Contractor dossier
936 projects on file, including joint ventures this contractor is part of.
Total projects
936
Total budget
₱59.2B
Average progress
91.5%
Completion rate
75.7%
Average risk score
54.0
Medium risk on average, out of 100
Flagged as unusual
90
9.6% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region II | 698 | ₱36.5B | 52.5 | 74 | 93.2% |
| Region I | 64 | ₱5.9B | 63.9 | 4 | 92.8% |
| Cordillera Administrative Region | 62 | ₱5.4B | 56.9 | 4 | 94.7% |
| Region III | 36 | ₱3.3B | 47.2 | 0 | 96.6% |
| Region IV-B | 30 | ₱3.2B | 55.5 | 3 | 65.7% |
| Region IV-A | 16 | ₱1.7B | 60.4 | 0 | 77.1% |
| National Capital Region | 13 | ₱1B | 65.6 | 2 | 55.7% |
| Region VII | 6 | ₱655.8M | 65.1 | 1 | 86.3% |
| Region V | 5 | ₱765.6M | 64.0 | 1 | 58.5% |
| Region VIII | 3 | ₱633.9M | 65.1 | 0 | 100.0% |
| Negros Island Region | 2 | ₱87.6M | 46.5 | 0 | 100.0% |
| Region XII | 1 | ₱73.8M | 77.1 | 1 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 378 | ₱23.6B | 51.4 | 13 | 91.7% |
| Flood Control and Drainage | 243 | ₱17.1B | 53.8 | 7 | 95.9% |
| Buildings and Facilities | 120 | ₱4.2B | 46.7 | 2 | 96.7% |
| Bridges | 117 | ₱8.7B | 53.7 | 27 | 88.3% |
| OTHER | 25 | ₱2.2B | 79.6 | 13 | 81.6% |
| GAA 2025 SSP | 20 | ₱1.1B | 95.0 | 20 | 57.4% |
| Water Provision and Storage | 17 | ₱586.6M | 54.3 | 0 | 99.0% |
| GAA 2025 OO-1 | 7 | ₱960.1M | 92.9 | 6 | 45.5% |
| GAA 2025 OO-2 | 5 | ₱400.6M | 91.4 | 2 | 74.5% |
| Bridges, Roads | 4 | ₱370.8M | 59.5 | 0 | 52.7% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25BE0021CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR STRATEGIC PUBLIC BUILDINGS/ FACILITIES-REHABILITATION OF POBLACION 1-DIVISORIA | Region II | Isabela 1st DEO | On-Going | ₱112.9M | 71% | High risk97 | Flagged0.030 |
| 25A00519SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), REHABILITATION OF FLOOD CONTROL STRUCTURE, DRAINAGE STRUCTURE AND SMALL WATER IMPOUNDING PROJECT (SWIP), BARANGAY 20, SAN PABLO, SAN NICOLAS, ILOCOS NORTE | Region I | Region I | On-Going | ₱140.4M | 0% | High risk96 | Flagged0.063 |
| 25BE0034CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR / STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF CONCRETE ROAD ALONG L | Region II | Isabela 1st DEO | On-Going | ₱24.5M | 92% | High risk96 | Flagged0.011 |
| 25BE0094CONVERGENCE AND SPECIAL SUPPORT PROGRAM -SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF BRIDGE AT BARANGAY | Region II | Isabela 1st DEO | On-Going | ₱74.8M | 15% | High risk96 | Flagged0.043 |
| 25BE0011CONVERGENCE AND SPECIAL SUPPORT PROGRAM- SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR / STRATEGIC PUBLIC BUILDINGS/ FACILITIES- CONSTRUCTION OF CONCRETE ROAD ALONG MOZZO | Region II | Isabela 1st DEO | On-Going | ₱49M | 81% | High risk96 | Flagged0.014 |
| 25A00300SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - CONSTRUCTION OF DAQUIOAG-TABUCBUC BRIDGE, MARCOS, ILOCOS NORTE | Region I | Region I | On-Going | ₱187.3M | 14% | High risk96 | Flagged0.064 |
| 25BE0071CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUTURE PROGRAM (BIP)-BIP- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG ROAD, BARANGAY | Region II | Isabela 1st DEO | On-Going | ₱4.8M | 99% | High risk96 | Flagged0.004 |
