Contractor dossier
36 projects on file, including joint ventures this contractor is part of.
Total projects
36
Total budget
₱322.9M
Average progress
98.7%
Completion rate
97.2%
Average risk score
33.3
Medium risk on average, out of 100
Flagged as unusual
1
2.8% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region XI | 17 | ₱175.2M | 35.4 | 0 | 100.0% |
| Region X | 14 | ₱120.7M | 34.8 | 1 | 96.6% |
| Region XIII | 4 | ₱15.2M | 20.5 | 0 | 100.0% |
| Region XII | 1 | ₱11.8M | 26.2 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 26 | ₱206.2M | 28.4 | 0 | 100.0% |
| Roads | 5 | ₱66M | 40.8 | 0 | 100.0% |
| Bridges | 2 | ₱11.7M | 45.7 | 0 | 100.0% |
| Water Provision and Storage | 2 | ₱12.4M | 34.5 | 0 | 100.0% |
| GAA 2025 SSP | 1 | ₱26.6M | 94.8 | 1 | 52.1% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 26 | 19LA0199CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HALL) AT BRGY. BANAGBANAG, MONTEVISTA, COMPOSTELA VALLEY PROVINCE | Region XI | Davao de Oro 1st DEO | Completed | ₱2M | 100% | Low risk14 | —-0.088 |
| 27 | 19LA0170COMPLETION OF MULTI-PURPOSE BUILDING (PUBLIC MARKET) AT POBLACION, NEW BATAAN, COMPOSTELA VALLEY PROVINCE | Region XI | Davao de Oro 1st DEO | Completed | ₱2M | 100% | Low risk14 | —-0.084 |
| 28 | 20LA0007CONSTRUCTION OF MULTI-PURPOSE BUILDING (SENIOR CITIZEN BUILDING), BRGY. LAHI, MARAGUSAN COMPOSTELA VALLEY PROVINCE | Region XI | Davao de Oro 1st DEO | Completed | ₱2.2M | 100% | Low risk13 | —-0.053 |
| 29 | 21NI0053PACKAGE 21- CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY POBLACION, CITY OF BISLIG, SURIGAO DEL SUR- CONSTRUCTION OF MULTI-PURPOSE BUILDING, PUROK 7A, BARANGAY TABON, CITY OF BISLIG, SURIGAO DEL SUR | Region XIII | Surigao del Sur 2nd DEO | Completed | ₱3.5M | 100% | Low risk12 | —-0.071 |
| 30 | 20KB0153CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HALL), BRGY PUALAS, DON CARLOS, BUKIDNON | Region X | Bukidnon 2nd DEO | Completed | ₱2.5M | 100% | Low risk11 | —-0.094 |
| 31 | 21KB0137CONSTRUCTION OF TWO (2) STOREY MULTI-PURPOSE BUILDING IN BARANGAY KIBATANG, DON CARLOS, BUKIDNON | Region X | Bukidnon 2nd DEO | Completed | ₱1.9M | 100% | Low risk10 | —-0.093 |
| 32 | 19LA0234CONSTRUCTION OF MULTI-PURPOSE BUILDING (STAGE WITH CR) AT BRGY. FATIMA, NEW BATAAN, COMPOSTELA VALLEY PROVINCE | Region XI | Davao de Oro 1st DEO | Completed | ₱1.7M | 100% | Low risk10 | —-0.085 |
| 33 | 19KB0052CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BRGY KIPILAS, KITAOTAO, BUKIDNON | Region X | Bukidnon 2nd DEO | Completed | ₱1.9M | 100% | Low risk9 | —-0.092 |
| 34 | 20KB0176CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY MINSALAGAN, DON CARLOS, BUKIDNON | Region X | Bukidnon 2nd DEO | Completed | ₱1.9M | 100% | Low risk9 | —-0.094 |
| 35 | 20KB0131CONSTRUCTION OF MULTI-PURPOSE BUILDING (COMMUNITY CENTER), BRGY SAN NICOLAS, DON CARLOS, BUKIDNON | Region X | Bukidnon 2nd DEO | Completed | ₱999.8K | 100% | Low risk9 | —-0.094 |
| 36 | 22NH0003CONSTRUCTION (COMPLETION)) OF MULTI-PURPOSE BUILDING, BARANGAY DAYO-AN, TAGO, SURIGAO DEL SUR | Region XIII | Surigao del Sur 1st DEO | Completed | ₱1.9M | 100% | Low risk8 | —-0.074 |