Opening the dossier…
Opening the dossier…
Contractor dossier
4 projects on file, including joint ventures this contractor is part of.
Total projects
4
Total budget
₱54.5M
Average progress
87.7%
Completion rate
75.0%
Average risk score
37.2
Medium risk on average, out of 100
Flagged as unusual
0
0.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region XIII | 4 | ₱54.5M | 37.2 | 0 | 87.7% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 3 | ₱44.6M | 37.0 | 0 | 83.5% |
| Roads | 1 | ₱9.9M | 37.6 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
Nothing to report.
No high-risk projects here.
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
Nothing to report.
No flagged projects here.
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25NG0089CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. MAPAWA, SURIGAO CITY, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 2nd DEO | On-Going | ₱4.9M | 51% | Medium risk39 | —-0.043 |
| 2 | 22NF0093REHABILITATION OF ROAD IN BRGY. 3-POBLACION, GENERAL LUNA, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 1st DEO | Completed | ₱9.9M | 100% | Medium risk38 | —-0.079 |
| 3 | 21N00161CONSTRUCTION OF REGIONAL EVACUATION CENTER, LANUZA, SURIGAO DEL SUR | Region XIII | Region XIII | Completed | ₱34.7M | 100% | Medium risk36 | —-0.064 |
| 4 | 22NF0094CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. DAKU, GEN. LUNA, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 1st DEO | Completed | ₱4.9M | 100% | Medium risk35 | —-0.068 |