| 25BG0165CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF RIVER FLOOD CONTROL STRUCTURE, CAGAYAN, PACKAGE 4, BARANGAY DAMMAO, GAMU, | Region II | Isabela 3rd DEO | On-Going | ₱89M | 0% | High risk95 | Flagged0.048 |
| 25BE0050CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/ FACILITIES- CONSTRUCTION OF SAN LORENZO BRIDGE (PHASE I) | Region II | Isabela 1st DEO | On-Going | ₱48M | 89% | High risk95 | Flagged0.011 |
| 25BE0070CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-SIPAG-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF CONCRETE ROAD WITH SLOPE | Region II | Isabela 1st DEO | On-Going | ₱14.2M | 65% | High risk95 | Flagged0.019 |
| 25B00063OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - CABAGAN-STA. MARIA BYPASS ROAD, PACKAGE 2, ISABELA | Region II | Region II | On-Going | ₱95M | 22% | High risk95 | Flagged0.024 |
| 25BE0032CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR / STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF CONCRETE ROAD WITH SL | Region II | Isabela 1st DEO | On-Going | ₱14.7M | 97% | High risk95 | Flagged0.007 |
| 25B00047OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: BRIDGE PROGRAM - WIDENING OF PERMANENT BRIDGES - MALALAM BR. (B01121LZ) ALONG MAHARLIKA HIGHWAY | Region II | Region II | On-Going | ₱253.5M | 46% | High risk95 | Flagged0.038 |
| 25B00038OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - ALICIA-ANGADANAN-SAN GUILLERMO-CAUAYAN CITY-NAGUILIAN ALTERNATE ROUTE, SAN GUILLERMO, PACKAGE 1, ISABELA | Region II | Region II | On-Going | ₱115.5M | 60% | High risk95 | Flagged0.015 |
| 25B00028OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: BRIDGE PROGRAM - REPLACEMENT OF PERMANENT WEAK BRIDGE - MINANGA BR. (B01129LZ) ALONG MAHARLIKA HIGHWAY | Region II | Region II | On-Going | ₱241.2M | 11% | High risk95 | Flagged0.047 |
| 25BE0033CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - REHABILITATION OF ROAD, BARANGAY CONCEPCION, DELFIN ALBANO, ISABEL | Region II | Isabela 1st DEO | On-Going | ₱24.7M | 96% | High risk95 | Flagged0.010 |
| 25B00001OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - CABAGAN-STA. MARIA BYPASS ROAD | Region II | Region II | On-Going | ₱106.1M | 43% | High risk95 | Flagged0.020 |
| 25OC0129CONSTRUCTION OF REVETMENT ALONG PARAÑAQUE RIVER MOUTH (NORTH SIDE), PHASE 2,PARAÑAQUE CITY, METRO MANILA | National Capital Region | Metro Manila 2nd DEO | On-Going | ₱94.6M | 18% | High risk95 | Flagged0.036 |
| 25EH0041CONSTRUCTION OF SEAWALL ALONG POBLACION LEADING TO AMBULONG, PHASE 2, MAGDIWANG, ROMBLON | Region IV-B | Romblon DEO | On-Going | ₱71.3M | 96% | High risk94 | Flagged0.012 |
| 25BE0017ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM- CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE | Region II | Isabela 1st DEO | On-Going | ₱96.5M | 72% | High risk94 | Flagged0.005 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24P00083COMPLETION OF FOUR-STOREY LIBRARY BUILDING, BULANAO CAMPUS - PHASE 2 - KALINGA STATE UNIVERSITY, BULANAO, TABUK CITY, KALINGA | Cordillera Administrative Region | Cordillera Administrative Region | On-Going | ₱124.3M | 38% | High risk90 | Flagged0.081 |
| 25BE0132CONCRETING OF BRGY. BUBUG FMR (PHASE II), BRGY. BUBUG, STO. TOMAS, ISABELA | Region II | Isabela 1st DEO | On-Going | ₱19.3M | 9% | High risk87 | Flagged0.073 |
| 24BE0173ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE A | Region II | Isabela 1st DEO | On-Going | ₱101.3M | 85% | High risk90 | Flagged0.065 |
