748 | 23BE0033ASSET PRESERVATION - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED ROADS - TERTIARY ROADS - JCT. DELFIN ALBANO RD - KO428+000-KO428+723 DELFIN ALBANO, ISABELA | Region II | Isabela 1st DEO | Completed | ₱17.7M | 100% | Medium risk44 | —-0.082 |
| 749 | 22AC0070CONCRETING OF BRGY. PAING FMR, BRGY. PAING, BANTAY, ILOCOS SUR | Region I | Ilocos Sur 1st DEO | Completed | ₱29.9M | 100% | Medium risk44 | —-0.023 |
| 750 | 18BC0090CONSTRUCTION OF BY-PASS AND DIVERSION ROADS-ALLACAPAN BYPASS ROAD AT ALLACAPAN, CAGAYAN | Region II | Cagayan 2nd DEO | Completed | ₱38M | 100% | Medium risk44 | —-0.074 |