| 25A00300SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - CONSTRUCTION OF DAQUIOAG-TABUCBUC BRIDGE, MARCOS, ILOCOS NORTE | Region I | Region I | On-Going | ₱187.3M | 14% | High risk96 | Flagged0.064 |
| 25A00519SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), REHABILITATION OF FLOOD CONTROL STRUCTURE, DRAINAGE STRUCTURE AND SMALL WATER IMPOUNDING PROJECT (SWIP), BARANGAY 20, SAN PABLO, SAN NICOLAS, ILOCOS NORTE | Region I | Region I | On-Going | ₱140.4M | 0% | High risk96 | Flagged0.063 |
| 25BE0136CONCRETING OF BRGY. MALASIN-BRGY. FELY FMR, BRGY. MALASIN AND BRGY. FELY, MACONACON, ISABELA | Region II | Isabela 1st DEO | On-Going | ₱14.5M | 34% | High risk87 | Flagged0.062 |
| 25BE0084CONCRETING OF BUBUG FMR (PHASE I), BRGY. BUBUG, STO. TOMAS, ISABELA | Region II | Isabela 1st DEO | On-Going | ₱14.5M | 49% | High risk87 | Flagged0.058 |
| 24A00041CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, BAUANG - SAN FERNANDO - SAN JUAN BY-PASS ROAD (BAUANG SECTION), PACKAGE 3, LA UNION | Region I | Region I | On-Going | ₱270.2M | 36% | High risk80 | Flagged0.054 |
| 25BG0165CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF RIVER FLOOD CONTROL STRUCTURE, CAGAYAN, PACKAGE 4, BARANGAY DAMMAO, GAMU, | Region II | Isabela 3rd DEO | On-Going | ₱89M | 0% | High risk95 | Flagged0.048 |
| 25BE0134CONCRETING OF BRGY. BARUMBONG FMR, BRGY. BARUMBONG, STO. TOMAS, ISABELA | Region II | Isabela 1st DEO | On-Going | ₱14.5M | 6% | High risk62 | Flagged0.047 |
| 25B00028OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: BRIDGE PROGRAM - REPLACEMENT OF PERMANENT WEAK BRIDGE - MINANGA BR. (B01129LZ) ALONG MAHARLIKA HIGHWAY | Region II | Region II | On-Going | ₱241.2M | 11% | High risk95 | Flagged0.047 |
| 22B00006OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT PROGRAM: CONSTRUCTION OF MISSING LINKS/NEW ROADS: NAGUILIAN-BENITO SOLIVEN-SAN MARIANO-DIVILACAN-MACONACON-PALANAN ROAD (DISABUNGAN BR.), ISABELA | Region II | Region II | On-Going | ₱101M | 47% | High risk68 | Flagged0.046 |
| 25BE0094CONVERGENCE AND SPECIAL SUPPORT PROGRAM -SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF BRIDGE AT BARANGAY | Region II | Isabela 1st DEO | On-Going | ₱74.8M | 15% | High risk96 | Flagged0.043 |
| 25B00047OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: BRIDGE PROGRAM - WIDENING OF PERMANENT BRIDGES - MALALAM BR. (B01121LZ) ALONG MAHARLIKA HIGHWAY | Region II | Region II | On-Going | ₱253.5M | 46% | High risk95 | Flagged0.038 |
| 24BE0175ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD MITIGATION STRUCTUR | Region II | Isabela 1st DEO | On-Going | ₱101.3M | 73% | High risk70 | Flagged0.037 |
| 25OC0129CONSTRUCTION OF REVETMENT ALONG PARAÑAQUE RIVER MOUTH (NORTH SIDE), PHASE 2,PARAÑAQUE CITY, METRO MANILA | National Capital Region | Metro Manila 2nd DEO | On-Going | ₱94.6M | 18% | High risk95 | Flagged0.036 |
| 22B00009OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: BRIDGE PROGRAM - WIDENING OF PERMANENT BRIDGES - SN. PABLO BRIDGE (B01137LZ) ALONG DAANG MAHARLIKA (LZ) | Region II | Region II | On-Going | ₱181.4M | 50% | High risk68 | Flagged0.035 |
| 24PL0069ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - TERTIARY ROADS - NAMBARAN-ISABELA RD - K0509 + (-903) - K0520 + 865 | Cordillera Administrative Region | Lower Kalinga DEO | On-Going | ₱193M | 88% | High risk80 | Flagged0.033 |
| 24B00100CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ILAGAN-DIVILACAN ROAD, IL | Region II | Region II | On-Going | ₱192.8M | 92% | High risk83 | Flagged0.030 |
| 25BE0021CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR STRATEGIC PUBLIC BUILDINGS/ FACILITIES-REHABILITATION OF POBLACION 1-DIVISORIA | Region II | Isabela 1st DEO | On-Going | ₱112.9M | 71% | High risk97 | Flagged0.030 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 101 | 22B00046OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - CONSTRUCTION OF MISSING LINKS/NEW ROADS - TUGUEGARAO CITY BOULEVARD (PINACANAUAN BRIDGE 2 AND APPROACHES) | Region II | Region II | Completed | ₱141.8M | 100% | High risk68 | —-0.016 |
| 102 | 21AA0008REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - PRIMARY ROADS - MANILA NORTH RD - K0578+850 - K0578+900, PAGUDPUD, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | Completed | ₱73.2M | 100% | High risk68 | —-0.072 |
| 103 | 22B00006OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT PROGRAM: CONSTRUCTION OF MISSING LINKS/NEW ROADS: NAGUILIAN-BENITO SOLIVEN-SAN MARIANO-DIVILACAN-MACONACON-PALANAN ROAD (DISABUNGAN BR.), ISABELA | Region II | Region II | On-Going | ₱101M | 47% | High risk68 | Flagged0.046 |
| 104 | 24B00016OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT: CONSTRUCTION OF MISSING LINKS/ NEW ROADS - JCT CAGAYAN VALLEY ROAD - SAMPAGUITA-WARAT-LA SUERTE-CATARAUAN-AFUSING RD (AMULUNG BRIDGE AND APPROACHES), CAGAYAN | Region II | Region II | On-Going | ₱140.9M | 91% | High risk68 | Flagged0.001 |
| 105 | 23B00022OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: BRIDGE PROGRAM: WIDENING OF PERMANENT BRIDGES - SAN PABLO BR. (B01137LZ) | Region II | Region II | On-Going | ₱144.6M | 85% | High risk68 | Flagged0.013 |
| 106 | 21AA0088REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - PRIMARY ROADS - MANILA NORTH RD - K0578+700 - K0578+729, PAGUDPUD, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | Completed | ₱49M | 100% | High risk68 | —-0.078 |
| 107 | 22B00009OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: BRIDGE PROGRAM - WIDENING OF PERMANENT BRIDGES - SN. PABLO BRIDGE (B01137LZ) ALONG DAANG MAHARLIKA (LZ) | Region II | Region II | On-Going | ₱181.4M | 50% | High risk68 | Flagged0.035 |
| 108 | 21B00060ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT PROGRAM: CONSTRUCTION OF MISSING LINKS/NEW ROADS JCT. CAGAYAN VALLEY ROAD-SAMPAGUITA-WARAT-LA SUERTE-CATARAUAN-AFUSING ROAD (AMULUNG BRIDGE AND APPROACHES), CAGAY | Region II | Region II | Completed | ₱202.9M | 100% | High risk68 | —-0.005 |
| 109 | 24A00484PREVENTIVE MAINTENANCE - PRIMARY ROADS, MANILA NORTH RD - K0570 + 726 -K0571 + 1000, K0572 + 179 - K0573 + 300 | Region I | Region I | On-Going | ₱43.4M | 75% | High risk68 | —-0.038 |
| 110 | 23P00004CONSTRUCTION OF MEGA DIKE PROJECT ALONG CHICO RIVER (LEFT BANK), TABUK CITY, KALINGA | Cordillera Administrative Region | Cordillera Administrative Region | Completed | ₱144.8M | 100% | High risk67 | —-0.038 |
| 111 | 24B00013OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS: FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF TUGUEGARAO CIRCUMFERENTIAL DIKE ROAD, TUGUEGARA | Region II | Region II | On-Going | ₱183M | 100% | High risk67 | —-0.007 |
| 112 | 23B00032OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT PROGRAM: CONSTRUCTION OF MISSING LINKS/NEW ROADS: JCT. CAGAYAN VALLEY ROAD - SAMPAGUITA-WARAT-LA SUERTE-CATARAUAN- AFUSING ROAD (AMULUNG BRIDGE AND APPROACHES), CAGAYAN | Region II | Region II | On-Going | ₱134.1M | 99% | High risk67 | Flagged0.006 |
| 113 | 25OF0133CONSTRUCTION OF FLOOD MITIGATING STRUCTURE AT AFP ROAD RD. BRGY. HOLY SPIRIT, QUEZON CITY | National Capital Region | Quezon City 1st DEO | On-Going | ₱97M | 5% | High risk67 | —-0.020 |
| 114 | 25OF0159CONSTRUCTION OF FLOOD MITIGATING STRUCTURE AT AIRFORCE ROAD RD. BRGY. HOLY SPIRIT, QUEZON CITY | National Capital Region | Quezon City 1st DEO | On-Going | ₱97M | 5% | High risk67 | —-0.020 |
| 115 | 21B00004ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: BRIDGE PROGRAM - WIDENING OF PERMANENT BRIDGES - SN. PABLO BRIDGE (B01137LZ) ALONG DAANG MAHARLIKA | Region II | Region II | On-Going | ₱131M | 81% | High risk67 | Flagged0.022 |
| 116 | 20BC0007REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS-PRIMARY ROADS-MANILA NORTH ROAD-K0604+663-K0605+305, BRGY. KILKILING, CLAVERIA, CAGAYAN | Region II | Cagayan 2nd DEO | Completed | ₱36.4M | 100% | High risk67 | —-0.011 |
| 117 | 23B00057OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS: FLOOD MANAGEMENT PROGRAM: CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF SLOPE PROTECTION WORKS FOR CAGAYAN RIVER BASIN, CAGAYAN RIVER AT STA. MARIA, I | Region II | Region II | Completed | ₱189.9M | 100% | High risk67 | —-0.033 |
| 118 | 17BE0096CONSTRUCTION OF WATER SUPPLY SYSTEM DIVILACAN, ISABELA | Region II | Isabela 1st DEO | Completed | ₱9.6M | 100% | High risk66 | —-0.030 |
| 119 | 17BE0087CONSTRUCTION OF WATER SUPPLY SYSTEM NAMNAMA, TUMAUINI, ISABELA | Region II | Isabela 1st DEO | Completed | ₱9.5M | 100% | High risk66 | —-0.029 |
| 120 | 17B00004MFO 1: NAT'L ROAD NETWORK SERVICES: ROAD UPGRADING (UNPAVED TO PAVED) BASED ON GRAVEL ROAD STRATEGIES, TRAFFIC BENCHMARK FOR UPGRADING TO PAVED ROAD STANDARD (HDM-4 PROJECT ANALYSIS) TERTIARY ROADS, SAMPAGUITA-WARAT-LA SWER | Region II | Cagayan 3rd DEO | Completed | ₱69M | 100% | High risk66 | —-0.040 |
| 121 | 17BE0088CONSTRUCTION OF WATER SUPPLY SYSTEM LIWANAG, TUMAUINI, ISABELA | Region II | Isabela 1st DEO | Completed | ₱9.4M | 100% | High risk66 | —-0.029 |
| 122 | 17P00077CONSTRUCTION/REHABILITATION OF ACCESSIBILITY FACILITIES FOR PHYSICALLY CHALLENGED PERSONS, REGIONAL OFFICES OF DICT-CAR, DOH-CAR, DSWD-CAR, NBI-CAR, BIR-CAR, TESDA-CAR, CHED-CAR, DEPED-CAR, CENRO-BAGUIO CITY, SPED-BAGUIO, SPED-BENGUET, BENGUET STATE UNIVE | Cordillera Administrative Region | Cordillera Administrative Region | Completed | ₱18.5M | 100% | High risk66 | —-0.056 |
| 123 | 17B00056PROPOSED CONSTRUCTION OF REGIONAL EVACUATION CENTER, SAN MATEO, TUMAUINI, ISABELA | Region II | Region II | Completed | ₱34.2M | 100% | High risk66 | —-0.049 |
| 124 | 17BE0032CONSTRUCTION OF MULTI-PURPOSE BUILDING(GYMNASIUM) TUMAUINI, ISABELA | Region II | Isabela 1st DEO | Completed | ₱9.5M | 100% | High risk66 | —-0.057 |
| 125 | 24HA0131CONSTRUCTION OF TAGBILARAN CITY WHARP PORT TO PICR SONGCULAN - TOTOLAN, DAUIS, BOHOL | Region VII | Bohol 1st DEO | On-Going | ₱144.5M | 62% | High risk66 | Flagged0.009 |